Filling Out the Contractor’s Final Payment Affidavit
February 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen preparing a contractor’s final payment affidavit, I always suggest for a contractor (or anyone in privity of contract with the owner) to identify the undisputed amounts their accounting reflects is owed to ALL subcontractors, etc., regardless of whether that entity preserved their lien rights. If the contractor provided a payment bond, I footnote this simply to support that none of the lower-tiered subcontractors have lien rights or are the traditional “lienor.” (Thus, there is no prejudice to the owner if an entity is inadvertently omitted from the affidavit.)
There are times, however, where a contractor does not identify a subcontractor that did not serve a notice to owner and, therefore, has no valid lien rights. Or, a contractor omits a lienor that actually did serve a notice to owner and preserve its lien rights; this happens.
There was an older First District Court of Appeals case that harshly (and, quite, unfairly) held that the contractor must identify everyone in the final payment affidavit regardless of whether that entity timely served a notice to owner or their lien is invalid. This case, however, predated, a 1998 statutory change to Florida’s Lien Law.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Illinois Appellate Court Finds That Damages in Excess of Policy Limits Do Not Trigger Right to Independent Counsel
June 22, 2020 —
Jason Taylor - Traub LiebermanUnder Illinois law, an insurer’s duty to defend includes the right to control the defense, which allows insurers to protect their financial interest in the outcome of the litigation. However, where a conflict of interest exists, the insured, rather than the insurer, is entitled to assume control of the defense of the underlying action. If this occurs, the insurer satisfies its obligation to defend by reimbursing the insured for the cost of defense provided by independent counsel selected by the insured. What circumstances and situations arise to the level of an actual conflict of interest between the insurer and insured are often grounds for dispute.
In Joseph T. Ryerson & Son, Inc. v. Travelers Indemnity Co. of America, 2020 IL App (1st) 182491 (Apr. 7, 2020), the Illinois Appellate Court addressed whether damages awarded by a jury in excess of the policy limits were sufficient to trigger a right to independent counsel for post-trial and appellate proceedings. According to the Illinois Appellate Court, at least under the facts of the Ryerson case, the answer is “no.”
In Ryerson, Nancy Hoffman sued Ryerson for injuries sustained in a tractor-trailer accident. Ryerson tendered the suit to its primary insurer, Travelers, and its umbrella insurer, Illinois National. The policy limits were $2 million and $25 million, respectively. A jury found in favor of Hoffman for over $27.6 million in damages, and Ryerson appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
ASCE Statement on House Failure to Pass the Infrastructure Investment and Jobs Act
October 04, 2021 —
Tom Smith - American Society of Civil EngineersThe following is a statement by Tom Smith, Executive Director, American Society of Civil Engineers (ASCE):
WASHINGTON, DC. – Today, American families and businesses are paying the price while the House plays politics and fails to pass the bipartisan Infrastructure Investment and Jobs Act (IIJA), a historic piece of legislation that would have monumental impacts on the economy, public safety, global competitiveness, and each American's well-being. After decades of kicking the can down the road on meaningful infrastructure legislation, Congress is missing an extraordinary chance to reverse this unsustainable trend with passage of the IIJA, instead choosing to allow critical projects to be delayed.
This legislation was passed in a strong vote by the Senate on August 10th, and almost two months later, it sits on the sidelines as the federal program for transit, roads, and bridges expired on September 30th and projects come grinding to a halt. While other countries are making investments in their future, we are letting politics steal this opportunity to move forward.
It does not have to be this way. This comprehensive bill would bring relief to communities facing strained power grids, aging bridges, leaking water pipes, and spotty broadband. American families do not want to have to wonder if their power will stay on in the next storm, if the bridge connecting their community will close for emergency repairs, or if a week of virtual school means their child will miss out.
We urge the House to pass this bipartisan, commonsense legislation today to create jobs, make goods and services move more quickly and reliably, and make American communities more climate-resilient. Our infrastructure bill has come due, and now is the time to act.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
BWB&O’s Motion for Summary Judgment is Granted in a Premises Liability Matter
November 05, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Newport Beach Partner Courtney Serrato and Associate Joseph Real on Prevailing on a Motion for Summary Judgment for their Client!
Plaintiff filed a lawsuit alleging negligence and premises liability against BWB&O’s client, a general contractor of a multi-level construction project. Plaintiff was injured after a fall at the construction project and filed suit against BWB&O’s client and another subcontractor.
Plaintiff alleged BWB&O’s client was negligent and was responsible for causing Plaintiff’s fall. BWB&O filed a Motion for Summary Judgment arguing under the Privette Doctrine and its progeny, it neither owed nor breached any duty to Plaintiff and that no exception to the doctrine applied. Under the Privette Doctrine, when a person or entity hires an independent contractor to provide work or services, and one of the contractor’s employees is injured on the job, the hirer is generally not liable to the employee.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Home Prices in 20 U.S. Cities Increased 5% in Year to June
August 26, 2015 —
Michelle Jamrisko – BloombergHome prices in 20 U.S. cities climbed 5 percent in June from the same month a year earlier, a sign of more progress in the housing market.
The increase in the S&P/Case-Shiller index of property values matched the year-over-year gains in the prior three months, the group said Tuesday in New York. The median estimate of economists surveyed by Bloomberg called for a 5.1 percent year-over-year advance. Nationally, prices rose 4.5 percent.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, Bloomberg
No Coverage Under Exclusions For Wind and Water Damage
March 30, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Mississippi Supreme Court affirmed the granting of summary judgment to the insurer that there was no coverage under the all risk policy for loss caused by wind and water. Porter v. Grand Casino of Miss., Inc., 2016 Miss. LEXIS 3 (Miss. Jan. 7, 2016).
Cherri Porter's home was destroyed during Hurricane Katrina. The destruction occurred when the barge operated by Grand Casino of Mississippi came loose from its moorings and collided with her home.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Preliminary Notices: Common Avoidable But Fatal Mistakes
August 26, 2019 —
William L. Porter - Porter Law GroupIn the California building and construction industry, service of a “Preliminary Notice” is a prerequisite for Subcontractor and Supplier claims for payment through the Mechanics Lien, Stop Payment Notice and Payment Bond Claim process. Without proper drafting and service of a Preliminary Notice, these extremely valuable claims cannot be protected. Unfortunately, despite the vital importance of the Preliminary Notice, Subcontractors and Suppliers often make common self-defeating mistakes that make their Preliminary Notice efforts completely ineffective, resulting in loss of their claims rights. The purpose of this article is to list some of these common mistakes in the hope that the reader will avoid such mistakes, preserve the integrity of the Preliminary Notice, and protect the claims rights it makes available:
Not Sending out the Preliminary Notice Within 20 Days After Supplying Labor or Materials:
The protection of a Preliminary Notice begins 20 days before it sent out. This means that if a Subcontractor or Supplier claimant delivered $100,000 in materials on February 1, that same claimant must serve the Preliminary Notice on or before February 21 (the sooner the better), or the claimant will not be able to pursue an enforceable Mechanics Lien, Stop Payment Notice or Payment Bond claim for that $100,000. There are very few exceptions. Best practice: A Subcontractor or Supplier must send out the Preliminary Notice as soon as an agreement to provide work or materials to a California construction project is in place (See California Civil Code 8204).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
“Professional Best Efforts” part 2– Reservation of Rights for Engineers who agree to “best” efforts? (law note)
April 20, 2017 —
Melissa Dewey Brumback - Construction Law in North CarolinaRecently, a reader reached out to me to ask about case examples of an engineer losing his insurance coverage because he agreed to a “heightened” or “best” standard of care. The reader stated that he was an insurance adviser who handled various construction professional coverages, and that in his experience it was very unusual to deny or limit damages because of a heightened standard of care.
This comment led me to an informal survey of several insurance brokers that I deal with, and the general consensus is that instead of outright denying a claim, most E&O insurers will issue a “reservation of rights” letter. What that means is that the insurance company will defend the claim (i.e., pay for your lawyer to defend you and your Firm), but with the understanding that they are (potentially) denying any liability for any adverse money judgment against you.
Inevitably, most such cases settle, but if they do not, the question then is whether the heightened duty created part of the damages. The insurer may ask to intervene in the lawsuit to ask the jury that question, in an effort to limit its share of the damages.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com