No Coverage for Property Damage That is Limited to Work Completed by Subcontractor
April 25, 2012 —
Tred R. Eyerly - Insurance Law HawaiiThe issue before the 11th Circuit was whether, under Florida law, a general contractor had coverage for a property damage claim limited to the defective work performed by a subcontractor, and not affecting any other portion of the project. The court found no coverage in Amerisure Mut. Ins. Co. v. Auchter Co., 2012 U.S. App. LEXIS 5412 (11th Cir. March 15, 2012).
Amelia Island Company contracted with Auchter Company, a general contractor, for construction of an inn and conference room. Auchter subcontracted with Register Contracting Company to install the Inn’s roof. Pursuant to the Florida Building Code, installation of the roof required that it be able to withstand 110 m.p.h. winds.
Register completed installing the roof tiles in January 1998. Beginning in 2002, the tiles began dislodging from the roof. During the 2004 hurricane season, three hurricanes caused more tiles to come off the roof. Some of these tiles hit other tiles, cracking them.
In 2006, the parties went to arbitration over the costs of repairs for the roof.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Be a Good Neighbor: Protect Against Claims by an Adjacent Landowner During Construction
November 09, 2020 —
Joshua Levy & Madeleine Bailey - Construction ExecutiveThere’s nothing like working in an office while pilings are being pounded into the ground next door, leading to crashing sounds of pile driving and the attendant afternoon headaches. Fortunately, that’s often the extent of a neighboring project’s real inconvenience. In other cases, however, construction in close quarters can mark the beginning of costly and emotional disputes, which can escalate to costly legal battles during and after construction.
NUISANCE AND STRUCTURAL DAMAGE CLAIMS
Construction claims are often based on the concept of “nuisance,” or on structural damage to adjacent property. Nuisance claims are typically based on noise and dust from construction sites, while structural damage claims are based on direct physical damage caused by neighboring demolition, vibrations, excavation and dewatering. These types of claims can result in monetary damages for neighbor plaintiffs, loss of permits for contractors and reputational damage to the developer.
In one recent case in New York City, the developer faces up to $10 million in damages in a lawsuit with a neighboring property owner. The developer was conducting excavation, dewatering and installation of steel sheet piles, which the plaintiff alleges caused its five-story building to settle and shift, rendering doors inoperable and causing extensive cracking and separation of floors and ceilings from walls and supports. The plaintiff filed its complaint on Jan. 24, 2019, and the lawsuit is ongoing, exemplifying that construction claims such as these can be time consuming and costly (Complaint, 642 East 14th St. v. 644 E. 14th Realty [N.Y. Sup. Ct. January 24, 2019]).
Reprinted courtesy of
Joshua Levy & Madeleine Bailey, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Levy may be contacted at
joshua.levy@huschblackwell.com
County Officials Refute Resident’s Statement that Defect Repairs Improper
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFManatee County, Florida officials stated that “they are confident construction defects at the Willowbrook subdivision being fixed by the builder KB Home are being properly supervised and repaired,” according to the Bradenton Herald. However, a resident told the Bradenton Herald previously that “mold remediation isn’t being done properly and good wood was being installed over rotted wood.”
John Barnott, director of the Manatee County Building & Development Services Department told the Bradenton Herald that the county building chief has been at the site “every week, three or four times a week.” Carroll Dupre, the county building chief, stated that the development “looks real good.” The commissioner, Vanessa Baugh, stated that she had not received any complaints from Willowbrook residents and that “she was ‘not pleased with the implications of the article.’”
Read the court decisionRead the full story...Reprinted courtesy of
Brookfield Wins Disputed Bid to Manage Manhattan Marina
January 28, 2015 —
Martin Z Braun – Bloomberg(Bloomberg) -- Brookfield Property Partners won a bid to run a marina in New York’s Battery Park City neighborhood over the objections of residents backing a local businessman who operated the facility and a popular sailing club and school.
The state’s Battery Park City Authority voted Thursday to approve a 10-year agreement with Brookfield, which owns an adjacent 8 million-square-foot office and retail complex. Brookfield is bringing in billionaire real estate investor Andrew Farkas’s Island Global Yachting to manage the North Cove Marina.
Read the court decisionRead the full story...Reprinted courtesy of
Martin Z Braun, BloombergMr. Braun may be contacted at
mbraun6@bloomberg.net
What Should Business Owners Do If a Customer Won’t Pay
January 02, 2024 —
Scott L. Baker - Los Angeles Litigation BlogIt should be simple: you provide a service, and your customer pays you for that service. Unfortunately, it is not always so simple.
Not getting paid for your work can be one of the most frustrating issues, especially for small businesses. It also does not take much for money matters to
lead to larger disputes. So, what should small business owners do in these cases?
1. Start with a reminder notice
Most sources, including the
U.S. Chamber of Commerce, agree that business owners should not begin by escalating the situation. Take time to review and fully understand the circumstances of this individual case. Then, begin with resending the invoice or sending reminders to pay.
Read the court decisionRead the full story...Reprinted courtesy of
Scott L. Baker, Baker & AssociatesMr. Baker may be contacted at
slb@bakerslaw.com
Additional Insured Not Entitled to Coverage for Named Insured's Defective Work
September 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Court of Appeals for the Seventh Circuit determined there was no duty to defend or to indemnify the additional insured for the named insured's defective work. St. Paul Guardian Ins. Co., et al. v. Walsh Construction Co., 99 F. 4th 1035 (7th Cir. 2024).
The City of Chicago contracted with Walsh Construction Company to manage the construction of a canopy and curtain wall system at O'Hare International Airport. Walsh entered into a contract with Carlo Steel Corporation, which in turn subcontracted with LB Steel, LLC to fabricate and install steel columns to support the wall and canopy. LB Steel listed Walsh as an additional insured in its commercial general liability policies. LB Steel's insurers were St. Paul, Travelers, and Charter Oak Fire Insurance Company.
Several years into the project, the City discovered cracks in the welds of the steel columns and sued Walsh. Walsh, in turn, sued LB Steel under its subcontract. Walsh also asked LB Steel's insurers to defend it in the City's lawsuit, but they refused to do so. Walsh eventually secured a judgment against LB Steel, but LB Steel declared bankruptcy. Walsh then sued LB Steel's insurers to recover the costs of defending against the City's lawsuit and indemnification for any resulting losses.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Is the Event You Are Claiming as Unforeseeable Delay Really Unforeseeable?
September 26, 2022 —
David Adelstein - Florida Construction Legal UpdatesIs the item or event you are claiming as an unforeseeable, excusable delay really unforeseeable? This is not a trick question.
Just because your construction contract identifies items or events that constitute unforeseeable, excusable delay does not mean those items can be used as a blanket excuse or crutch for the contractor. That would be unfair.
For instance, it is not uncommon for a construction contract to list as unforeseeable, excusable delay the following events or items: “(i) acts of God or of the public enemy, (ii) act of the Government in either its sovereign or contractual capacity, (iii) acts of another Contractor in the performance of a contract with the Government, (iv) fires, (v) floods, (vi) epidemics, (vii) quarantine restrictions, (viii) strikes, (ix) freight embargoes, (x) unusually severe weather, or (xi) delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers.” See, e.g., F.A.R. 52.249-10(b)(1). While the itemization of excusable delay may be worded differently, the point is there may be a listing as to what items or events constitute excusable delay. An excusable delay would justify additional time and, potentially, compensation to the contractor.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Designing a Fair Standard of Care in Design Agreements
February 21, 2022 —
ConsensusDocsOne of the concerns faced by construction companies is now design liability. Design liability concerns are not limited to just design-build projects. It is a hot-button issue for builders because the line between an architect’s responsibility to create sufficient design documents and a builder’s responsibility to execute the means, methods, and techniques is increasingly blurry. Problems arise when owners, design professionals, and builders point fingers, rather than truly collaborate, and communicate. While construction technologies used to assemble complex systems within buildings are increasingly sophisticated, such sophistication is unfortunately not matched with increased information sharing and effective communication.
Another reason for growing design liability is unclear and inadequate specifications. Too often projects rush as well as shortchange design budgets. And some projects use hybrid prescriptive and performance specifications. This hybrid approach often confuses and obfuscates rather than clarifies design requirements.
Read the court decisionRead the full story...Reprinted courtesy of