Private Project Payment Bonds and Pay if Paid in Virginia
January 05, 2017 —
Christopher G. Hill – Construction Law MusingsOne of the many items of construction law that has always been about as clear as mud has been the interaction between a contractual pay if paid clause and payment bond claims either under the Federal Miller Act or Virginia’s “Little Miller Act.” While properly drafted contractual “pay if paid” clauses are enforceable by their terms in Virginia, what has always been less clear is whether a bonding company can take advantage of such a clause when defending a payment bond claim. As always, these questions are very fact specific both under the Federal Act and the state statute. I wish that this post would answer this question, but alas, it will not.
A recent case from the City of Roanoke, Virginia looked at the interaction between a payment bond and a “condition precedent” pay if paid clause as it relates to a private project that is not subject to the Little Miller Act. In the case of IES Commercial, Inc v The Hanover Insurance Company, the Court examined a contractual clause between Thor Construction and IES Commercial in tandem with the bond language between Hanover Insurance Company and Thor as it related to a surprisingly familiar scenario. The general facts are these: IES performed, Thor demanded payment from the owner for the work that IES performed and the owner, for reasons that are left unstated in the opinion, refused to pay. IES sues Hanover pursuant to the payment bond and Hanover moves to dismiss the suit because Thor hadn’t been paid by the owner and therefore Hanover could take advantage of the pay if paid language.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Navigating the Construction Burrito: OCIP Policies in California’s Construction Defect Cases
November 16, 2023 —
Alexa Stephenson & Ivette Kincaid - Kahana FeldIn the early 2000’s, Owner-Controlled Insurance Programs (OCIP) or WRAPS, were traditionally used in large commercial projects of over $50 million in construction costs. As construction defect lawsuits became more prevalent, subcontractors found themselves unable to meet the insurance requirements of their contracts with developers and general contractors because they could not find insurance companies that were willing to insure the risk. This presented a problem for developers and general contractors and left them with no option but to look into new insurance products that would insure them and all subcontractors who worked on the project. OCIPs became in some instances the only insurance option for developers, general contractors, and subcontractors to build single-family or multi-family projects in California and other western states.
OCIPS or WRAPS, often likened to the layers of a savory burrito, offer both enticing benefits and potential pitfalls. Just as a burrito’s ingredients can harmonize or clash, OCIP policies can shape the outcome of legal battles, impacting contractors, developers, and insurers alike.
Pros – Savoring the OCIP Burrito:
1. Wrapped Protection: Much like a well-folded burrito envelops its contents, OCIP policies offer comprehensive coverage for construction projects. Developers, general contractors, and subcontractors find comfort in knowing that their liability risks are bundled into a single policy, ensuring all enrolled parties have coverage in the event of a claim.
Reprinted courtesy of
Alexa Stephenson, Kahana Feld and
Ivette Kincaid, Kahana Feld
Ms. Stephenson may be contacted at astephenson@kahanafeld.com
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Comply with your Insurance Policy's Conditions Precedent (Post-Loss Obligations)
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesI am of the opinion that if your property insurer requests a sworn proof of loss, furnish one with the assistance of counsel (preferably). Ignoring the insurer’s request or refusing to comply with insurer’s request is NOT value-added; it is simply placing you at a disadvantage based on the insurer’s argument that you, as the insured, materially breached the policy. I generally find no value having to confront this expected argument. Instead, I find value making an effort to comply with post-loss obligations including the insurer’s request to submit a sworn proof of loss. Working with counsel can help you comply with post-loss obligations (conditions precedent) while not weakening the value or merits of your claim.
By way of example, in Edwards v. Safepoint Ins. Co., 46 Fla. L. Weekly D1086a (Fla. 4th DCA 2021), the insured did not provide its property insurer with the requested sworn proof of loss. The insurer moved for summary judgment that the insured’s failure to submit the sworn proof of loss was a material breach of the policy that rendered the policy ineffective. The trial court agreed and granted summary judgment. The Fourth District Court of Appeal affirmed explaining “[a] total failure to comply with policy provisions made a prerequisite to suit under the policy may constitute a breach precluding recovery from the insurer as a matter of law. If, however, the insured cooperates to some degree or provides an explanation for its noncompliance, a fact question is presented for resolution by a jury.” Edwards, supra, quoting Haiman v. Federal Ins. Co., 798 So.2d 811, 812 (Fla. 4th DCA 2001).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Quick Note: Third-Party Can Bring Common Law Bad Faith Claim
July 01, 2019 —
David Adelstein - Florida Construction Legal UpdatesA third-party claimant may bring a common law bad faith claim against a defendant’s liability insurer. Mccullough v. Royal Caribbean Cruises, 2019 WL 2076192, *2 (S.D.Fla. 2019). “A bad faith claim may be brought by a third party absent an assignment from the [defendant] insured.” Id. This can only be done in the third-party bad faith context with the argument that the insurer’s “bad faith” conduct resulted in a judgment against the defendant-insured in excess of the policy limits. However, in any third-party bad faith claim (and, really, bad faith claim in general), coverage must first be determined under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court of Appeals Issues Decision Regarding Second-Tier Subcontractors and Pre-Lien Notice
February 06, 2023 —
Travis Colburn - Ahlers Cressman & SleightVelazquez Framing, LLC (“Velazquez”) v. Cascadia Homes, Inc. (“Cascadia”) is a Court of Appeals, Division 2 case where the primary issue on appeal was whether a second tier subcontractor was required to provide pre-lien notice under RCW 60.04 for its labor.
The defendant, Cascadia, was the general contractor that planned to build a home on property it owned in Lakewood, Washington.[1] High End Construction, LLC (“High End”), submitted a bid to Cascadia for framing work on the home. High End began work on Cascadia’s home, but later subcontracted with Velazquez to complete the framing work.[2] Velazquez did not submit a prelien notice for its work on Cascadia’s home, and Cascadia claimed it was unaware that High End subcontracted with Velazquez for framing at the project.
High End invoiced Cascadia and was paid for its work, but High End never paid Velazquez. Subsequently, Velazquez recorded a lien for both labor and materials, and later filed a complaint to foreclose its lien. Cascadia, due to the fact Velazquez did not provide it with prelien notice, moved for summary judgment, arguing prelien notice was required under RCW 60.04.031(1)[3] and the labor portion of a lien cannot be segregated where a subcontractor’s lien includes both labor and materials. Velazquez argued that no prelien notice was required under RCW 60.04.021[4] and RCW 60.04.031 and claimed that subcontractors can segregate the labor portion from the materials portion. The trial court granted Cascadia’s motion and ruled Velazquez did not fall within one of the exceptions for prelien notice in RCW 60.04.031(2), and therefore, could not enforce the lien. Velazquez appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
Predicting the Future of Texas’s Grid Is a Texas-Sized Challenge
June 27, 2022 —
Nathaniel Bullard - BloombergA little more than a year after a paralyzing winter freeze, the Texas power market just experienced the stress of extreme heat. Last week, power prices in Houston briefly jumped above $5,000 per megawatt-hour as high temperatures coincided with a number of generators being offline for maintenance.
Yet a few days earlier, power prices in west Texas had been negative $883 dollars per megawatt-hour, because at the time wind generation was abundant and demand was low.
“Dynamic” is one way to describe the price swings within the Electric Reliability Council of Texas (Ercot), the grid that provides the majority of the state’s power. “Jarring” or “terrifying” might be other words for it, particularly for those buying power in the spot market.
Read the court decisionRead the full story...Reprinted courtesy of
Nathaniel Bullard, Bloomberg
Concerns Over Unstable Tappan Zee Bridge Push Back Opening of New NY Bridge's Second Span
October 02, 2018 —
The New York Daily News - Engineering News-RecordSept. 08 --Big bridge, big scissors, big problems.
A day after an elaborate ribbon-cutting ceremony, the grand opening of the second span of the new Gov. Mario M. Cuomo bridge was postponed over concerns that the remains of the "destabilized" and "dangerous" Tappan Zee Bridge could collapse.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Colorado Hotel Neighbors Sue over Construction Plans
October 02, 2015 —
Beverley BevenFlorez-CDJ STAFFNeighbors of the Sky Hotel in Aspen, Colorado, filed suit against the owners “alleging that the construction project will impede access to their units and steal their airspace,” reported the Aspen Daily News Online.
The problem, the plaintiff suit alleges, is that the Sky’s plan would close the “east-west alley,” which is also used by the condo complex: “Owners, renters and guests mainly use the alley, which is configured for one-way traffic entering on Durant Avenue and exiting at Original Street, to access their condos in the Chaumont, says the 12-page complaint filed by local attorney Jody Edwards.”
The plaintiffs are demanding that the plan be voided or at least require the issues in the suit to be addressed. They are also seeking attorney and other costs.
Read the court decisionRead the full story...Reprinted courtesy of