140 Days Until The California Consumer Privacy Act Becomes Law - Why Aren't More Businesses Complying?
September 09, 2019 —
Kyle Janecek and Jeff Dennis – Newmeyer DillionCalifornia, for better or for worse, has a reputation as being a trendsetter, and has taken the lead in the United States by passing the "California Consumer Privacy Act," or "CCPA." This massive law has been on the books since 2018, but hasn't taken effect yet. However, the timeframe for businesses to be in compliance is rapidly diminishing. Currently, there are less than five months for businesses to (a) familiarize themselves with what the law requires; (b) determine how and if they are affected by the law; and (c) determine how to be in compliance with the law's demands. Right now, companies aren't making a rush to become CCPA compliant, but this is a mistake. Below are a few of the misconceptions that businesses have, as well as the realities.
MISCONCEPTION 1: It doesn't apply to my company.
For many businesses, it will apply. The baseline of the CCPA is: (1) does the business do anything with California residents (including employees); (2) is it for-profit; and (3) it either has $25 million annual revenue, "sells" 50,000 pieces of personal information or receives 50% or more of its revenue from personal information.
It does not matter if the business is in Nevada, Arizona, Texas or Delaware. So long as there is some connection to Californian residents, exists to make a profit, and otherwise satisfies either the profit, volume, or revenue percentage requirements, it applies. On that note, even if a business does not sell personal information, it does not mean it does not "sell" personal information under the law, as it includes any exchange of personal information for valuable consideration, such as the exchange of consumer data between companies, or the sale of information to a University for study.
MISCONCEPTION 2: The Federal Government will stop it.
One of the main reasons we have the CCPA is because the Federal Government has not acted on this issue. Furthermore, there is a high likelihood that any Federal law will not be substantially different from the CCPA, keeping the core principles in place. It's also unlikely that such a law will take effect and be passed in the remaining five months before the CCPA begins enforcement. Companies must accept that ideals of transparency, choice, consent and reasonable security as they relate to consumers' personal information are here to stay.
MISCONCEPTION 3: California is still changing the law, so I should wait.
California is still in the process of fine-tuning the CCPA, but this is no reason to wait. Fixes to questions arising regarding the CCPA have come out piecemeal, and continued changes, including expansions are likely. For example, employees were previously not addressed specifically within the CCPA, but are being addressed in the planned AB 25, excluding employees from some of the CCPA's protections. Conversely, there have also been planned provisions to expand on the protections and enforcement mechanisms of the CCPA, including a broad and expansive private right of action to permit individuals to sue for technical violations of the statute, like having to wait too long for a response to the demand, even if no actual damage is suffered. Again, the foundational requirements of the CCPA will not change via amendment – so companies should act now.
MISCONCEPTION 4: It's too expensive.
Actually no. Many of the basic actions are not cost-prohibitive, and are actions a business would want to do anyways: (a) Employee training to avoid data breaches and how to respond to user requests; (b) data mapping to quickly find, access, and arrange protections for consumer data; and (c) ensuring you have reasonable cyber security. This can even be turned into a competitive advantage, as consumers increasingly value companies that share their interests, including their privacy.
A compliance mistake could be extraordinarily costly. Currently, a violation for statutory violations of the CCPA can carry a penalty between $2,500 to $7,500 per individual violation. Furthermore, there is a private right of action with statutory damages of $100 to $750 per individual violation that could quickly balloon to exceed $5 million at a minimum, and invites class action/lawsuits for a data breach.
While this is true of almost every legal risk, an ounce of prevention is worth a pound of cure. The penalties on the higher end of the spectrum are for willful violations, and attempts to comply with the law can act to curb potential risks.
What Should I Do?
If you feel CCPA compliance is important to your business, and decide to prepare for the CCPA with us, our firm has created a 90-day CCPA compliance program where our team will collaborate with you to determine a scalable, practical, and reasonable way for you to meet your needs, without breaking the bank. Let us provide you a free initial consultation to see if our CCPA compliance program works for you.
Kyle Janecek is an associate in the firm's Privacy & Data Security practice, and supports the team in advising clients on cyber related matters, including policies and procedures that can protect their day-to-day operations. For more information on how Kyle can help, contact him at kyle.janecek@ndlf.com.
Jeff Dennis is the head of the firm's Privacy & Data Security practice. Jeff works with the firm's clients on cyber-related issues, including contractual and insurance opportunities to lessen their risk. For more information on how Jeff can help, contact him at jeff.dennis@ndlf.com.
About Newmeyer Dillion
For 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that align with the business objectives of clients in diverse industries. With over 70 attorneys working as an integrated team to represent clients in all aspects of business, employment, real estate, privacy & data security and insurance law, Newmeyer Dillion delivers tailored legal services to propel clients' business growth. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
Contractual Waiver of Consequential Damages
January 21, 2019 —
David Adelstein - Florida Construction Legal UpdatesContractual waivers of consequential damages are important, whether they are mutual or one-sided. I believe in specificity in that the types of consequential damages that are waived should be detailed in the waiver of consequential damages provision. Standard form construction agreements provide a good template of the types of consequential damages that the parties are agreeing to waive.
But, what if there is no specificity in the waiver of consequential damages provision? What if the provision just states that the parties mutually agree to waive consequential damages or that one party waives consequential-type damages against the other party? Let me tell you what would happen. The plaintiff will argue that the damages it seeks are general damages and are NOT waived by the waiver of consequential damages provision. The defendant, on the other hand, will argue that the damages are consequential in nature and, therefore, contractually waived. FOR THIS REASON, PARTIES NEED TO APPRECIATE WHAT DAMAGES ARE BEING WAIVED OR LIMITED, AND POTENTIALLY THOSE DAMAGES NOT BEING WAIVED OR LIMITED, WHEN AGREEING TO A WAIVER OF CONSEQUENTIAL DAMAGES PROVISION!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
State Farm to Build Multi-Use Complex in Dallas Area
December 30, 2013 —
CDJ STAFFState Farm in Insurance is building a new office complex which will have space for thousands of State Farm employees in the Dallas area, according to The Dallas Morning News. That’s not all the $1.5 billion development, CityLine, will include. The first phase of the complex will include three office towers, a shopping center, a hotel, and apartments. Opening is expected in early 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Cracked Girders Trigger Scrutiny of Salesforce Transit Center's Entire Structure
November 21, 2018 —
Nadine M. Post - Engineering News-RecordNov. 15, 2018 Update:
After calling on Nov. 8 for a “complete structural evaluation” of San Francisco's 1.2-million-sq-ft SalesForce Transit Center, following the discovery on Sept. 25 of significant, mid-span cracks in the bottom flanges of twin parallel girders spanning 80 ft over Fremont Street, the Transbay Joint Powers Authority now says the problems with girders are localized.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Court Clarifies Sequence in California’s SB800
December 20, 2012 —
CDJ STAFFAs California’s Right-To-Repair law, SB800, nears its ninth birthday, it has remained “largely untested in the legal system” as noted by Megan MacNee of Wood, Smith, Henning & Berman LLP on the site RealEstateRama. She writes that some homeowners have requested documents prior to filing a claim, which she describes as an attempt to “game the system,” and “analogous to requiring a party to litigation to comply with discovery before a complaint is filed.”
The court determined that homeowners may not request documents from the builder until they have actually filed a claim. The court noted that SB800 lacks any clear indication that homeowners may request documents before filing a claim (and also does not indicate that a builder would have to provide documents in these circumstances). The court concluded that the section that sets up the prelitigation procedures occurs before they section on documents discovery. “Because the document request is part of the prelitigation procedure, and the prelitigation procedure does not begin until the homeowner has served notice of a claim, it follows that there can be no prelitigation obligation to produce documents under section 912, subdivision (a) unless the homeowner has commenced the prelitigation procedure by serving notice of a claim.”
Read the court decisionRead the full story...Reprinted courtesy of
Disrupt a Broken Industry—The Industrial Construction Sandbox
November 23, 2020 —
Brian Sayre - Construction ExecutiveThe existing built environment structure—arguably—is antiquated and must be disrupted to meet the rapidly changing demands of the industry. The built environment struggles with labor shortages, addressing demand, sustainability needs, cost controls, affordability and efficiency gains. Even with the advancement of emerging technology trends, the construction industry still lags behind more technologically advanced verticals.
What’s missing? Something is needed beyond incremental change that will truly disrupt the industry, increase the value of other innovations and tackle industry challenges.
The answer is industrialized construction technology with offsite manufacturing as the cornerstone. Technology innovation becomes exponentially more valuable when placed in this context. Shadow Ventures, a venture capital firm focused on the built environment, set out to test these theories with verifiable research published this year in a report titled, “Disrupt a Broken Industry—The Industrial Construction Sandbox.”
Reprinted courtesy of
Brian Sayre, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Best Lawyers® Recognizes 49 White and Williams Attorneys
September 16, 2024 —
White and Williams LLPThirty-eight White and Williams lawyers were recognized in Best Lawyers in America® 2025. Inclusion in Best Lawyers® is based entirely on peer-review. The methodology is designed to capture, as accurately as possible, the consensus opinion of leading lawyers about the professional abilities of their colleagues within the same geographical area and legal practice area. Best Lawyers® employs a sophisticated, conscientious, rational, and transparent survey process designed to elicit meaningful and substantive evaluations of quality legal services.
In addition, eleven lawyers were recognized as Best Lawyers: Ones to Watch® in America. This recognition is given to attorneys who are earlier in their careers for outstanding professional excellence in private practice in the United States.
The firm is also pleased to announce Best Lawyers® has recognized three attorneys as "Lawyer of the Year” including: Chuck Eppolito, Litigation - Health Care, Philadelphia, who focuses his practice on medical malpractice defense as well as other insurance-related defense; William D. Kennedy, Litigation – Insurance, Philadelphia, who focuses his practice on complex claims of injury and damage arising in both the professional and general liability contexts; and, Michael O. Kassak, Litigation – Insurance, Cherry Hill, who focuses his practice on large complex commercial matters including insurance coverage and healthcare disputes.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Kiewit-Turner Stops Work on VA Project—Now What?
December 31, 2014 —
Craig Martin – Construction Contractor AdvisorThe Kiewit-Turner joint venture created to build the VA’s hospital near Denver stopped work on December 10 after the Civilian Board of Contract Appeals ruled that the VA breached the contract. Kiewit-Turner claims that the VA owes it over $100 million on the project. And, given the appeals board’s recent ruling entirely against the VA, the claim may get some traction.
This project has been plagued with problems from the beginning. One strange aspect of the project is the VA’s apparent unwillingness to incorporate value engineering or require the architects to redesign the project to fit within the budget. The latest budget was $582M, while the latest projections show that the project will cost more than $1 billion to complete.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com