Contractual “Pay if Paid” and “Pay when Paid” Clauses? What is a California Construction Subcontractor to Do?
November 29, 2021 —
William L. Porter - Porter Law GroupThe Situation California Construction Subcontractors Face in Obtaining Payment:
California construction subcontractors find themselves faced with a significant payment issue every time they are asked to sign a subcontract on a major project. Invariably, the subcontract the prime contractor presents to the subcontractor for signature will contain a clause by which the prime contractor imposes a condition on payment from the prime contractor to the subcontractor. The condition will be either one or the other of two general types. Either the prime contractor will specify that it never has to pay the subcontractor if the prime contractor itself is not paid by the owner (a “pay-if-paid” clause), or the prime contractor will pay the subcontractor only after the prime contractor has first exhausted all its efforts to obtain payment from the owner through litigation, arbitration or otherwise, possibly delaying payment to subcontractors by months or even years (a “pay-when-paid” clause).
Goal of the Article:
The goal of this article is to draw a distinction between the pay-if-paid and pay-when-paid clauses, discuss the legality of these clauses in California, the problems these clauses create for subcontractors, advise the reader of helpful recent legal developments in this area of law, address the possibility of a further legislative remedy to address the issue, and discuss what the subcontractor might do to protect itself while awaiting a legislative remedy that may or may not ever arrive.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
End of an Era: Los Angeles County Superior Court Closes the Personal Injury Hub
October 24, 2022 —
Elizabeth A. Evans & Angela S. Haskins - Haight Brown & Bonesteel LLPOn September 21, 2022, the Los Angeles County Superior Court announced that it would start a gradual shutdown of the Personal Injury Hub, currently located at the Spring Street Courthouse. This closure will see the return of personal injury cases being venued in the district where they occurred.
The Personal Injury Hub was established in 2012 as a means of consolidating personal injury cases after several civil courtrooms around the County were closed due to significant budget cuts. It first began as two courtrooms in Stanley Mosk Superior Court, then moved to the Spring Street Courthouse and ballooned to six courtrooms, each handling a case load of reportedly over 9,000 cases at times. Case Management Conferences were abolished and the parties were largely left to their own devices to move cases along. At times, slow chaos ensued. With a new and increased budget, Los Angeles Superior Court has now decided that enough is enough.
Effective October 10, 2022, new personal injury cases will be filed and handled from start to finish in independent calendar courtrooms in the districts where the events giving rise to the claims occurred. Any cases properly filed in the Central District will continue to be heard in the Personal Injury Hub for now. A new Civil Case Cover Sheet Addendum that reflects this change will be available on the Los Angeles County Superior Court website for use as of October 10th.
Reprinted courtesy of
Elizabeth A. Evans, Haight Brown & Bonesteel LLP and
Angela S. Haskins, Haight Brown & Bonesteel LLP
Ms. Evans may be contacted at eevans@hbblaw.com
Ms. Haskins may be contacted at ahaskins@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Ruling Dealing with Constructive Changes, Constructive Suspension, and the Implied Covenant of Good Faith and Fair Dealing
January 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA dispute pending in the Armed Services Board of Contract Appeals (ASBCA) dealt with interesting legal issues on a motion to dismiss. See Appeals of McCarthy Hitt-Next NGA West JV, ASBCA No. 63571, 2023 WL 9179193 (ASBCA 2023). The dispute involves a contractor passing through subcontractor claims due to impacts caused by the COVID-19 pandemic and the government’s response to the pandemic. More particularly, the claim centers on the premise that the government “failed to work with [the contractor] in good faith to develop a collaborative and cooperative approach to manage and mitigate the impacts and delays arising from the COVID-19 pandemic.” See Appeals of McCarthy Hitt.
The contractor (again, submitting pass through claims from subcontractors) claimed: (a) constructive changes to the contract entitling it to an equitable adjustment under the Changes clause of Federal Acquisition Regulation (F.A.R.) 52.243-4; (b) construction suspensions of the contractor’s work entitling it to an equitable adjustment under the Suspensions of Work clause of F.A.R. 52-242-14; and (c) the government breached the implied covenant of good faith and fair dealing. Each of these legal issues and theories will be discussed below because they are need-to-know legal issues. Keep these legal issues in mind, and the ASBCA’s ruling on the motion to dismiss as its analysis may demonstrate fruitful in other applications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Texas Shortens Cut-Off Date for Suits Against Homebuilders Who Provide a 6-Year Written Warranty
June 26, 2023 —
Kim Altsuler - Peckar & Abramson, P.C.Summary of the new law as it pertains to builders of new homes:
The existing 10-year statute of repose for builders of new homes (the ultimate cut-off date for filing suit) has been shortened to 6 years if the builder provides a 1-2-6 written warranty (1-year workmanship and materials; 2-year plumbing, electrical and HVAC; 6-year structural).
Extended time to bring suit if written claim presented during the period of repose:
If a written claim for damages, contribution, or indemnity is presented to the builder during the applicable limitations period and the 6-year statute of repose applies, the time to sue is extended one year from the date the claim is presented. In practical effect, this means that if a written claim is presented and the statute of repose expires before suit is filed, suit may still be filed provided it is within one year of the date the written claim was made.
When the new law goes into effect:
The new law is effective as of June 9, 2023 and applies to suits commenced on or after that date. However, if the contract under which the claim is brought was entered into before June 9, 2023, the former 10-year version of the statute of repose applies. In other words, the statute applies to contracts entered into on or after June 9, 2023, if the contract has at least a 1-2-6 warranty.
Read the court decisionRead the full story...Reprinted courtesy of
Kim Altsuler - Peckar & Abramson, P.C.Ms. Altsuler may be contacted at
kaltsuler@pecklaw.com
Georgia State and Local Governments Receive Expanded Authority for Conservation Projects
May 31, 2021 —
David R. Cook Jr. - Autry, Hall & Cook, LLPIn the 2020-2021 session, the Georgia General Assembly amended existing laws to expand state and local governments’ authority to enter conservation projects. In connection with these projects, the contractor guarantees that cost savings or revenue increases will cover any payments for the project.
Read more about
conservation projects, including
Guaranteed Energy Savings Performance Contracts
With regard to school systems, conservation projects had previously included facility alterations designed to reduce energy or water consumption or operation costs. But the new law expands the permitted projects to include equipment purchases used in new construction or building retrofit, addition, or renovation. It also adds training programs incidental to the contract.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
When Your “Private” Project Suddenly Turns into a “Public” Project. Hint: It Doesn’t Necessary Turn on Public Financing or Construction
September 28, 2017 —
Garret Murai - California Construction Law BlogIn 1931, during the Great Depression, the federal government enacted the Davis-Bacon Act to help workers on federal construction projects. The Davis-Bacon Act, also known as the federal prevailing wage law, sets minimum wages that must be paid to workers on federal construction projects based on local “prevailing” wages. The law was designed to help curb the displacement of families by employers who were recruiting lower-wage workers from outside local areas. Many states, including California, adopted “Little Davis-Bacon” laws applying similar requirements on state and local construction projects.
California’s current prevailing wage law requires that contractors on state and local public works projects pay their employees the general prevailing rate of per diem wages based on the classification or type of work performed by the employee in the locality where the project is located, as well as to hire apprentices enrolled in state-approved apprentice programs and to make monetary contributions for apprenticeship training.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Following Pennsylvania Trend, Federal Court Finds No Coverage For Construction Defect
December 08, 2016 —
Tred R. Eyerly – Insurance Law HawaiiBound by Pennsylvania law, the federal district court found there was no coverage for defects in the installation of a roof. State Farm Fire & Cas. Co. v. Kim's Asia Constr., 2016 U.S. Dist. LEXIS 138915 (E.D. Pa. Oct. 5, 2016).
Kim's Asia Construction contracted to remove and dispose of Powerline Imports, Inc.'s roof, and then install a new roof. After completion of the project, Powerline sued, alleging that Kim's Asia's negligent construction of the roof caused the roof to leak, even in minor rain storms. Kim's Asia made additional repairs, but the leaks continued. Powerline had to hire a new contractor to remove and dispose of the roof and install another roof. Powerline then sued Kim's Asia.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Florida “Property Damage” caused by an “Occurrence” and “Your Work” Exclusion
July 23, 2014 —
Scott Patterson - CD CoverageIn J.B.D. Construction, Inc. v. Mid-Continent Casualty Co., * Fed.Appx. *, 2014 WL 3377690 (11th Cir. 2014), claimant property owner Sun City contracted with insured general contractor J.B.D. for the construction of a fitness center. The fitness center was to be physically connected to an existing Sun City building. J.B.D. utilized subcontractors for some of the work. Shortly after completion, leaks developed in the fitness center’s roof, windows and doors which J.B.D. attempted to fix. After Sun City refused to make the final contract payment, J.B.D. sued Sun City for contract amounts owed. Sun City counterclaimed for the construction defects, alleged damage to the fitness center and other property. J.B.D. tendered defense of the counterclaim to its CGL insurer Mid-Continent. After Mid-Continent failed to agree to defend, J.B.D. settled with Sun City, paying Sun City $182K. Following several demands from J.B.D. for reimbursement of defense costs and the settlement amount, Mid-Continent tendered the defense costs minus a deductible. J.B.D. then sued Mid-Continent for breach of duties to defend and indemnify. On cross motions for summary judgment, the federal district trial court entered judgment for Mid-Continent, finding no duties to defend or indemnify. On appeal, the Eleventh Circuit reversed on the duty to defend while affirming on the duty to indemnify. Applying Florida law, the court first held that the defective work, including the defective installation of the fitness center’s windows, doors, and roof, did not constitute “property damage.” Thus, the costs to repair or replace the defective work did not constitute damages because of “property damage.” The court next held that, while damage to other portions of the fitness center would constitute “property damage” caused by an “occurrence,” all such “property damage” fell within the “your work” exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Patterson, CD Coverage