OH Supreme Court Rules Against General Contractor in Construction Defect Coverage Dispute
October 30, 2018 —
Theresa A. Guertin - Saxe Doernberger & Vita, P.C.On October 9, 2018, the Ohio Supreme Court issued a decision in Ohio Northern University v. Charles Construction Services, Inc., Slip Op. 2018-Ohio-4057, finding that a general contractor was not entitled to defense or indemnity from its CGL insurer in a construction defect suit brought by a project owner post-project completion. With this decision, Ohio has solidified its place amongst a diminishing number of states, including Pennsylvania and Kentucky, which hold that there is no coverage for defective construction claims because those losses do not present the level of fortuity required to trigger CGL coverage. This places Ohio amongst the worst in the country on this issue at a time when numerous states have abandoned old precedent and moved towards a policyholder friendly analysis.
Ohio Northern University (“ONU”) hired Charles Construction Services, Inc. (“CCS”) to construct the University Inn and Conference Center, a new hotel and conference center on their campus in Ada, Ohio. CCS purchased CGL insurance from Cincinnati Insurance Company (“CIC”) insuring the project. Following completion of the project, ONU sued CCS alleging defects in the construction of the completed project, including allegations that windows improperly installed by one subcontractor led to damage to walls built by another subcontractor. CIC agreed to defend CCS under a reservation of rights but intervened in the action between ONU and CCS to pursue a declaratory judgment that it had no obligation to defend or indemnify its insured for the alleged losses.
Read the court decisionRead the full story...Reprinted courtesy of
Theresa A. Guertin, Saxe Doernberger & Vita, P.C.Ms. Guertin may be contacted at
tag@sdvlaw.com
Indiana Court Enforces Contract Provisions rather than Construction Drawing Markings
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFTimothy J. Abeska, a vice-chair of Barnes & Thornburg LLP’s Construction Law Practice Group, analyzed Goodrich Quality Theaters, Inc. v. Fostcorp Heating and Cooling, Inc., 16 N.E.3d 426 (Ind. Ct. App. 2014), which “provides an example of a court enforcing contract provisions rather than markings on construction drawings that are inconsistent with contract requirements.”
The case evolved from a dispute on a construction of an IMAX theater, when the general contractor did not understand the architect’s markings for non-standard joist girders, and ordered standard joist girders, per the contract. The error created delays and other problems, which led to payment disputes and mechanic’s liens against the project.
Abeska stated that “[t]his case shows the importance of making sure all documents which comprise a construction contract are consistent with each other, as courts will enforce contracts negotiated by the parties. The case also demonstrates that litigation is not a quick process, as the Court of Appeals Opinion was issued more than seven years after the project was completed.”
Read the court decisionRead the full story...Reprinted courtesy of
Pre-Suit Settlement Offers and Construction Lien Actions
July 21, 2018 —
David Adelstein - Florida Construction Legal UpdatesIt is unfortunate, but in certain matters, a construction lien foreclosure action is not actually driven by the principal amount in dispute. Oh no. Rather, it is driven by attorney’s fees. That’s right. Attorney’s fees. This is true even though Florida applies the significant issues test to determine the prevailing party for purposes of attorney’s fees. However, oftentimes the prospect of attorney’s fees is enough for parties to fear that exposure.
There is a 1985 Florida Supreme Court case that I like to cite if applicable, C.U. Associates, Inc. v. R.B. Grove, Inc., 472 So.2d 1177, 1179 (Fla. 1985), that finds, “in order to be a prevailing party entitled to the award of attorney’s fees pursuant to section 713.29 [a construction lien claim], a litigant must have recovered an amount exceeding that which was earlier offered in settlement of the claim.” Accord Sullivan v. Galske, 917 So.2d 412 (Fla. 2d DCA 2006) (explaining that although contractor is receiving a judgment in his favor, he may not be the prevailing party if the homeowner offered to settle prior to the lawsuit for an amount equal to or greater than the award in the judgment).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Builder Waits too Long to Dispute Contract in Construction Defect Claim
May 10, 2012 —
CDJ STAFFThe Louisiana Court of Appeals has affirmed the lower court’s judgment in the case of Richard v. Alleman. The Richards initiated this lawsuit under Louisiana’s New Home Warranty Act, claiming that they had entered into a construction contract with Mr. Alleman and that they quickly found that his materials and methods had been substandard. They sued for the cost of repairing the home and filing the lawsuit. Mr. Alleman countersued, claiming the Richards failed to pay for labor, materials, and services. By his claim, they owed him $12,838.80.
The trial court split the issues of liability and damages. In the first trial, the court concluded that there was a contact between Alleman and the Richards and that the New Home Warranty Act applied. Mr. Alleman did not appeal this trial.
The second trial was on the issue of damages. Under the New Home Warranty Act, the Richards were found to be entitled to $36,977.11 in damages. In a second judgment, the couple was awarded $18,355.59 in attorney’s fees. Mr. Alleman appealed both judgments.
In his appeal, Alleman contended that the trial court erred in determining that the Home Warranty Act applied. This was, however, not the subject of the trial, having been determined at the earlier trial. Nor did the court accept Alleman’s claim that the Richards failed to comply with the Act. The trial record made clear that the Richards provided Alleman with a list of problems with their home by certified mail.
The court did not establish whether the Richards told Alleman to never return to their home, or if Alleman said he would never return to the home, but one thing was clear: Alleman did not complete the repairs in the list.
A further repair was added after the original list. The Richards claimed that with a loud noise, a large crack appeared in their tile flooring. Mr. Alleman stated that he was not liable for this as he was not given a chance to repair the damage, the Richards hired the flooring subcontractors, and that the trial court rejected the claim that the slab was defective. The appeals court found no problem with the award. Alleman had already “refused to make any of the repairs.”
Finally Alleman made a claim on a retainage held by the Richards. Since Alleman did not bring forth proof at trial, the appeals court upheld the trial courts refusal to award a credit to Alleman.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Court Finds that Subcontractor Lacks Standing to Appeal Summary Judgment Order Simply Because Subcontractor “Might” Lose at Trial Due to Order
May 03, 2021 —
Garret Murai - California Construction Law BlogCases sometimes take unanticipated twists and turns. Atlas Construction Supply, Inc. v. Swinerton Builders, Case No. D076426 (January 26,2021), involving a tragic construction accident, a motion for summary judgment, a motion for good faith settlement, and a stipulated dismissal, is one of those cases.
The Accident
Swinerton Builders was the general contractor on a residential construction project in San Diego, California. Swinerton contracted with J.R. Construction, Inc. to perform concrete work and with Brewer Crane & Rigging, Inc. to perform crane work on the project. J.R. Construction in turn rented a concrete column formwork approximately 10 feet tall and weighing 300 to 400 pounds from Atlas Construction Supply, Inc.
One day on the construction project, Marcus Develasco, Sr. and another co-worker, employees of J.R. Construction, climbed to the top of the formwork to adjust its size. The formwork, which had been positioned on the site by Brewer, was upright but unsupported by braces. When the co-worker stepped off the formwork, Develasco’s weight caused the unsecured formwork to topple over, killing Develasco in the process.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
The Conscious Builder – Interview with Casey Grey
February 16, 2017 —
Aarni Heiskanen – AEC BusinessIn this podcast interview, Casey Grey talks about Conscious Building, passive houses, and and how we can make our homes healthier.
About Casey Grey
Casey Grey is the founder and CEO of The Conscious Builder Inc., an Ontario company.
Casey is one of those very few people who knew what he wanted from a very young age. Although his goals have changed over the years, they have always revolved around building homes. From Lego, to tree houses to custom homes, he is constantly looking for ways to build better homes.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aarni@aepartners.fi
Do Change Orders Need to be in Writing and Other Things That Might Surprise You
June 02, 2016 —
Garret Murai – California Construction Law BlogYou’ve likely heard it before or maybe you’ve even said it yourself: “Go ahead and get started, we’ll get you a change order later.”
The only thing is, “later” never happens, and after you’ve finished performing the work you find yourself in a fight over whether you’re entitled to get paid for the work you performed.
So, do you need a written change order to get paid for extra work you performed? Read on, you may be surprised.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Delay Leads to Problems with Construction Defects
November 27, 2013 —
CDJ STAFFThe Bardwells bought a new home in the Philadelphia area in 2000. Now, thirteen years later they’ve learned that their house has been slowly rotting away due to moisture trapped beneath the stucco. And they’re not alone. The O’Days bought a home for about $1 million, and it now needs about $200,000 in repairs. All the stucco has been removed and their home is being rebuilt. Monica Bardwell said that “everything was rotted,” and “there was not a piece of good wood to be salvaged.”
Other area homeowners are finding similar problems. Wendy Meyer had her home inspected by Kevin Thompson. Mr. Thompson said, “I shouldn’t be able to take a piece of plywood like that and crush it in my hands completely disintegrated.”
Mr. Thompson described it as due to “faulty construction,” which he estimated accounted for such damage “95 percent of the time.” The Pennsylvania Builders Association says that diligent homeowners can head off problems with maintenance. “Make sure water isn’t continually on the outside of the stucco,” said Brent Sailhamer of the PBA. “Make sure there are no large cracks where water can seep behind the stucco.”
For those who bought their homes as far back as the Bardwells, it’s already too late to sue anyone. Pennsylvania construction defect law allows 12 years for lawsuits.
Read the court decisionRead the full story...Reprinted courtesy of