Colorado’s New Construction Defect Law Takes Effect in September: What You Need to Know
November 21, 2017 —
Jesse Witt - The Witt Law FirmOriginally published by CDJ on September 7, 2017
Colorado’s new construction defect law officially takes effect this month. Although HB 17-1279 was passed in May, the statutory text provides that it only applies “with respect to events and circumstances occurring on or after September 1, 2017.” With that date now upon us, practitioners should be mindful of the law’s new requirements.
The law applies to any lawsuit wherein a homeowner association files a construction defect action on behalf of two or more of its members. “Construction defect action” is defined broadly to include any claims against construction professionals relating to deficiencies in design or construction of real property. Before an association may commence such an action, its board must follow several steps.
First, the board must deliver notice of the potential construction defect action to all homeowners and the affected construction professionals at their last known addresses. This requirement does not apply to construction professionals identified after the notice has been mailed, or to construction professionals joined in a previously-approved lawsuit. The notice must include a description of the alleged construction defects with reasonable specificity, the relief sought, a good-faith estimate of the benefits and risks involved, and a list of mandatory disclosures concerning assessments, attorney fees, and the marketability of units affected by construction defects. The notice must also call a meeting of all homeowners. The notice should be sent to the construction professionals at least five days before the homeowners.
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Summarizing Changes to NEPA in the Fiscal Responsibility Act (P.L. 118-5)
September 05, 2023 —
Anthony B. Cavender & Marcus Manca - Gravel2Gavel Construction & Real Estate Law BlogThe National Environmental Policy Act (NEPA) was signed into law on January 1, 1970, and it has rarely been amended or revised since then. NEPA is basically a procedural statute which requires Federal permitting authorities, before a major federal project is approved, to carefully consider the significant environmental consequences of the proposed federal action. NEPA has been employed to conduct a probing review of wide variety of federal projects and actions, and the President’s Council on Environmental Quality (CEQ) has promulgated a comprehensive set of rules and guidance documents that must be followed or consulted. (See 40 CFR Section 1500 et seq.) The first set of NEPA rules was issued in 1978, and very little was done to bring the rules up to date until 2020. The first phase of this review has been completed, and a second and final phase will soon be underway. The NEPA review process includes the use of “categorical exclusions,” environmental assessments and environmental impact statements to measure the environmental impact of a proposed project. Over time, the rules and their implementation and judicial interpretation have become ever more complex, and an enormous body of NEPA case law has resulted.
The recent Congressional debt limit deliberations provided an opportunity to revise some of these procedures, and the Fiscal Responsibility Act, signed into law on June 3, 2023, included at Title III, a section devoted to “Permitting Reform.”
Reprinted courtesy of
Anthony B. Cavender, Pillsbury and
Marcus Manca, Pillsbury Read the court decisionRead the full story...Reprinted courtesy of
Mr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Fence Attached to Building Covered Under Dwelling Provisions
March 01, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Texas Supreme Court determined that a damaged fence attached to the insureds' dwelling was covered under the dwelling provisions, not the "other structure" portion of the policy. Nassar v. Liberty Mutual Fire Ins. Co., 2017 Tex. LEXIS 113 (Tex. Jan. 27 ,2017).
The insureds' owned six acres of property. Hurricane Ike caused significant damage to the property on September 13, 2008. The insureds submitted a claim to Liberty Mutual under their homeowners' policy. Liberty Mutual paid several claims, but disputes arose over the value of various items of damaged property, including the fencing on the property. The insured's fencing spanned over 4,000 linear feet, including a white picket fence at the northeast corner of the dwelling, an ornamental iron fence in front of the dwelling, numerous cross fences, garden fences, and a larger, perimeter fence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Remodels Replace Construction in Redding
September 09, 2011 —
CDJ STAFFThe Record Searchlight reports that while new construction is down in Redding, California, residential and commercial remodel permits are up 17 percent. By August 2010, there had been 63 housing and commercial business starts in Redding, while this year has seen only 15.
One such remodel, that of Parkview Market, will cost about $201,000. Safeway is planning on two $80,000 remodels of its grocery stores in Redding. In all, the 150 building permits for remodels are worth a total of $2.8 million.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Updates to Residential Landlord Tenant Law
October 18, 2021 —
Lawrence S. Glosser - Ahlers, Cressman & SleightOver the past several months, there have been major updates to the residential landlord tenant laws in Washington State and Seattle. There are also some remaining moratoria or eviction restrictions in Washington and Seattle. The following is a general overview of the changes.
Eviction Moratoria:
Washington State
Governor Inslee’s state-wide eviction moratorium technically ended on June 30, 2021. However, in late June 2021, Governor Inslee announced a “bridge” proclamation between the eviction moratorium and the housing stability programs put in place by the Washington State Legislature. The bridge is effective July 1 through September 30. The goal of the bridge period was to protect tenants from evictions for non-payment of rent to allow local governments to set up distribution programs for funds. More than $650 million of federal relief dollars allocated to assist renters was predicted to be available beginning in July. This is in addition to the $500 million previously released by the Department of Commerce to local governments for rental assistance and will help more than 80,000 landlords and renters. However, insofar as many localities have not established distribution protocols, the bridge period was instituted to allow time for those programs to be set up in various parts of the state.
Read the court decisionRead the full story...Reprinted courtesy of
Lawrence S. Glosser, Ahlers, Cressman & SleightMr. Glosser may be contacted at
larry.glosser@acslawyers.com
Addressing the Defective Stucco Crisis
November 28, 2018 —
Wally Zimolong - Supplemental ConditionsI received several emails regarding the expose by Caitlin McCabe and Erin Arvedlund in the Philadelphia Inquirer titled “Rotting Within.” The story outlines the epidemic of defective stucco and other “building envelope” issues in Southeastern Pennsylvania that is causing homes to literally rot from within. Having litigated several of these cases, they are frustrating for both the attorneys that handle them and the homeowners who must deal with the reality that their home is rotting away. The story points to the multiple (and all too common) causes for the epidemic: unskilled subcontractors, lack of oversight and care, and poor construction drawings. The is no quick solution to the crisis and litigation regarding these defects is sure to proliferate.
However, there is one potential solution that the story does not cover and which could help alleviate some of the challenges homeowners face in recovering damages for their claims. The Pennsylvania Legislature must act to change the insurance laws in Pennsylvania to make defective construction covered by a developer’s, contractor’s, and subcontractor’s commercial general liability policy (“CGL”). Most homeowners and many attorneys incorrectly assume that defective construction is covered by insurance. This assumption makes sense. If someone operates a car in a negligent manner and hits your car and causes damage, the negligent driver’s insurance company with cover your loss. In reality, Pennsylvania courts follows a minority of states that holds that generally speaking defective workmanship is not a “covered occurrence” under an insurance policy. (There are several exceptions to this rule and thorough discussion is beyond this blog post and would probably bore you.)
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Purse Tycoon Aims at Ultra-Rich With $85 Million Home
September 24, 2014 —
John Gittelsohn and Nadja Brandt – BloombergThe eight-bedroom, 15-bath Beverly Hills, California, mansion has $5,600 toilets, a wall of caramel onyx and an 18-seat screening room with doors clad in Italian lizard skin. Asking price: $85 million.
Rapper Jay Z has taken two tours of the hillside aerie with views that sweep from downtown Los Angeles to the Pacific Ocean. The estate was developed by Bruce Makowsky, who made his fortune selling handbags through department stores and the QVC television channel.
“There was a void of homes for super-wealthy people, and that’s why I did it,” Makowsky said while sitting near a curved 54-foot (16-meter) glass wall that slides open to an infinity pool with iPad-controlled fountains. “I don’t think there’s anybody who’s served up $85 million-to-$100 million homes at this level for somebody to step into and buy.”
Mr. Gittelsohn may be contacted at johngitt@bloomberg.net; Ms. Brandt may be contacted at nbrandt@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn and Nadja Brandt, Bloomberg
Read Her Lips: “No New Buildings”
November 18, 2011 —
CDJ STAFFMartha Johnson, the head of the General Services Administration, has said that her agency will not be building any new buildings in the near future. Among other duties, the GSA is responsible for the building, renovating, and leasing of federal office space. The White House had proposed $840 million in new construction, the Senate only $56 million. The House did not appropriate any money for the agency to use for new construction.
In addition to cutbacks on new buildings, Congress is suggesting only $280 million in repairs of existing government buildings. In order to cut back, the GSA has dropped plans to renovate their own offices in favor of renovations at the Department of Homeland Security and the Food and Drug Administration.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of