An Obligation to Provide Notice and an Opportunity to Cure May not End after Termination, and Why an Early Offer of Settlement Should Be Considered on Public Works Contracts
August 17, 2020 —
Jeff Kaatz - Ahlers Cressman & SleightIn 2015, the City of Puyallup (“City”) and Conway Construction Company (“Conway”) executed a public works contract for road improvements (“Project”). On March 9, 2016, approximately four months after work started on the Project, the City issued Conway a notice of suspension and breach of contract and identified nine defective and uncorrected work and safety concerns. Conway denied any wrongdoing, and on March 25, 2016, the City issued a notice of termination for default and withheld payments due to Conway.
Conway subsequently filed suit in Pierce County Superior Court and alleged the City’s termination for default breached the contract and sought a determination that the City’s termination for default was improper and should be deemed a termination for convenience. Conway sought approximately $1.25 million in damages and recovery of its attorney fees and costs. Following a bench trial, the Trial Court found the City breached the contract and awarded Conway damages, attorney fees, and costs. The City appealed.[1]
On appeal, after affirming the trial court’s determination that the City improperly terminated Conway, the Court of Appeals considered two other issues raised by the City. First, whether the City was entitled to a set-off for replacing defective work discovered after Conway was terminated. Second, whether Conway is entitled to attorney fees if it did not make the statutorily required offer of settlement per RCW 39.04.240.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Kaatz, Ahlers Cressman & SleightMr. Kaatz may be contacted at
Jeff.Kaatz@acslawyers.com
The Contract Disputes Act: What Every Federal Government Contractor Should Know
February 07, 2018 —
Sarah K. Carpenter – Smith Currie BlogClaims on construction projects are unpleasant, but sometimes unavoidable. Contract with the federal government and you are by statute and by contract required to resolve any and all disputes under the Contract Disputes Act. So what is the Contract Disputes Act? This article sets forth basic information all federal government contractors should know when faced with the necessity of making or defending a claim on a federal project.
What Is the Contract Disputes Act?
The Contract Disputes Act of 1978 (CDA or Act) was enacted by Congress to implement a comprehensive statutory scheme for the resolution of government contract claims. The CDA provides a framework for asserting and handling claims by either the government or a contractor. All disputes under the CDA must be submitted to either the U.S Court of Federal Claims or to an administrative board of contract appeals. The vast majority of board cases are handled by either the Armed Services Board of Contract Appeals or the Civilian Board of Contract Appeals. The ASBCA is generally responsible for deciding appeals from decisions of contracting officers in the Department of Defense, the Department of the Army, the Department of the Navy, NASA, and when specified, the CIA. The CBCA hears disputes from all other executive agencies except the United States Postal Service (USPS), the Postal Rate Commission, and the Tennessee Valley Authority.
The USPS is served by the Postal Service BCA. In addition, the Government Accountability Office Contract Appeals Board handles contract disputes arising in the legislative branch, and the Office of Dispute Resolution for Acquisition handles contract disputes and bid protests arising out of Federal Aviation Administration procurements.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah K. Carpenter, Smith Currie
Indemnity Clauses That Conflict with Oregon Indemnity Statute Can Remain Partially Valid and Enforceable
November 30, 2016 —
Masaki James Yamada – Ahlers & Cressman PLLCWhen the indemnity provision of a contract conflicts with ORS 30.140, it is voided to the extent that it conflicts with the statute, but no more. Such provisions can remain partially valid and enforceable.[i] In Montara Owner Assn., the owner brought claims against the contractor for construction defects and damage relating to the construction of 35 townhouses. Contractor then brought third-party claims against more than 20 subcontractors for breach of contract and indemnity. Before trial, contractor settled with all but one subcontractor. The subcontract contained an indemnity provision requiring subcontractor to indemnify contractor for losses arising out of subcontractor’s work, including losses caused in part by contractor’s own negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Masaki James Yamada, Ahlers & Cressman PLLCMr. Yamada may be contacted at
myamada@ac-lawyers.com
Top 10 Take-Aways from the 2024 Fall Forum Meeting in Pittsburgh
December 03, 2024 —
Marissa L. Downs - The Dispute ResolverOver 500 construction law attorneys and consultants convened last week at the confluence of three rivers in what became the first-ever meeting in Pittsburgh, Pennsylvania of the ABA Forum on Construction Law. The Steel City was a fitting backdrop for a meeting focused on issues of design in construction. Thanks to the hard work of many, most notably the newly minted Forum Chair Keith Bergeron and Meeting Coordinators Kendall Woods and Michael Clark, the meeting's attendees brought home new connections and a host of new lessons learned. Read on for my top 10 take-aways from the 2024 Fall Meeting in Pittsburgh and feel free to share yours in the comments below.
10. An architect's standard of care does not require perfection. A common refrain across many of the meeting's plenary sessions was that any design that is produced by human hands will never be perfect. In recognition of our own fallibility, the legal standard to which design professionals will be held to account does not require that their designs be error-free. A design professional must generally exercise the degree of care and skill ordinarily exercised by professionals performing similar services under similar circumstances. Establishing what that means in each locality will vary and will most likely need to be supported by the expert opinion of another practicing design professional.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
“Details Matter” is the Foundation in a Texas Construction Defect Suit
March 01, 2012 —
CDJ STAFFThe Court of Appeals of Texas has ruled in the case of Barzoukas v. Foundation Design. Mr. Barzoukas contracted with Heights Development to build a house. He subsequently sued Heights Developments and “numerous other defendants who participated in the construction of his house.” Barzoukas eventually settled with all but two defendants, one who went bankrupt and Foundation Design, the defendant in this case. In the earlier phase, Barzoukas made claims of “negligence, negligent misrepresentation, fraud, fraudulent inducement, conspiracy, and exemplary damages in connection with the foundation.”
Foundation Design had been hired to install 15-foot piers to support the foundation. The engineer of record, Larry Smith, sent a letter to Heights Development noting that they had encountered hard clay stone when drilling. Smith changed the specifications to 12-foot piers. Initially, the City of Houston called a halt to work on the home when an inspector concluded that the piers were too shallow. Heights Development later convinced the city to allow work to continue. Subsequently, experts concluded that the piers were too shallow.
Foundation Design filed a motion for summary judgment. The trial court granted this, “without specifying the basis for its ruling.” Barzoukas contends the court was in error. Foundation Design contends that “Barzoukas failed to proffer competent evidence establishing that their conduct proximately caused damages.” Further, they did not feel that Smith’s letter gave “rise to viable claims for fraud and fraudulent inducement.”
One problem the court had was a lack of evidence. The court noted that “the purported subcontract is entirely missing” in the pleadings. The court has no contract between Bazourkas and Heights Development, nor one between Heights Development and either Foundation Design or Smith. The court underscored the importance of this, writing, “details matter.” They found that “the details are largely missing here.” Without the contract, the court found it impossible to determine if “Smith or an entity related to him agreed to indemnify Heights Development for damages arising from Smith’s negligent performance.”
As the material facts are in dispute, the appeals court found that there were no grounds for a summary judgment in the case. “Pointing to the existence of a contract between Heights Development and Barzoukas, or to the existence of a subcontract, is the beginning of the analysis ? not the end.”
Foundation Design and Smith also claimed that Barzoukas’s expert did not proffer competent evidence and that the expert’s opinions were conclusory. The trial court did not rule on these claims and the appeals court has rejected them.
Finally, Barzoukas made a claim that the trial court should not have rejected his argument of fraud and fraudulent inducement. Here, however, the appeals court upheld the decision of the lower court. “Barzoukas did not present evidence supporting an inference that Smith or Foundation Design made a purposeful misrepresentation.
The court remanded the case to the trial court for reconsideration. One member of the panel, Judge Charles Seymore, upheld the entire decision of the trial court. He dissented with the majority, finding that the economic loss rule foreclosed the claim of negligence.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Supreme Court Rejects Class Action Status, Reducing Homes from 1000 to 71
July 02, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Las Vegas Review-Journal reported that the “Nevada Supreme Court has rejected a request for class action status for claims of damaged stucco from faulty construction by Del Webb Communities involving nearly 1,000 Sun City Summerlin residents,” however, “the court upheld the award of damages to 71 homeowners following a jury trial in Clark County District Court in 2008.”
The case began in 2003, and the Las Vegas Review-Journal referred to it as “one of the largest construction-defect cases in Nevada history.” But District Judge Allan Earl denied class action lawsuit in 2006. “Attorneys were seeking $70 million for the homeowners.” In 2008, another court “determined that only 71 homeowners merited compensation totaling $4 million for the stucco issues.”
According to the Las Vegas Review-Journal, “[h]omeowners alleged that Del Webb failed to install metal screeds that would protect homes from water damage, and as a result, the homes suffered from cracked stucco, mold and weakened walls.”
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations 2016 DE, MA, NJ, NY and PA Super Lawyers and Rising Stars
October 27, 2016 —
White and Williams LLPThirty-two White and Williams lawyers have been named by Super Lawyers as a Delaware, Massachusetts, New Jersey, New York or Pennsylvania "Super Lawyer" while fourteen received "Rising Star" designations. Each lawyer who received the distinction competed in a rigorous selection process which took into consideration peer recognition and professional achievement. The lawyers named to this year's Super Lawyer list represent a multitude of practices throughout the firm.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Roof's "Cosmetic" Damage From Hail Storm Covered
August 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Seventh Circuit affirmed the district court's determination that cosmetic damage to the insured's roof was covered. Advance Cable Co., LLC v. Cincinnati Ins. Co., 2015 U.S. App. LEXIS 9805 (7th Cir. June 11, 2015).
The insured submitted a claim to its insurer, Cincinnati, for damage to the metal roof of its building caused by a hail storm. The insured inspected the roof with a claims representative for Cincinnati. Dents were spotted, but there was little other evidence of damage. The loss was estimated at $1,894.74. A check for this amount was sent to the insured.
Six months later, the insured considered selling the building. A potential buyer inspected the roof and found hail damage. At the request of the insured, Cincinnati conducted another inspection of the roof. Again, dents of approximately 1 inch in diameter were found. The inspector noted that the denting would not affect the performance of the roof panels or detract from their life expectancy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com