Hawaii Court Finds No Bad Faith, But Negligent Misrepresentation Claim Survives Summary Judgment in Construction Defect Action
November 06, 2013 —
Tred Eyerly — Insurance Law HawaiiJudge Mollway, U.S. District Court Judge for the District of Hawaii, found the insurer was not in bad faith for allegedly leading its insured to believe that construction defects would be covered under the policy. The court, however, allowed the insured's negligent misrepresentation claim to survive summary judgment. Ill Nat'l Ins. Co v. Nordic PCL Constr., 2013 U.S. Dist. LEXIS 151748 (D. Haw. Oct. 22, 2013).
The insurer denied coverage when Nordic was sued for construction defects related to its construction of two Safeway stores in Honolulu. Prior to the issuance of the policies the Ninth Circuit had issued its opinion in Burlington Ins. Co. v .Oceanic Design & Constr., Inc., 398 F.3d 940 (9th Cir. 2004), which predicted that Hawaii appellate courts would rule that construction defects were not "occurrences." Nevertheless, Nordic's witnesses contended when the policies were purchased, they believed construction defects were covered. Specifically, Nordic thought the policies provided completed operations coverage for property damage arising out of Nordic's subcontractors' work.
Nordic further contended that only after the Hawaii Intermediate Court of Appeals decided in Group Builders, Inc. v. Admiral Ins .Co., 123 Haw. 142 (Haw. Ct. App. 2010) that construction defect claims did not constitute an "occurrence" did the insurer change its position and decide the policies did not cover construction defects.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
No Additional Insured Coverage Under Umbrella Policy
March 12, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe additional insured was not covered under a property policy for an injury occurring after work was completed. Lewark v. Davis Door Servs., 2014 Wash. App. LEXIS 341 (Wash. Ct. App. Feb. 10, 2014).
Public Storage, Inc. hired Davis Door Service Inc. to perform work at its facilities. The master agreement required Davis Door to maintain a CGL policy that insured Public Storage "during the entire progress of the work." Davis Door secured a CGL policy with American Economy. It also took out an umbrella liability policy with American States.
After Davis Door completed work on a door, Terrie Lewark injury her back opening the door. She sued Public Storage and Davis Door. Lewar and Public Storage settled. Public Storage assigned to Lewark its rights under the umbrella policy with American States. Lewark then sued Davis Door and American States. The trial court found that Public Storage was not an additional insured under the American States umbrella policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Florida Contractor on Trial for Bribing School Official
October 28, 2011 —
CDJ STAFFLloyd Whann, an executive in M. M. Parrish Construction, a Gainesville, Florida firm, is going to trial over claims that he bribed a school district official with more than $50,000 in gifts. The trial has been pushed to March of 2012, in order for his defense to review documents.
Bob Williams, the former school official, plead guilty to conspiracy to commit bribery. He agreed to testify against Whann and M.M. Parrish Construction.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
If You Can’t Dazzle Em’ With Brilliance, Baffle Em’ With BS: Apprentices on Public Works Projects
October 24, 2023 —
Garret Murai - California Construction Law BlogThe “Big Four” when it comes to public works contracting on state and local projects in California are:
- Registration with the California Department of Industrial Relations (“DIR”);
- Payment of prevailing of wages and maintenance and submission of certified payroll;
- Compliance with the “skilled and trained workforce” requirements on certain projects; and
- Hiring apprentices on state and local public works projects with a value of $30,000 or more.
The next case,
GRFCO, Inc. v. Superior Court, 89 Cal.App.5th 1295 (2023), discusses the last of these requirements. The case also reminded me of W.C. Field’s old saying – “If you can’t dazzle em’ with brilliance, baffle em’ with bullshit” – and which ended with expected results.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Work to Solve the Mental Health Crisis in Construction
September 05, 2022 —
Bruce Morton & Diane Andrea - Construction ExecutiveThe suicide rate for construction is one of the highest among major industries. That statistic is from a 2018 report from the Centers for Disease Control and Prevention. And it’s one major reason why the concern about mental health in the construction industry has grown. Research shows that as many as 90% of all people who die by suicide have a mental health condition. Depression is the most common cause, but other conditions such as substance use disorders may have an impact as well.
What is causing mental health conditions in the construction industry? According to the U.S. Bureau of Labor Statistics, 97% of the U.S. construction industry is male—and men experience the highest rate of suicides. Yet, while the suicide rate for women in construction is lower than that for men in the construction industry, it appears to be much higher than the suicide rate for the general female population. Being “tough” and “strong” are highly valued; acknowledging mental health concerns—or even seeking help—may be considered a sign of weakness. There is often fear of shame and judgment for admitting you have a problem.
In addition, the nature of construction industry jobs may affect mental health. Injuries may cause chronic pain, which can result in substance disorders like opioid use. Seasonal work can result in layoffs, which puts a strain on family relationships and finances. The job is high-stress and the work is deadline-driven. Employees work long hours, potentially resulting in fatigue. Sometimes work is away from home for extended periods. The pandemic has exacerbated every other problem while creating its own.
Reprinted courtesy of
Bruce Morton and Diane Andrea, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Morton may be contacted at bruce.morton@marshmma.com
Ms. Andrea may be contacted at Diane.Andrea@MarshMMA.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Termination Issues Part 4: What to Do When They Want to Fire You, the Architect or Engineer
August 14, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaWhat if you are told that your own design services are no longer needed or welcome on a project? Can they do that? What happens then? How do you protect yourself.
As you probably realize, while rare, the Owner does have the legal right to fire you “for cause”. See B101 §9.4, as long as the Owner gives you 7 days written notice. In fact, the Owner can terminate your contract for any reason at all (maybe you root for the wrong basketball team?) by terminating you for convenience (i.e., for any reason whatsoever) under B101 §9.5, again with 7 days written notice.
As with
Contractor terminations, the money you get when fired for convenience is much greater than when you are terminated for cause. If you are fired “for convenience”, you get paid for all services previously rendered as well as termination expenses, including anticipated profit on the value of services not performed. See B101 §9.7.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Congratulations to Arezoo Jamshidi & Michael Parme Selected to the 2022 San Diego Super Lawyers Rising Stars List
April 04, 2022 —
Arezoo Jamshidi & Michael C. Parme - Haight Brown & Bonesteel LLPCongratulations to Arezoo Jamshidi and Michael Parme who were selected for the 2022 San Diego Super Lawyers Rising Stars list. The 2022 San Diego Rising Stars list is an honor reserved for lawyers who exhibit excellence in practice. Only 2.5% of attorneys in San Diego receive this distinction.
Reprinted courtesy of
Arezoo Jamshidi, Haight Brown & Bonesteel, LLP and
Michael C. Parme, Haight Brown & Bonesteel, LLP
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Revisiting the CMO; Are We Overusing the Mediation Privilege?
November 19, 2021 —
Michael T. Kennedy Jr. - BERDING|WEILOne of the most common features in construction defect cases is the Case Management Order (“CMO”) or Pre-Trial Order (“PTO”) to govern pre-trial and mediation procedures. CMOs and PTOs arose in the days when the HOA would sue the developer, the developer would cross-complaint against the subcontractors, and each defendant and cross-defendant might have 2 or 3 insurance carriers defending, each of whom may retain their own panel counsel. In a large case there may have been 20 parties and 30 defense attorneys. In order to avoid the cost and chaos of all of those parties propounding their own discovery, and in order to prepare these cases for mediation well before trial and the associated costs, it became standard practice in California to include provisions in the CMO to stay all discovery until just before trial.
Plaintiff would provide a Defect List or Statement of Claims and the parties experts would meet and exchange information as part of the mediation process. All of the information exchanged would be subject to mediation privileges and inadmissible at trial. The benefit of this practice was that the parties (and carriers) would avoid the cost of formal discovery and allow the experts to discuss compromised scopes of repair to help settle the case while being able to take a more aggressive position at trial. The disadvantages are that each party uses its privileged initial expert reports to stake out negotiating positions more extreme than what they would put on at trial, with each side losing credibility with the other in assessing the value of the case, and for those cases that did not settle, the parties would be faced with having to do all of the depositions and discovery in the last 60 days, or delaying trial, or both.
Over the last 10 or 15 years with the advent of wrap-up insurance policies, these cases now usually involve 2 sides instead of 20; only the HOA and the developer remain in the case. However, old habits die hard, and the standard CMO/PTO hasn’t evolved with other aspects of these cases. The practice of staying all discovery and exchanging information only under mediation privileges remains, and as a result insurance carriers don’t receive the admissible evidence that they need to determine coverage and evaluate the real settlement value of the case until just before trial. On the plaintiff’s side, if most of the experts’ work is done under the guise of mediation privilege, those costs may not be recoverable. Outside the context of mediation, costs incurred in investigation of the defects and preparation of a scope and cost of repair are recoverable.
This reflexive claim of mediation privilege over all information exchanged during the case has outlived its usefulness. The CMO can and should remain to regulate formal discovery and to help the parties prepare for mediation, but regulated discovery should be opened early in the case. In California, the SB800 process already provides for the exchange of admissible information during the prelitigation right to repair process. Continuing that exchange during the early litigation allows the parties to continue to prepare for mediation, but waiving privileges had advantages for both sides.
A senior claims manager once commented that Plaintiff’s mediation-protected Statement of Claims “might as well be a stack of blank paper” for all of its usefulness to the carrier in assessing the value of the case. If the Plaintiff and it expects are free to inflate their claims early in the case without having to worry about every supporting those claims in front of a jury, they have little or no credibility. And if those claims are inflated or not “real,” not only can the carrier not properly assess the verdict range and settlement value of the case, but it may also be hampered in making a coverage determination. Simply put, if the exchange of real information through formal discovery is put off until just before trial, the defense cannot be ready to settle until then. Worse, the cost of defense goes through the roof in the last 60 days before trial as the lawyers’ scramble to take all of the depositions and to all of the other work that had been stayed for the previous year or two.
The Plaintiff is faced with the same question of credibility of defense experts where they are free to take a “low ball” negotiating position without having to support that position through cross-examination in front of the jury. Just as the carrier behind the defense attorney needs the Plaintiff’s “real” evidence to assess the claim, so does the HIOA Board of Directors behind the Plaintiff’s counsel. Additionally, in California as in most states, the cost of experts’ preparation for mediation may not be recoverable as costs or damages, but investigation of the defects and preparation of the scope and cost of repair is recoverable.
The biggest challenge is resolving construction defect claims for both sides is how to resolve these cases quickly while keeping costs under control. Practices that worked 20 years ago are no longer applicable with changes in insurance, and in light of some of the bad habits that arise when all of the information exchanged was confidential.
The CMO/PTO process can still be useful to regulate the discovery and mediation schedule given the volume of documents and other information to be exchanged but exchanging “real” information in a form that may come into evidence at trial should foster earlier resolution, resulting in cost savings for the parties. The CMO can provide for the parties to respond to controlled discovery, and the exchange of expert reports and potentially depositions can and should be done earlier in the case, well before the eve of trial. The parties can then assess the true value of each case and prepare for more substantive mediation without waiting until they are on the figurative courthouse steps.
Construction defect cases have a pattern, and it is tempting for busy lawyers to just put each case through the same algorithms that they have used for years. However, these cases have evolved and those of us handling these cases need to reevaluate our approach to these cases. Taking aggressive negotiating positions that no longer have any credibility with the other side has become counterproductive, and the exchange of real evidence earlier in the case would better serve our clients and carriers.
BERDING|WEIL is the largest and most experienced construction defect and common interest development law firm in California. For more information, please visit https://www.berding-weil.com
Read the court decisionRead the full story...Reprinted courtesy of
Michael T. Kennedy Jr., BERDING|WEILMr. Kennedy may be contacted at
mkennedy@berdingweil.com