No Coverage for Additional Insured for Construction Defect Claim
July 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit affirmed the district court's grant of summary judgment to the insurers, finding there was no coverage for the additional insured on a construction defect claim. St. Paul Guardian Ins. Co. v. Walsh Construction. Co., 2024 U.S. App. LEXIS 10285 (7th Cir. April 29, 2024).
The City of Chicago hired Walsh Construction Company as general contractor for the Facade and Circulation Enhancement (FACE) project at O'Hare International Airport. The FACE project involved building and installing a new canopy for Terminals 1, 2 and 3. The project also called for the construction of a steel and glass curtain wall that would be integrated with the curtain wall at Terminals 2 and 3. Walsh contracted with Carlo Steel Corporation to manufacture the steel and curtain wall. Carlo, in turn, subcontracted with LB Steel, LLC to manufacture and install the steel elements of the wall, which included steel columns, hammer heads and box girders. The subcontract between Carlo and LB Steel included an indemnity provision that required LB Steel to indemnify Carlo and Walsh for any property damage resulting from LB Steel's negligent performance.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Booms With FivePoint New Schools: Real Estate
May 13, 2014 —
John Gittelsohn – BloombergFivePoint Communities Management Inc. is already constructing a school at its Great Park Neighborhoods project in Irvine, California, for 1,000 elementary and middle school students even as it’s still building the first 700 homes.
“We build the schools ahead of time,” said Emile Haddad, chief executive officer of Aliso Viejo, California-based FivePoint, which has permits for about 10,000 homes at Great Park. “That way we always have them ready.”
Local schools, along with parks and recreation facilities, have long been draws for buyers in new communities. Now, as school districts face tight construction budgets and homebuilders compete to attract families able to qualify for mortgages, developers are taking the lead on school construction instead of waiting for local governments to do the job.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelsohn may be contacted at
johngitt@bloomberg.net
Contract Void Ab Initio: Key Insights into the KBR vs. Corps of Engineers Affirmative Defense
February 12, 2024 —
Matthew DeVries - Best Practices Construction LawIn a recent Board decision dated December 13, 2023, the United States Army Corps of Engineers sought to amend its answer in the case of APPEALS OF – KELLOGG BROWN & ROOT SERVICES, INC., under Contract No. W912GB-13-C-0011. The proposed amendment introduces an affirmative defense, contending that Kellogg Brown & Root Services, Inc. (KBR) made material misrepresentations in its proposal, rendering the fully-performed contract void ab initio.
Background: The contract in question, executed on July 9, 2013, was for the construction of an Aegis Ashore Missile Defense System site in Deveselu, Romania, with a firm, fixed-price amount of $134,211,592. The Corps moved to amend its answer to allege that KBR’s material misrepresentations induced the Corps to enter the contract, justifying the voiding of the contract. The alleged misrepresentations include issues related to subcontractor quotes, firm fixed prices, subcontracting plans, and more.
Motion to Amend and Legal Defense: The Corps, despite delays in formally amending its answer, argued that KBR was aware of the potential affirmative defense before the conclusion of fact discovery. The proposed affirmative defense asserts that KBR made eight material misrepresentations in its proposal, upon which the Corps relied in awarding the contract and defending against a GAO protest.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Need and Prejudice: An Eleventh-Hour Trial Continuance Where A Key Witness Is Unexpectedly Unavailable
July 10, 2018 —
Angela S. Haskins & Allegra Perez - Haight Brown & Bonesteel LLPIn Padda v. Superior Court (GI Excellence), No. E070522, the Court of Appeal, Fourth Appellate District, Division Two, recently held that a trial court abused its discretion in denying Defendants/Cross-Complainants’ request for a trial continuance where their key expert witness suddenly became ill twelve days before trial and before his deposition had been taken.
Reprinted courtesy of
Angela S. Haskins, Haight Brown & Bonesteel LLP and
Allegra Perez, Haight Brown & Bonesteel LLP
Ms. Haskins may be contacted at ahaskins@hbblaw.com
Ms. Perez may be contacted at aperez@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Be Careful with Mechanic’s Lien Waivers
June 09, 2016 —
Christopher G. Hill – Construction Law MusingsMechanic’s liens are near and dear to my heart here at
Construction Law Musings. These powerful tools can and should be properly used to help you, as a construction professional, get paid for your good work. Of course, the correct steps toward perfecting one of these liens must be followed, including being sure to
meet the stringent lien deadlines. I’ve discussed
the steps for filing such a lien and the various pitfalls relating to the
very picky statutory requirements for recording an enforceable memorandum of lien in Virginia.
One important area that I have not discussed as thoroughly as these basic requirements (and an area of which I have been
reminded by my pals at the Construction Payment Blog) is the area of mechanic’s lien waivers. While the Virginia General Assembly has
ended the days of pre-payment contractual waiver of mechanic’s lien rights for subcontractors and suppliers, mechanic’s lien waivers that waive rights either simultaneous with or after receipt of progress and final payments are still valid and used on a regular basis.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
No Signature? Potentially No Problem for Sureties Enforcing a Bond’s Forum Selection Clause
March 21, 2022 —
Brian C. Padove - ConsensusDocsOne of the foundational tenets of contract law is that a party may only be bound by terms they agree to, or in other words, if the party did not sign a contract, that party cannot be bound by the terms thereof. While this principle is generally unwavering, there are certain situations in which a non-signatory to a contract may still be bound by the terms of a contract.
In particular, this non-signatory issue may arise when a payment bond claimant makes a bond claim, subsequently files a lawsuit, but the bond contains a forum selection clause different than the venue of the lawsuit and the surety seeks to enforce the bond’s forum selection clause. For example, the claimant may have filed its lawsuit against the surety in federal court, even though the bond provides language specifically mandating that no lawsuit shall be commenced by any claimant other than in a state court where the project is located. Thus, the question then becomes, can the surety enforce the forum selection clause against the claimant when the claimant did not sign the bond and/or never agreed to the terms thereof? The short answer, it depends (yes, that is a very lawyer-like answer). Given recent case law over the past decade, however, the surety has a strong argument in favor of enforcement of the forum selection clause.
Read the court decisionRead the full story...Reprinted courtesy of
Brian C. Padove, Watt, Tieder, Hoffar & Fitzgerald, LLP (ConsensusDocs)Mr. Padove may be contacted at
bpadove@watttieder.com
Designing the Process to Deliver Zero-Carbon Construction – Computational Design in Practice
January 04, 2023 —
Peter Debney - AEC BusinessComputational Design is generating increasing interest in the construction industry as well as a certain amount of confusion. It is not parametric design; instead it takes parametric design to the next level. It is a set of methods that will define how we design structures over the next decades.
With Computational Design, you don’t design the building; you design the automated process to find the best building design.
Why use Computational Design?
Computational Design is enabling us to create buildings that are far more efficient than we can manage using more traditional methods. Some architects are indeed using it to produce novel building forms, but its great advantage is in helping us towards efficient, zero-carbon construction.
Read the court decisionRead the full story...Reprinted courtesy of
Peter Debney, AEC Business
Privity Problems Continue for Additional Insureds in the Second Circuit
November 08, 2017 —
Samantha M. Martino – Saxe Doernberger & Vita, P.C.On October 4, the Second Circuit held that Harleysville Insurance Company had no duty to defend or indemnify a project owner or general contractor as additional insureds under a sub-subcontractor’s commercial general liability (CGL) policy due to lack of direct contractual privity. 1
The underlying claim arose when an employee of The Kimmell Company, Inc. (Kimmell) was injured while repairing an HVAC system at a building owned by the University of Rochester Medical Center (UR). The injured employee sought damages for his injuries and fi led suit against (1) UR; (2) LeChase Construction Corp. (LeChase), the general contractor for the project; and (3) J.T. Mauro Co. Inc. (Mauro), a subcontractor hired by LeChase.
Mauro hired Kimmell as a sub-subcontractor to perform HVAC services at the project. The Mauro-Kimmel contract required Kimmel to add Mauro, UR, and LeChase as additional insureds under Kimmell’s CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Samantha M. Martino, Saxe Doernberger & Vita, P.C.Ms. Martino may be contacted at
smm@sdvlaw.com