Defects, Delays and Change Orders
November 01, 2021 —
Jacob A. Epstein - Construction ExecutiveAs every construction professional is aware, unexpected events and problems are guaranteed on every large project. Defects, delays and change orders are sure to arise, and depending on how they are dealt with and addressed at the time, they can either have minimal effects on the overall project or they can have drastic, long-term and often costly effects, including but not limited to thousands of dollars in legal fees, increases in insurance premiums and/or years of litigation down the road.
There are many reasons why so many large construction projects end up in some type of litigation. Delay claims, construction contract disputes and construction defect lawsuits are so prevalent in certain parts of the country that certain judges designate specific time blocks in their courtrooms for construction cases only—just to deal with the large portions of their case dockets dealing with construction issues at the same time.
Reprinted courtesy of
Jacob A. Epstein, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Epstein may be contacted at
jepstein@haber.law
Disjointed Proof of Loss Sufficient
June 11, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found that when considered as a whole, separately filed proofs of loss and estimates of damage were sufficient to meet the requirements of a flood policy. Young v. Imperial Fire & Cas. Ins. Co., 2014 U.S. Dist. LEXIS 51863 (April 15, 2014).
On August 29, 2012, plaintiffs' property sustained flood damage due to Hurricane Isaac. After Imperial's adjustor inspected the property, advance payments were made for $5000 under the building coverage and $5000 under the contents coverage.
On October 26, 2012, the plaintiffs' adjustor submitted a proof of loss for building damages, stating the amount of loss was $175,100, which was the policy limit minus the deductible. The insured wife signed the proof of loss. The actual case value, full cost of replacement or repair, and applicable depreciation were listed "undetermined."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
OIRA Best Practices for Administrative Enforcement and Adjudicative Actions
November 23, 2020 —
Anthony B. Cavender - Gravel2GavelOn March 2, 2020, the Environmental Protection Agency revised its “On-Site Civil Inspection Procedures” in accordance with Executive Order 13892 . (The rules are located at 40 CFR Part 31.) These rules set forth the components of an appropriate inspection procedure. Briefly, the rules require that, after the inspector’s credential are made available, the object of the inspection will be discussed (and most inspections will be held during regular working hours), consent to enter must be obtained, there should be an opening and a closing conference with facility representatives, safety protocols must be observed, confidential business information must be protected, and there will be an opportunity for split sampling. Once the report is completed, it will be shared with the facility.
A few months later, on August 31, 2020, the Office of Management and Budget’s Office of Information and Regulatory Affairs (OIRA) circulated a memo to the heads of all federal agencies to implement the principles of fairness in administrative enforcement and adjudication. This directive implements Executive Order 13924, and includes a comprehensive list of “best practices” that should be employed in their administrative enforcement and adjudicative actions. Briefly, these best practices (which are framed in broad terms) are:
1. The government has the burden of proving a violation of the rules or other authorities;
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Manhattan Developer Wants Claims Dismissed in Breach of Contract Suit
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Real Deal reported that Savannah, the developer of the condo conversion at 141 Fifth Avenue, “has filed to dismiss a number of claims in a $7.5 million breach of contract lawsuit by the property’s board of managers, while alleging professional negligence against several of its own contractors.”
Savanah’s lawyers stated, according to The Real Deal, that whether or not construction defects exist, their client isn’t responsible: “However to the extent that any of the alleged defects exist at the building, sponsor cannot be held liable for the existence of such defects.”
Read the court decisionRead the full story...Reprinted courtesy of
Subcontractor Allowed to Sue Designer for Negligence: California Courts Chip Away at the Economic Loss Doctrine (Independent Duty Rule)
August 30, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCAn architect may have to pay over $1 million to a subcontractor who was contractually obligated to rely on the designer’s plans – even though the architect was not a party to the contract.[1] That was the ruling in U.S. f/u/b/o Penn Air Control, Inc. v. Bilbro Constr. Co., Inc.[2]
The dispute involved a $7.3 million design-build contract award to Bilbro Construction (“Bilbro”) to renovate a facility for the Naval Facilities Engineering Command in Monterey, California. Bilbro hired an architect (“FPBA”) to serve as the designer of record and provide all the architectural design services. FPBA’s design team included an acoustical sub-consultant (Sparling). The general contractor (design builder) also retained Alpha Mechanical (Alpha) as the mechanical electrical and plumbing (“MEP”) design/build subcontractor. Alpha, in turn, subcontracted the MEP design to Shadpour Consulting Engineers. During the design phase of this project, Alpha’s MEP design was reviewed by FPBA, Bilbro, and Sparling at the 35, 75, and 100 percent design completion levels. Alpha demonstrated that it regularly received direct communications during design development from Sparling and FPBA, including comments, changes, and revisions. One example Alpha cited was it raised some concerns about anticipated noise level in eight rooms. Sparling made several recommendations to Alpha and Shadpour that were implemented.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Is Your Construction Business Feeling the Effects of the Final DBA Rule?
June 04, 2024 —
Nathaniel Peniston - Construction ExecutiveThe Biden administration’s final rule “Updating the Davis-Bacon and Related Acts Regulations” took effect on Oct. 23, 2023. In “the first comprehensive regulatory review in nearly 40 years,” the Department of Labor has returned to the definition of “prevailing wage” it used from 1935 to 1983—before Microsoft released the first Windows operating system.
Construction industry leaders must be aware that this is the most comprehensive review and overhaul of the act in 40 years; with it, the DOL has attempted to modernize its approach to wage creation and fringe benefit allocation. There are more than 50 procedural changes to the act, which means it is very important for contractors to be aware of wage classifications when bidding, performing work on Davis-Bacon Act projects and using applicable fringe dollars for bona fide benefits.
UNDERSTANDING THE CHANGES
Some of the critical adjustments included in the final rule that contractors should be aware of include:
Wage determination changes during a project: Historically, contractors could rely on the wage determinations used to win a project for the life of the project. However, the final rule now requires the contractor to use current wage determinations when a contract is changed or extended. The DOL “proposed this change because—like a new contract—the exercise of an option requires the incorporation of the most current wage determination.”
Reprinted courtesy of
Nathaniel Peniston, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Peniston may be contacted at
npeniston@fbg.com
Slavin Doctrine and Defense from Patent Defects
June 13, 2018 —
David Adelstein - Florida Construction Legal UpdatesThe Slavin doctrine is an affirmative defense primarily geared to the personal injury context designed to protect contractors from third-party negligence-type claims when an owner accepts a patent defect.
The Slavin doctrine protects contractors from liability for injuries to third parties by presuming that the owner has made a “reasonably careful inspection” of the contractor’s work prior to accepting it as completed; if the owner accepts the contractor’s work as complete and an alleged defect is patent, then the owner “accepts the defects and the negligence that caused them as his own,” and the contractor will no longer be liable for the patent defect.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Notice of Completion Determines Mechanics Lien Deadline
August 13, 2019 —
William L. Porter - Porter Law GroupThe California Mechanics Lien is one of the most valuable collection devices available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California Private Works project. The mechanics lien allows the claimant to sell the property where the work was performed in order to obtain payment. The process starts with the recording of a mechanics lien in the office of the County Recorder where the property in question is located. As noted below, certain deadlines must be met.
Know Your Mechanics Lien Filing Deadlines Generally
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a ”direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The primary differences are that, the direct contractor is only required to serve the “Preliminary Notice” on the Construction Lender (Civil Code section 8200-8216), whereas the subcontractor and material supplier must serve not only the Construction Lender, but also the Owner and Direct Contractor (see Civil Code section 8200(e)). Another difference is that a direct contractor has a longer period of time in which to record a mechanics lien after a valid “notice of completion” or a “notice of cessation” has been recorded (Civil Code sections 8180-8190), (60 days for original contractors as compared to 30 days for subcontractors and suppliers – See Civil Code sections 8412 and 8414). A further general description of the rules is as follows:
Read the court decisionRead the full story...Reprinted courtesy of