South Adams County Water and Sanitation District Takes Proactive Step to Treat PFAS, Safeguard Water Supplies
November 28, 2022 —
Cameron McWilliam – Brown and CaldwellDENVER, Colo., Nov. 15, 2022 — The South Adams Country Water and Sanitation District (District) is enhancing its water treatment process to meet EPA Health Advisory Levels (HALs) for per- and polyfluoroalkyl substances (PFAS) in drinking water supplies.
Deemed “forever chemicals,” PFAS is a group of human-made chemicals used in many applications, including stain- and water-resistant fabrics and carpeting, cleaning products, paints, and firefighting foams. PFAS are resistant to grease, oil, water, and heat and may enter water supplies from landfills, the use of firefighting foam (e.g., at airports, fire training facilities, petroleum fires, etc.), industrial sites, and wastewater treatment plant discharge.
The District’s water supply, serving over 67,000 residents in Commerce City and parts of unincorporated Adams County, comes primarily from 13 groundwater supply wells. As it continues to meet all federal and state drinking water requirements, the District has been proactively pursuing PFAS reduction strategies since it first discovered a low-level presence in its water supply through voluntary testing in 2018. Upon discovery, the District stopped drawing from its most impacted wells and has been purchasing additional treated water to blend into its supply to reduce PFAS levels along with optimizing use of their existing granular activated carbon treatment system.
“Ever since the District first began voluntarily testing for PFAS, we have been monitoring for these compounds and working to reduce their impact on our customers,” said District Manager Abel Moreno. “The EPA has moved the goalposts, and we are taking steps to reduce the presence of PFAS even further. We are committed to finding long-term, sustainable solutions to offer our community high-quality drinking water.”
To tackle the challenge, the District has hired leading environmental and construction services firm Brown and Caldwell to design a new 18 million gallons per day (MGD) ion exchange (IX) process at its Klein Water Treatment Facility. IX treatment is currently the most effective technology in removing PFAS/PFOA, consisting of a highly porous resin that acts as a powerful magnet to adsorb and hold onto the substances. The new system at the Klein facility will consist of seven IX treatment trains, a 375,000-gallon equalization tank, and six vertical turbine pumps to feed the IX trains from the District’s 13 groundwater supply wells.
Furthermore, nine 5-micron cartridge filters will be installed to remove particulate matter in the water before reaching the IX trains, thus increasing the efficacy of the treatment process.
Scheduled for completion by the end of 2026, the new IX treatment facility will provide a peak combined capacity of 26 MGD.
About South Adams County Water and Sanitation District
The South Adams County Water and Sanitation District is a special district providing water and sanitary sewer service to over 67,000 residents in Commerce City and parts of unincorporated Adams County. For more information about the District, please visit www.sacwsd.org
About Brown and Caldwell
Headquartered in Walnut Creek, California., Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and 1,800 professionals across North America and the Pacific. For 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients’ expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Court Holds Radioactive Materials Exclusion Precludes E&O Coverage for Negligent Phase I Report
October 30, 2018 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Merritt Environmental Consulting Corp. v. Great Divide Ins. Co., 2018 U.S. Dist. LEXIS 175527 (E.D.N.Y. Oct. 10, 2018), the United States District Court for the Eastern District of New York had occasion to consider the application of a radioactive materials exclusion in a professional liability policy.
Great Divide’s insured, Merritt Environmental, was hired as an environmental consultant by a bank in connection with a mortgage refinance of a property located in Westchester County, New York. Merritt’s responsibility was to prepare a Phase I environmental report concerning the property, which the bank ultimately relied on in agreeing to the refinance. It was later claimed, however, that Merritt’s report failed to document the full extent of the property’s radium and uranium contamination resulting from its use in the Manhattan Project. Merritt was named in two separate lawsuits as a result of its allegedly faulty report, including one by the bank alleging that Merritt negligently prepared its report.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub Lieberman Straus & Shrewsberry LLPMr. Margolies may be contacted at
bmargolies@tlsslaw.com
Partner John Toohey and Senior Associate Sammy Daboussi Obtain a Complete Defense Verdict for Their Contractor Client!
December 11, 2023 —
Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to share that Newport Beach attorneys John Toohey and Sammy Daboussi obtained a complete defense verdict after years-long litigation in favor of their concrete contractor client.
This lawsuit arises from a claim made by Plaintiff for construction defects in a high-end single-family home. Our client was hired to perform concrete work on the foundations of the home. It was alleged that the home’s foundation was incorrectly built. It was further alleged that the construction defects/errors led to delays and substantial expenses. We argued that our client relied on the certifications provided to them by design professionals and the City. We further argued that our client, like any reasonable concrete/foundation subcontractor, has no responsibility or obligation, contractual or otherwise, to review and recheck the work completed by a licensed professional.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
After Breaching its Duty to Defend, Insurer Must Indemnify
August 11, 2011 —
Tred R. Eyerly - Insurance Law HawaiiIn a brief decision analyzing Oregon law, the Ninth Circuit determined that once an insurer breaches its duty to defend, it must indemnify. See Desrosiers v. Hudson Speciality Ins. Co., 2011 U.S. App. LEXIS 12591 (9th CIr. June 21, 2011).
The victim secured a judgment against the insured after he was beaten by another patron outside the insured's bar. Hudson Speciality Insurance refused to defend the insured, claiming the injury arose from an assault and battery, which excluded coverage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Penalty for Failure to Release Expired Liens
April 02, 2024 —
William L. Porter - Porter Law GroupI was recently contacted by a commercial building owner in the process of trying to sell his building. Two years prior to this, a subcontractor had recorded a mechanics’ lien with the local County Recorder’s office in relation to the owner’s property. The subcontractor recorded the mechanics lien after the subcontractor was not paid by a prime contractor for work the subcontractor had performed on the property. Unfortunately, the subcontractor then failed to file a lawsuit to foreclose on the lien within the requisite ninety (90) day time period for filing a lawsuit to foreclose on the mechanics’ lien. Since the subcontractor missed this 90 day deadline to file the mechanics lien foreclosure lawsuit, the mechanics lien expired and became unenforceable.
Subject to certain exceptions, under California Civil Code Section 8460, a lawsuit to foreclose on a mechanics lien must be filed within ninety (90) days after the mechanics lien is recorded or the mechanics lien expires. Although the mechanics lien had expired, the title company and intended purchaser of the building and property were perhaps understandably insistent that the mechanics lien constituted a cloud on title to the property and must be removed from the official records for the property. The prospective purchaser would not buy the property unless the mechanics’ lien was removed.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Washington’s Court of Appeals Protects Contracting Parties’ Rights to Define the Terms of their Indemnity Agreements
March 19, 2024 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIt has long been the law in Washington that contracting parties are free to draft contractual indemnity agreements to allocate risk arising from performance of the work, and Courts will generally enforce those agreements as written. This well-settled principle was recently reaffirmed in King County v. CPM Development Corp., dba ICON Materials[1] a decision from Division I of the Washington Court of Appeals, wherein one party to an indemnity agreement attempted to evade its contractual obligations by arguing that certain common law indemnity principles supersede the written terms. This appeal followed a multi-week jury trial from which the client and Ahlers Cressman and Sleight legal team, including Lindsay Watkins, Klien Hilliard, and Christina Granquist, obtained a seven-figure judgment in the client’s favor, including an award of all attorneys’ fees and costs.
ICON was the general contractor on a Vashon Island Highway Pavement project for King County. Part of the work on the project involved hauling away and disposing of ground milled asphalt (the “millings”) at King County-approved sites. ICON and D&R Excavating Inc., (“D&R”) executed a subcontract for D&R to perform that work. The subcontract incorporated the contract between ICON and King County, including the obligation to stockpile millings only at approved sites. D&R, however, did not obtain the requisite approvals from King County, and placed the millings at various sites on the Island, including locations that King County explicitly rejected.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Residential Mortgage Lenders and Servicers Beware of Changes to Rule 3002.1
December 08, 2016 —
James C. Vandermark & Amy E. Vulio – White and Williams LLPThis December, residential mortgage lenders and servicers will be required to comply with new requirements for providing notices of payment changes (PCNs) and post-petition fees, expenses, and charges (PPFNs) to mortgage borrowers in Chapter 13 bankruptcies. While the new Federal Bankruptcy Rule 3002.1 will provide much needed clarity, it will also significantly increase the number of PCNs and PPFNs that lenders will need to file.
Reprinted courtesy of
James C. Vandermark, White and Williams LLP and
Amy E. Vulio, White and Williams LLP
Mr. Vandermark may be contacted at vandermarkj@whiteandwilliams.com
Ms. Vulpio may be contacted at vulpioa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Courthouse Reporter Series: The Travails of Statutory Construction...Defining “Labor” under the Miller Act
August 01, 2023 —
Brendan J. Witry - The Dispute ResolverIn a recent case—United States ex rel. Dickson v. Fidelity & Deposit Co. of Maryland (“Dickson”)—the U.S. Court of Appeals for the Fourth Circuit recently re-examined and defined what work qualifies as “labor” under the Miller Act.
United States ex rel. Dickson v. Fidelity & Deposit Co. of Maryland, No. 21-160, 67 F.4th 182 (4th Cir. April 26, 2023) (slip op.).
Unlike private projects, unpaid subcontractors cannot encumber the federal government’s property with mechanics liens. Instead, the Miller Act provides a remedy for subcontractors in the form of a payment bond on all federal public works contracts exceeding $100,000. 40 U.S.C. § 3131(b).
In the Dickson case, Claimant Elliot Dickson served as a subcontractor to Forney Enterprises (“Forney”), with whom the Department of Defense (the “DOD”) contracted to renovate several staircases and the fire suppression systems at the Pentagon.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Conway & Mrowiec Attorneys LLLPMr. Witry may be contacted at