U.S. District Court of Colorado Interprets Insurance Policy’s Faulty Workmanship Exclusion and Exception for Ensuing Damage
August 15, 2022 —
Carin Ramirez - Colorado Construction LitigationRecently, the United States District Court for the District of Colorado interpreted a faulty workmanship exclusion in a property insurance policy in The Lodge at Mountain Village Owner Association v. Eighteen Certain Underwriters of Lloyd’s of London, 22 U.S Dist. Ct LEXIS 48883*, decided on March 18, 2022. The Court held that the faulty workmanship exclusion at issue extended to preclude coverage for later ensuing damage that arose from the faulty workmanship, even though the damage was weather related, because faulty workmanship was the primary cause of the ensuing damage.
The claims in The Lodge at Mountain Village arose from maintenance work performed on log siding at three multi-unit condominium buildings in Telluride. The maintenance work to the log siding included staining, finishing, and chinking repairs to joints between the logs. About a year after completion of the work, The Lodge at Mountain Village Owners Association (“The Lodge”) notified the maintenance contractor that logs were extremely weathered and that its work was defective. The Lodge retained an expert who prepared a report stating that the log finish and underlying wood was deteriorating because of the contractor’s work and that some areas were not properly protected from exposure to snow, rain, and brine from ice-melting salt. The Lodge pursued and settled its claims against the contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Carin Ramirez, Higgins, Hopkins, McLain & Roswell, LLCMs. Ramirez may be contacted at
ramirez@hhmrlaw.com
DC Circuit Approves, with Some Misgivings, FERC’s Approval of the Atlantic Sunrise Natural Gas Pipeline Extension
December 02, 2019 —
Anthony B. Cavender - Gravel2GavelThe U.S. Court of Appeals for the DC Circuit decided the case of Allegheny Defense Project, et al. v. Federal Energy Regulatory Commission on August 2, 2019. In a Per Curiam opinion, the court denied petitions challenging the Commission’s orders permitting the Transcontinental Gas Pipe Line Company’s expansion of an existing natural gas pipeline which extends from northern Pennsylvania across the Carolinas into Alabama. The expansion is called the “Atlantic Sunrise Project.” In February 2017, FERC approved the expansion, and denied various petitions, filed by environmental organizations and affected landowners, who then challenged the decision in the DC Circuit. However, the court concluded, on the basis of the administrative record, that these challenges “cannot surmount the deferential standards of agency review and binding DC Circuit precedent.” Under the law, the Commission must consider whether the projected pipeline project meets a market need, and whether the public benefits outweigh the harms. If both criteria are satisfied, FERC will, as in this instance, issue a certificate authorizing the pipeline’s construction, and that certificate also empowers the certificate holder to exercise eminent domain authority under to the Natural Gas Act when necessary. It was the latter consequence of the FERC’s determinations that caused several Pennsylvania landowners to file their objections with the Commission and seek to stay construction.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
U.S. Building Permits Soared to Their Highest Level in Nearly Eight Years
June 17, 2015 —
Michelle Jamrisko – BloombergThrough all its ups and downs, the U.S. homebuilding industry is making slow progress.
While housing starts declined 11.1 percent in May to a 1.04 million annualized rate, it followed a revised 1.17 million pace the prior month to cap the best back-to-back readings since late 2007, Commerce Department data showed Tuesday in Washington. Permits for future projects climbed to the highest level in almost eight years.
The stop-and-go nature of the rebound, which has been exacerbated by the inclement weather that brought construction to a near standstill at the start of the year, masks a steady recovery in the industry at the center of the past recession. While residential real estate has yet to fulfill its typical role as a pillar of this economic expansion, gains in hiring and bigger paychecks are brightening Americans’ moods and could lift home purchases in the second half of 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, Bloomberg
The Advantages of Virtual Reality in Construction
August 20, 2019 —
Spivey Lipsey - Construction ExecutiveVirtual realty provides an unparalleled spatial sense for visualization at a lower cost than full-scale replicas. Today, VR is being used heavily in preconstruction to align owner expectations and educate design team stakeholders. For those already employing BIM solutions, coordination can be made much more effective by leveraging existing design models with very little added cost.
As anyone who has tried a VR headset before can attest, the ability to accurately perceive spatial relationships in design cannot be replicated through traditional 2D media such as screens or paper. VR solutions also have the ability to iterate rapidly. These technologies are linked to BIM, providing real-time feedback as the design changes. This is in stark contrast to traditional full-scale mockups and offline renders, which are cumbersome and time-consuming to update with design changes.
Substantial benefits without a hefty price tag
Budget limitations and ROI are always a concern with emerging technology. Fortunately, VR comes cheaply with BIM production. These solutions are significantly less expensive than full-scale mockups and far more efficient when compared to longhand sequencing explanations and esoteric detailing of complex designs. Even the most elaborate VR setups are a fraction of overall construction cost, ranging from a few hundred to a few thousand dollars depending on the level of adoption.
Reprinted courtesy of
Spivey Lipsey, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
How to Drop a New Building on Top of an Old One
December 05, 2022 —
Kriston Capps - BloombergFaçadectomy. That’s the tongue-in-cheek term for a widely unloved architectural compromise that developers sometimes strike: saving the historic veneer of an existing building while demolishing and replacing its internal structure. Façade preservation is especially popular in Washington, DC, where a federal cap on the height of buildings and the strength of the preservationist cause locally makes the case for adapting existing structures, even at great expense.
Façadism is rarer where cheaper tear-downs are possible, but over the last 40 years, this trend hit its stride on the East Coast. Prominent examples include the Spanish Embassy in DC and the Penn Mutual tower in Philadelphia.
A new condo tower in Boston’s South End isn’t a typical façadectomy. The development at 100 Shawmut Avenue looks as if a glassy modern building had been plopped down on top of an old warehouse. According to Tom Schultz, associate for The Architectural Team, the Boston-area firm behind the project, the case for incorporating a six-story warehouse into a new residential project wasn’t merely aesthetic. The site and structure lent itself to building up.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Judgment for Insurer Reversed Due to Failure to Establish Depreciation
August 01, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court erred in placing the burden on the policyholder to establish depreciation in determining the actual cash value of the loss. SFR Serv., LLC v. Tower Hill Prime Ins. Co., 2023 Fla. App. LEXIS 3570 (Fla. Ct. App. May 26, 2023).
The insureds' roof was damaged by Hurricane Irma. They submitted their claim to their insurer, Tower Hill. The cost of repair was assessed at $7,726.94, below the amount of the deductible. Therefore, there was no recovery under the policy. The insureds assigned their claim to SFR Services, LLC, their roofing contractor. SFR submitted a claim to Tower Hill for $162,083.84. Tower Hill refused to pay and SFR sued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Most Expensive Apartment Listings in New York That Are Not in Manhattan
August 26, 2015 —
James Tarmy & Oshrat Carmiel – BloombergApartments for very wealthy New Yorkers have remained mostly within the city’s smallest borough. Until now.
The record price for a Brooklyn home broke the $15 million threshold this summer, and by now it’s widely accepted that New York’s outer boroughs are not much of a bargain, growing further out of reach for the aspiring homeowner. The rush of new construction in gentrifying neighborhoods has pushed up the price of land, and that’s caused construction costs to rise, too. Eventually, to make a profit, developers have to build luxury buildings, according to Jonathan Miller, the president of New York appraiser Miller Samuel.
“We have this perfect storm,” he says. “Everybody gets the same idea at the same time, so materials and labor are at a premium. Throw in the high price of land at each locale, and you’ve got to build a luxury product.”
Reprinted courtesy of
James Tarmy, Bloomberg and
Oshrat Carmiel, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Judicial Panel Denies Nationwide Consolidation of COVID-19 Business Interruption Cases
October 05, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Judicial Panel on Multidistrict Litigation denied motions to centralize pretrial proceedings in pending COVID-19 business interruption claims. In re COVID-19 Business interruption Protection Insurance Litigation, 2020 U.S. District. LEXIS 144446 (Aug. 12, 2020).
Plaintiff policy holders sought consolidation, contending their policies provided coverage for business interruption losses caused by the COVID-19 pandemic and the related government orders suspending, or severely curtailing, operations of non-essential businesses. The Panel considered 15 actions on the pending motions, but had notice of 263 related actions.
Some plaintiffs opposed centralization or sought to be excluded from any MDL. Some argued the Panel should centralize the coverage actions on a state-by-state, regional, or insurer-by-insurer basis.
The Panel did not accept consolidation of all cases. There was little potential for common discovery across the litigation because there was no common defendant as the actions involved either a single insurer or insurer-group. The various cases involved different insurance policies with different coverages, conditions, exclusions, and policy language, purchased by different businesses in different industries located in different states.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com