Insurance Policy Provides No Coverage For Slab Collapse in Vision One
August 17, 2011 —
Douglas Reiser, Builders Council BlogThis post will examine whether Division Two of the Washington Court of Appeals properly reversed and remanded several lower court decisions in the case of Vision One LLC v. Philadelphia Indemnity Insurance. In short, and from the perspective of an appellate attorney, the court of appeals got the decision right. Given the rules of contract interpretation and causation in tort claims, there was really no other way the court could have ruled. I understand that from a contractor’s perspective and insurance perspective, the decision seems odd. But from a purely legal standpoint, the decision is well-reasoned and well-supported. Let me explain.
Background
First, here are the facts in a nutshell. Vision One is a construction company that undertook to construct a condo complex in Tacoma. Vision then contracted with D&D Concrete to pour a concrete slab for a section of the foundation. To shore the concrete slab, D&D further contracted Berg Equipment to provide necessary equipment to stabilize the structure. Well, something down the line went wrong. The shoring failed and the slab collapsed, causing a great deal of damage.
Read the full story…
Read the court’s decision…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Underpowered AC Not a Construction Defect
November 07, 2012 —
CDJ STAFFAfter buying a home in Louisiana, Mike Gines determined that the home’s air conditioning unit was insufficient to maintain an appropriate temperature. He contacted the home builder, D.R. Horton, Inc., which worked with the air conditioning installer, Reliant Heating & Air Conditioning, in order to repair the system. When the problems persisted, Gines filed a class action petition against Horton and Reliant in state court. Horton and Reliant moved the case to the federal courts, whereupon Gines asserted the defendants were in violation of the Louisiana New Home Warranty Act (NHWA). Horton stated that the claim under the NHWA was invalid, because Gines had not alleged actual physical damage to his home.
The district court granted Horton’s motion to dismiss. Gines sought a reversal from the Fifth Circuit Court of Appeals and sought to have two questions of state law addressed by the Louisiana Supreme Court.
The district court ruled that the NHWA was the “sole remedy under Louisiana law for a purchaser of a new home with construction defects. Gines argued that court erred in this, but also conceded that this was the conclusion of the Louisiana Supreme Court.
Further, Gines argued that a provision in the NHWA that allows the inclusion of construction defects that do not cause damage was satisfied by paragraph 6 of the contract. The court noted that Gines did not attach a copy of the contract to either the original or amended complaint, and so the court does not need to address these claims. However, the court cautioned that if a copy had been included, they still would have rejected the claim, as “the cited language does not indicate a waiver of the physical damage requirement.” They also note that “paragraph 13 of the contract shows that Gines was aware to the absence of any such waiver in the contract.”
The court concludes that “the moral of this story is that in order to avoid the harsh result that has obtained here, the buyer of a newly constructed home in Louisiana should seek to obtain in the contract of sale an express waiver of the actual damage requirement of the NHWA.” The appeals court affirmed the decision of the circuit court and denied the application to certify questions to the Louisiana Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Just When You Thought General Contractors Were Necessary Parties. . .
November 30, 2020 —
Christopher G. Hill - Construction Law MusingsDid you think that a subcontractor had to name a general contractor in a mechanic’s lien suit? I did. Did you think that nothing about this changed in the case where a Virginia mechanic’s lien was “bonded off” pursuant to Va. Code Section 43-71? I did.
Well, a recent Virginia Supreme Court case, Synchronized Construction Services Inc. v. Prav Lodging LLC, seems to at least create some doubt as to whether the a general contractor is a “necessary” party to a lawsuit by a subcontractor in the case where a bond is posted for release of a mechanic’s lien.
In Prav Lodging, the facts were a bit unusual. The day after the mechanic’s lien was recorded by Synchronized Construction Services, Inc. (“Synchronized”) the construction manager, Paris Development Group, the construction manager and de facto general contractor, went out of business. Despite this fact, and after the lien was bonded off, Synchronized sued to enforce the lien and for breach of contract against Paris. The wrinkle here is that Synchronized was unable to serve several defendants, among them Paris, within one year of filing suit as required by Virginia statute. In the Circuit Court, the financing bank moved to dismiss the suit for failure to serve necessary parties. The Circuit Court dismissed the breach of contract count but refused to dismiss the mechanic’s lien count on this basis.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
1st District Joins 2nd District Court of Appeals and Holds that One-Year SOL Applies to Disgorgement Claims
June 14, 2021 —
Garret Murai - California Construction Law BlogWe’re beginning to see a trend.
This past year, the 2nd District Court of Appeals, in Eisenberg Village of the Los Angeles Jewish Home for the Aging v. Suffolk Construction Company, 53 Cal.App.5th 1201 (2020), held for the first time that a one (1) year statute of limitations period beginning upon substantial completion of a project applies to disgorgement claims under Business and Professions Code section 7031. In San Francisco CDC LLC v. Webcor Construction L.P., the 1st District Court of Appeals became the second Court of Appeals in the state to hold that a one (1) year statute of limitations beginning upon completion or cessation of work on a project applies to disgorgement claims under Business and Professions Code section 7031.
The San Francisco CDC LLC Case
The Defect Action
In September 2005, San Francisco CDC LLC entered into a $144 million construction contract with Webcor Construction, Inc. doing business as Webcor Builders to build the InterContinental Hotel in San Francisco, California.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Third Circuit Holds That Duty to Indemnify "Follows" Duty to Defend
December 27, 2021 —
Jeffrey J. Vita - Saxe Doernberger & Vita, P.C.In a win for policyholders, the Third Circuit Court of Appeals recently affirmed a District Court’s 2018 ruling, which held that the duty to indemnify follows the duty to defend where a settlement precludes a determination on the facts of the case relative to liability and apportionment.
In Liberty Mutual Insurance Co. v. Penn National Mutual Casualty Insurance Co.,1 a large concrete panel collapsed and killed a construction worker at a construction site in New Kensington, Pennsylvania. Cost Company (“Cost”), Liberty Mutual’s insured, was a masonry subcontractor on the project and had further subcontracted with Pittsburgh Flexicore Co. (“Flexicore”), Penn National’s insured, for the concrete panels. Cost’s subcontract agreement required Flexicore to name Cost as an additional insured under its general liability policy issued by Penn National.
When the construction worker’s widow filed a wrongful death lawsuit against Cost and Flexicore, Cost demanded that Penn National defend and indemnify it as an additional insured under the policy. Penn National refused, arguing that any additional insured status had terminated at the conclusion of Flexicore’s work for Cost. As a result, Liberty Mutual defended Cost in the lawsuit, which was ultimately settled.
Read the court decisionRead the full story...Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C.Mr. Vita may be contacted at
JVita@sdvlaw.com
Construction Group Seeks Defense Coverage for Hard Rock Stadium Claims
December 09, 2019 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogIn an insurance coverage action pending in the S.D.N.Y., Hunt Construction Group (Hunt) contends that Berkley Assurance Company wrongfully denied defense coverage for claims arising out of the renovation of Hard Rock Stadium (home to the Miami Dolphins and Miami Hurricanes football teams).
The stadium owner, South Florida Stadium LLC (SFS), hired Hunt to serve as the construction manager for the renovation project. Hunt subcontracted with Alberici Constructors Inc. (Alberici) to design and fabricate roof structures for the stadium.
Hunt and SFS sued Alberici over its work on the project. In March 2017, Alberici asserted counterclaims against Hunt and SFS. In May 2018, SFS sought defense and indemnification from Hunt with respect to Alberici’s coverage claims.
Hunt is insured under claims made and reported professional liability insurance policies issued by Berkley with policy periods from June 15, 2016 to June 15, 2017 (with an automatic extended reporting period through August 14, 2017) and from July 15, 2017 to June 15, 2018. Hunt notified Berkley of Alberici’s counterclaim on July 20, 2017 (within the extended reporting period of the 2016-2017 policy) and of SFS’s indemnity claim on June 5, 2018 (within the 2017-2018 policy period).
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Costs Absorb Two Big Hits This Quarter
July 14, 2016 —
Tim Grogan and Bruce Buckley – Engineering News-RecordTwo big events hit construction this quarter: Brexit—that is, the British vote to leave the European Union— and the U.S government’s decision to increase tariff duties on Chinese cold-rolled flat steel by 522%. However, neither will have much of an impact on domestic construction costs, according to ENR’s sources.
Reprinted courtesy of
Tim Grogan, ENR and
Bruce Buckley, ENR
Mr. Grogan may be contacted at grogant@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
The Secret to Success Is Doing Things a Little Bit Differently
November 16, 2020 —
Charlie Kimmel - Construction ExecutiveThroughout the 1960s and 1970s, Rick Barry made his mark on the world of college and professional basketball. He was a skilled small forward who averaged 37.4 points per game during his senior year at the University of Miami, and he was the second overall pick in the 1965 NBA draft. But he’s best remembered as a prolific free-throw shooter: he led the NBA in free-throw percentage for several consecutive years. When he retired in 1980, his free-throw percentage (.900) was the highest in NBA history.
So what was the secret to his success? He did things a little bit differently. While the vast majority of basketball players shoot overhand free throws, Barry was famous for his unorthodox underhanded shots. This technique was not only incredibly effective, but it also set him apart as a player and contributed to his popularity.
Construction companies can learn a lot from Barry’s strategy of doing things a little bit differently to achieve success. Most companies don’t need to worry about their employees’ free-throw techniques. But all of them need to set themselves apart from their competition and establish strong reputations in today’s highly competitive market.
Reprinted courtesy of
Charlie Kimmel, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of