Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Public Contract Code Section 1104 Does Not Apply to Claims of Implied Breach of Warranty of Correctness of Plans and Specifications
October 30, 2023 —
Garret Murai - California Construction Law BlogIt’s the classic tale of two cities. One city is occupied by architects and engineers. The other, by contractors. And while the cities typically co-exist relatively peacefully together, at times, they do not, such as when a defect arises that can either be a design or construction defect.
Sometimes, project owners are pulled into these fights as well. There is a common law rule that when contracting with a contractor the owner impliedly warrants to the contractor that the plans and specifications are sufficiently accurate and correct.
And, if you work on local public works projects, you may be familiar with Public Contract Code section 1104 which provides that, with the exception of design-build projects, local public entities cannot require a bidder to assume responsibility for the completeness and accuracy of architectural or engineering plans and specifications.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
City Potentially Liable for Cost Overrun on Not-to-Exceed Public Works Contract
June 29, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPOn a public works construction project, a contractor incurred additional costs and asserted a claim against the city. The city denied the claim because the contract had a not-to-exceed price, and the city council and mayor did not approve contract modifications to exceed that amount. City ordinances require approval for contract modifications and change orders exceeding ten percent of the original not-to-exceed amount.
But the contractor argued that the ordinance did not apply because the excess costs did not result from a contract modification or change order. In addition, the contractor argued that, in refusing to approve an increase in the not-to-exceed amount, the city breached the implied duty of good faith and fair dealing. The court concluded that these questions were factual issues for the jury to decide.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Union Handbilling: When, Where, and Why it is Legal
November 06, 2018 —
Wally Zimolong - Supplemental ConditionsA few days ago, IBEW Local 98 began began protesting a restaurant owned by professional football player Jahri Evans. The organizers are accusing Evans of violating local construction wage standards and are advertising their dispute with “handbills.”
What are handbills?
Walking down Fremont Street in Las Vegas is impossible without one or several characters putting a small business card with “questionable” adult entertainment advertisements in your hand. Some will slap papers to your chest, leaving you no choice but to grab the flyers.
On a different level, this action occurs on a regular basis by union member. But instead of shady characters pushing questionable entertainment, it is union representatives pushing a dispute with a local employer over working conditions. However, in either case the practice is known as i as handbilling.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Drought Dogs Developers in California's Soaring Housing Market
September 17, 2015 —
John Gittelsohn – BloombergCalifornia’s already tight housing market is facing another long-term complication: drought.
The state’s dry spell is creating challenges for developers at a time when home prices are soaring because of limited inventory. The metropolitan areas of San Jose, San Francisco and San Diego had the nation’s biggest gap between the number of new jobs and residential building permits from 2012 to 2014, according to a report Wednesday by the National Association of Realtors. Now the drought, into its fourth year, stands to curb affordability further.
“It’s contributing to price appreciation by restricting supply,” said Mark Boud, founder of Real Estate Economics, a housing-consulting firm based in Irvine, California.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, Bloomberg
Zinc in London Climbs for Second Day Before U.S. Housing Data
January 21, 2015 —
Alex Davis – BloombergZinc rose for a second day and copper held gains before data showing increased housing construction in the U.S. and a stimulus decision by the European Central Bank.
Zinc advanced as much as 0.8 percent. Housing starts in the U.S., the second-largest metals consumer, climbed 1.2 percent in December from the previous month, according to a Bloomberg survey, after falling 1.6 percent in November. The ECB will announce a 550 billion-euro ($636 billion) government-bond purchase program this week, according to 93 percent of respondents in a separate survey.
Read the court decisionRead the full story...Reprinted courtesy of
Alex Davis, BloombergMr. Davis may be contacted at
adavis150@bloomberg.net
Quick Note: Expert Testimony – Back to the Frye Test in Florida
December 19, 2018 —
David Adelstein - Florida Construction Legal UpdatesExpert testimony (opinions) – very important testimony in construction disputes. Whether it is a delay claim, an inefficiency claim, a defect claim, etc., expert testimony plays an invaluable role in construction disputes. Construction attorneys work closely with expert witnesses to ensure that an expert helps render an opinion to support their client’s burden of proof (including damages) or an affirmative defense.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Thanks for Four Years of Recognition from JD Supra’s Readers’ Choice Awards
May 20, 2019 —
Garret Murai - California Construction Law BlogA big thank you to the folks at JD Supra and its readers for recognizing us in its Construction category for its 2019 Readers’ Choice Awards! We’re honored to be among the 228 authors recognize for their visibility, engagement and thought leadership out of more than 50,000 who have published articles on JD Supra this past year.
Congratulations as well to the other JD Supra 2019 Readers’ Choice Award recipients whose hard work encourages us to be better authors.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com