Contract Change # 10: Differing Site Conditions (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaPreviously, the A201 required a Contractor to provide notice to the Owner and Architect within 21 days after discovery of unforeseen site conditions. This notification is required prior to the conditions being disturbed, so as to allow the Design Team the ability to evaluate the site and determine the compensability of any such differing conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
Trumark Homes Hired James Furey as VP of Land Acquisition
April 08, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to GlobeSt.com, “Homebuilder Trumark Homes has hired James Furey as VP of land acquisition.” The “veteran developer” has held positions at Meritage Homes, Richmond American Homes, and Beazer Homes USA.
“James is a versatile manager who brings a wealth of experience in many elements of the homebuilding process,” Jason Kliewer, partner and general counsel for Trumark, told GlobeSt.com. “He will be an invaluable asset as Trumark moves aggressively in the California market.”
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Federal District Court Compels Appraisal
December 03, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Hawaii federal district court denied the insurers' motion to dismiss on forum non convenient grounds and granted the insured's motion to compel arbitration. BRE Hotels and Resorts LCC, et al. v. Ace Am Ins. Co., et al., 2024 U,.S. Dist. LEXIS 163852 (D. Haw. Sept. 11, 2024).
BRE Hotels & Resorts LLC (BRE) owned the Grand Wailea Resort on Maui and the Turtle Bay Resort on Oahu. Both hotels were damaged by a rainstorm on March 9, 2021. Estimated losses exceeded $55 million. BRE filed a claim with its sixteen insurers. BRE sought $46 million in four categories: business interruption losses at the Grand Wailea ($29.6 million); damaged tiles at the Grand Wailea ($8.3 million); furniture, fixtures, and equipment at Turtel Bay ($6.2 million); and an assortment of ancillary issues at both properties ($1.9 million).
The insurers investigated and took issued with BRE's estimates. The insurers contended that most of the tiles suffered from an independent defect and were not damaged by the storm, that the insurance policies did not cover the replacement of undamaged furniture, and that the claimed business interruption losses were too high. The insurers paid $4 million.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Surge in Home Completions Tamps Down Inflation as Fed Meets
June 17, 2015 —
Carlos Torres – BloombergAmerican builders are tamping down what little inflation there is.
Construction companies completed 392,000 buildings with five or more units at an annualized rate in May, the most since 1988, Commerce Department figures showed Tuesday in Washington.
“The pickup in demand is pushing up rents and also creating more incentive for builders to put up more units,” said Michael Hanson, a senior economist at Bank of America Corp. in New York. The jump in completions “helps offset some of the upward pressure we’ve seen” on rents, said.
Read the court decisionRead the full story...Reprinted courtesy of
Carlos Torres, Bloomberg
Sureties and Bond Producers May Be Liable For a Contractor’s False Claims Act Violations
October 19, 2017 —
Michael C. Zisa & Susan Elliott – Peckar & Abramson, P.C.Two recent decisions from the United States District Court for the District of Columbia and the United States Court of Federal Claims highlight that sureties and bond producers are not immune to the potentially severe consequences of the False Claims Act (“FCA”) and related federal fraud statutes. In each case, the Court determined that sureties and bond producers can face potential liability under these fraud statutes for direct and indirect submission of false claims to the federal government.
Reprinted courtesy of
Michael C. Zisa, Peckar & Abramson, P.C. and
Susan Elliott, Peckar & Abramson, P.C.
Mr. Zisa may be contacted at mzicherman@pecklaw.com
Ms. Elliott may be contacted at selliott@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Reconstructing the Francis Scott Key Bridge Utilizing the Progressive Design-Build Method
June 04, 2024 —
Lisa D. Love - The Dispute ResolverHaving awakened on the morning of March 26 to the devastating news of the collapse of Baltimore’s Francis Scott Key Bridge after being struck by the Dali, a 984 length /52 beam foot cargo container ship, I thought of the many times I crossed the bridge as a child growing up in Washington, D.C. I also recalled Montgomery Schyler’s comments on the opening of the Brooklyn Bridge, when he stated that “the work which is likely to be our most durable monument, and to convey some knowledge of us to the most remote posterity, is a work of bare utility; not a shrine, not a fortress, not a palace, but a bridge.”
I thought of the beauty of New York’s Mario Cuomo Bridge, a 3.1-mile cable-stayed twin-span bridge with eight traffic lanes, bicycle and pedestrian paths, six lookout points and room for future rapid transit. It was completed in 2018 and constructed under a design-build procurement model[i] at a cost of $3.98 billion. Accelerated bridge construction (ABC) techniques were utilized in its construction. ABC techniques employ innovative planning, design, materials, and construction methods in a safe and cost-effective manner to reduce the on-site construction time that occurs when building new bridges or replacing and rehabilitating existing ones. ABC techniques improve site constructability, total project delivery time, work-zone safety for the traveling public and traffic impacts, on-site construction time, and weather-related time delays.[ii]
I also thought of the gracefulness of Boston’s Leonard P. Zakim Bunker Hill Memorial Bridge, a 0.27-mile hybrid cable-stayed steel and concrete bridge with pedestrian and bicycle access that holds 10 lanes of traffic. The Zakim Bridge was completed in 2004 at a cost of approximately $100 million as part of the $24.3 billion Big Dig.[iii] Despite its elegant, streamlined appearance, the bridge was designed to be exceptionally strong, withstand winds over 400 miles per hour and endure a magnitude 7.9 earthquake.[iv]
Read the court decisionRead the full story...Reprinted courtesy of
Lisa D. Love, JAMS
Fifth Circuit -- Damage to Property Beyond Insured’s Product/Work Not Precluded By ‘Your Product/Your Work Exclusion’
January 24, 2022 —
Anthony L. Miscioscia & Marianne Bradley - White and Williams LLPOn January 11, 2022, the United States Court of Appeals for the Fifth Circuit issued its decision in Siplast, Incorporated v. Employers Mutual Casualty Company, 2022 U.S. App. LEXIS 795 (5th Cir. Jan. 11, 2022), finding that an insurer had a duty to defend its insured in a construction defect case where the underlying complaint alleged damage to property beyond the product and work of the insured.
Siplast, Inc. (Siplast) had contracted with the Archdiocese of New York (the Archdiocese) to install a roof membrane system at a high school in the Bronx, New York. Id. at *1. As part of the contract, Siplast guaranteed that the roof membrane system would remain in a watertight condition for at least twenty years. Id. at *2. If it did not, Siplast would repair the roof membrane system at its own expense. Id.
Several years after the installation, the Archdiocese observed water damage in the ceiling tiles at the high school. Id. The Archdiocese contacted Siplast, who attempted to repair the damage and prevent further leaks; however, leaks and resultant damage continued to occur. Id. Siplast subsequently refused to make any more improvements to the roof. Id.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Marianne Bradley, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Bradley may be contacted at bradleym@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
A Look Back at the Ollies
May 03, 2018 —
Beverley BevenFlorez-CDJ STAFFThe Jerrold S. Oliver Award of Excellence, also known as the “Ollie” award, is presented to “an individual who is outstanding or has contributed to the betterment of the construction defect community.” West Coast Casualty asks members of the construction defect community to nominate those they feel are deserving of the award, and then members vote for one of four nominees. The award is presented at the West Coast Casualty Seminar. Those recognized receive a plaque and a donation in the winner’s name to Habitat for Humanity as well as a local California and Nevada charity.
Jerrold S. Oliver was a “’founding father’ in the alternate resolution process in construction defect claims and litigation. His loyalty and commitment to this community were beyond mere words as he was a true believer in the process of resolution.”
Past Award Winners:
1996 - Awarded to Ross R. Hart, Esq. (Mediator - American Arbitration Assoc.)
1997 - Awarded to Merv Thompson, Esq. (Mediator in private practice)
1999 - Awarded to Tom Craigo, (Adjuster - C.N.A. Insurance Company)
2000 - Awarded to Kristi Cole, (Adjuster - Safeco Insurance Company)
2001 - Awarded to Karen Rice, (Claims Manager - ACE / USA)
2002 - Awarded to Stephen Henning, Esq. (Wood, Smith, Henning and Berman, LLP)
2003 - Awarded to Ross Feinberg, Esq. (Feldscott, Lee, Feinberg, Grant and Mayfield LLP)
2004 - Awarded to Janet Shipes (Adjuster – C.N.A. Insurance Company)
2005 - Awarded to Edward Martinet (Expert – MC Consultants)
2006 - Awarded to Hon. Victoria V. Chaney (Judge – Los Angeles Superior Court)
2007 - Awarded to Bruce Edwards, Esq. (Mediator) JAMS
2008 - Awarded to Gerald Kurland, Esq. (Mediator) JAMS
2009 - Awarded to Keith Koeller, Esq. (Koeller, Nebecker, Carlson and Haluck, LLP)
2010 - Awarded to Terry Wolcott – (Construction Defect Manager – Travelers Ins. Co.)
2011 - Awarded to George Calkins, Esq. (Mediator) JAMS
2012 - Awarded to Joyia Greenfield, Esq. (Lorber, Greenfield and Polito, LLP)
2013 - Awarded to Margee Luper (Claim Manager – XL Insurance Group)
2014 - Awarded to Matt Liedle, Esq. (Liedle, Lounsbery, Larson & Lidl, LLP)
2015 - Awarded to Robert A. Bellagamba, Esq. (Special Master/Mediator, Castle & Dekker)
2016 - Awarded to Lisa Unger, (Senior Claims Examiner, Global Management Liability Markel)
2017 - Awarded to Caryn Siebert, (Vice President, Claims, Knight Insurance Group)
Read the court decisionRead the full story...Reprinted courtesy of