New York Court of Appeals Finds a Proximate Cause Standard in Additional Insured Endorsements
June 15, 2017 —
Geoffrey Miller - Saxe Doernberger & Vita, P.C.In The Burlington Insurance Company v. NYC Transit Authority, et al., No. 2016-00096, the New York Court of Appeals issued a landmark decision with regard to the meaning of “caused, in whole or in part, by” in the additional insured context. In a split decision, the court rejected Burlington Insurance Company’s argument that the language implied a “negligence” standard, but held that coverage was provided to the additional insured only where the named insured’s acts or omissions were the proximate cause of the injury:
While we [the majority] agree with the dissent that interpreting the phrases differently does not compel the conclusion that the endorsement incorporates a negligence requirement, it does compel us to interpret ‘caused, in whole or in part’ to mean more than ‘but for’ causation. That interpretation, coupled with the endorsement’s application to acts or omissions that result in liability, supports our conclusion that proximate cause is required here.[1]
Read the court decisionRead the full story...Reprinted courtesy of
Geoffrey Miller, Saxe Doernberger & Vita, P.C.Mr. Miller may be contacted at
gjm@sdvlaw.com
John O’Meara is Selected as America’s Top 100 Civil Defense Litigators
December 02, 2019 —
John O'Meara - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce that Partner John V. O’Meara has been selected as a member of America’s Top 100 Civil Defense Litigators. This invitation resulted from a national selection process and is intended to honor the best defense attorneys in the Country. Mr. O’Meara was selected to join a group of lawyers which include past and current state bar presidents, national ABOTA Presidents, ABOTA Masters in Trial and International Academy of Trial Lawyer presidents.
Read the court decisionRead the full story...Reprinted courtesy of
John O'Meara, Bremer Whyte Brown & O'Meara, LLPMr. O'Meara may be contacted at
jomeara@bremerwhyte.com
Delaware “occurrence” and exclusions j(5) and j(6)
June 10, 2011 —
CDCoverage.comIn Goodville Mut. Cas. Co. v. Baldo, No. 09-338 (D. Del. June 2, 2011), claimants condominium association and unit owners sued project developer Rehoboth and general contractor Capano seeking damages because of moisture penetration property damage to common elements and individual units resulting from construction defects. Rehoboth and Capano filed a third party complaint against insured property manager Baldo alleging that, if Rehoboth and Capano were liable to claimants, Baldo was also liable because of Baldo’s failure to properly manage, maintain, and repair the property
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
AI and the Optimization of Construction Projects
February 19, 2024 —
Rahul Shah - Construction ExecutiveSeeking answers on how to construct smarter and greener buildings or improve water efficiency in homes and offices, those who create our buildings and construction projects are entering a new era of learning as they turn their attention to the benefits of artificial intelligence.
While human involvement will continue to be paramount, AI has the potential to assist in creating informed decisions, for example by suggesting sustainable, durable materials or cost-effective, but still safe, practices.
The possible applications of AI for the construction industry could be transformative across design, procurement, construction, operation and decommissioning. In fact,
research suggests designers and contractors are already applying AI and machine learning to manage the volumes of data involved in the design of buildings, the planning of construction projects and the day-to-day operations of sites.
Reprinted courtesy of
Rahul Shah, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
A Brief Primer on Perfecting Your Mechanics Lien When the Property Owner Files Bankruptcy
January 22, 2024 —
William L. Porter - Porter Law GroupOverview of the Mechanics Lien Law
This is a brief description of steps to be taken when the Owner of property on which you have recorded a mechanics lien files bankruptcy.
The California mechanics lien is a powerful tool for contractors, subcontractors and materials suppliers to secure payment of unpaid construction debts. A contractor, subcontractor or materials supplier is allowed to record a mechanics lien on real property, based on the value added to the property by the claimant during the construction process.
The recorded mechanics lien provides the claimant with legal right to force the sale of the improved real property and thereby obtain the funds necessary to pay the delinquent debt. Under the usual procedure, the first step is the recording of the mechanics lien with County Recorder’s office in the County where the property is located. A lawsuit to foreclose on the lien must then be filed in the County Superior Court of that County, within ninety (90) days after the mechanics lien is recorded. The goal of the lawsuit is to obtain a judgment for foreclosure on the mechanics lien in order to force a sale of the property. The net proceeds of the sale will be used to pay the unpaid construction debt secured by the recorded mechanics lien, assuming sale proceeds exceed the amount of senior liens and encumbrances.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
A Court-Side Seat: Environmental Developments on the Ninth Circuit
July 13, 2020 —
Anthony B. Cavender - Gravel2GavelOn May 26, 2020, the U.S. Court of Appeals for the Ninth Circuit decided three significant environmental law cases. Two of these cases involved whether global warming tort cases could be brought in California state courts on, for example, a public nuisance claim, and whether the defendant energy companies had the right to have them removed to the federal courts.
County of San Mateo, et al. v. Chevron Corp., et al. and City of Oakland v. BP PLC, et al.
While acknowledging the immensity of the legal issues, the Ninth Circuit held that the federal removal statutes did not permit these cases to be removed to the federal courts. For one thing, state court jurisdiction was not preempted by the Clean Air Act. Accordingly, the court affirmed the ruling of Federal Judge Chhabria in the Chevron case, and vacated Judge Alsup’s ruling in the BP case that he had jurisdiction to hear this case pursuant to federal common law, and then to dismiss it. The court also remanded the case to Judge Alsup, and directed him to determine if there was an “alternate basis” for federal court jurisdiction based on the pleadings that an issue of ”navigable waters” was a concern.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Automated Weather Insurance Could Offer Help in an Increasingly Hot World
July 10, 2023 —
Michelle Ma - BloombergCarlos José Báez experienced the full brunt of Hurricane Maria when it made landfall in Puerto Rico as a catastrophic storm in 2017.
The auto paint shop owner, who lives in Aguas Buenas, Puerto Rico, saw his home badly damaged by Maria’s ferocious winds and rain. Despite submitting claims to his homeowner’s insurance policy for over $25,000, Báez ultimately received a payout of $11,000.
“We had a lot of property damage and insurance, but they didn’t want to pay,” Báez said in an interview in Spanish.
More than
$1.6 billion in insurance claims remained unresolved more than two years after Maria while others were denied completely. The latter happened to Jonathan González’s mother, who waited nearly a year for an adjuster to come take photos of water damage and a broken wheelchair ramp only for the claim to be denied six months later.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Ma, Bloomberg
MTA’S New Debarment Powers Pose an Existential Risk
July 15, 2019 —
Steven M. Charney, Gregory H. Chertoff & Paul Monte - Peckar & Abramson, P.C.The normal project and contractual risks faced by contractors, consultants and suppliers to the Metropolitan Transportation Authority are considerable. A new law and regulations mandating that the MTA debar contractors, consultants and suppliers for unexcused schedule and cost overruns creates a new and unfair existential risk.
The new law, Public Authorities Law Section 1279-h, slipped into the New York State budget bill and passed without public comment, was enacted on April 12, 2019. Implementing regulations were issued on June 5, 2019, and mandate that the MTA debar contractors (defined to include consultants, vendors and suppliers) if they: (1) fail to achieve substantial completion of their contractual obligations within 10% of the adjusted contract time; or (2) present claims for additional compensation that are denied in an amount that exceeds the total adjusted contract amount by 10% or more.[1]
To say that your business and your livelihood are at risk is not an overstatement. The MTA umbrella includes the New York City Transit Authority, MTA Capital Construction, Bridges & Tunnels, Long Island Railroad and Metro North, among others. A debarment by one of these authorities will lead to a debarment by all of them, and then to a debarment by all New York State agencies and authorities,[2] and possibly debarment across state lines. Public and major private owners, as part of their RFP and procurement processes, routinely inquire regarding a bidding contractor’s debarment history.
The risk is to new contracts and, because the MTA has decided to give retroactive effect to the law and regulations, to contracts that are already ongoing (even though these risks could not have been considered, priced or agreed to by contractors or their sureties).
Reprinted courtesy of Peckar & Abramson, P.C. attorneys
Steven M. Charney,
Gregory H. Chertoff and
Paul Monte
Mr. Charney may be contacted at scharney@pecklaw.com
Mr. Chertoff may be contacted at gchertoff@pecklaw.com
Mr. Monte may be contacted at pmonte@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of