An Obligation to Provide Notice and an Opportunity to Cure May not End after Termination, and Why an Early Offer of Settlement Should Be Considered on Public Works Contracts
August 17, 2020 —
Jeff Kaatz - Ahlers Cressman & SleightIn 2015, the City of Puyallup (“City”) and Conway Construction Company (“Conway”) executed a public works contract for road improvements (“Project”). On March 9, 2016, approximately four months after work started on the Project, the City issued Conway a notice of suspension and breach of contract and identified nine defective and uncorrected work and safety concerns. Conway denied any wrongdoing, and on March 25, 2016, the City issued a notice of termination for default and withheld payments due to Conway.
Conway subsequently filed suit in Pierce County Superior Court and alleged the City’s termination for default breached the contract and sought a determination that the City’s termination for default was improper and should be deemed a termination for convenience. Conway sought approximately $1.25 million in damages and recovery of its attorney fees and costs. Following a bench trial, the Trial Court found the City breached the contract and awarded Conway damages, attorney fees, and costs. The City appealed.[1]
On appeal, after affirming the trial court’s determination that the City improperly terminated Conway, the Court of Appeals considered two other issues raised by the City. First, whether the City was entitled to a set-off for replacing defective work discovered after Conway was terminated. Second, whether Conway is entitled to attorney fees if it did not make the statutorily required offer of settlement per RCW 39.04.240.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Kaatz, Ahlers Cressman & SleightMr. Kaatz may be contacted at
Jeff.Kaatz@acslawyers.com
PSA: Pay If Paid Ban Goes into Effect on January 1, 2023
December 05, 2022 —
Christopher G. Hill - Construction Law MusingsI have
written a couple of times here at Musings regarding the new pay-if-paid legislation passed by the General Assembly last session. While the statute has some inconsistencies and a working group has made
some recommendations, the legislation as passed will go into effect on January 1, 2023, without any changes (at least until next session). As always, such action by our legislature here in Virginia will create work for construction attorneys assisting their clients to amend contracts to meet the new rules.
Essentially (and with minor inconsistencies between public and private contracts), the bill requires that any construction contract entered into after January 1, 2023 have the following provisions:
- On public projects: A payment clause that obligates a contractor on a construction contract to be liable for the entire amount owed to any subcontractor with which it contracts. Such contractor shall not be liable for amounts otherwise reducible due to the subcontractor’s noncompliance with the terms of the contract. However, in the event that the contractor withholds all or a part of the amount promised to the subcontractor under the contract, the contractor shall notify the subcontractor, in writing, of his intention to withhold all or a part of the subcontractor’s payment with the reason for nonpayment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Hoboken Mayor Admits Defeat as Voters Reject $241 Million School
February 21, 2022 —
Nic Querolo - BloombergHoboken Mayor Ravi Bhalla said late Tuesday that the city’s $241 million bond referendum to build a new high school won’t pass.
“While the will of the voters has made it clear that the Board of Education’s current proposal for the new high school will not move forward, I sincerely believe that the effort to improve our public schools will continue,” Bhalla said in a statement. While the board of education put forth the proposal, the mayor was a big proponent.
The vote in a special election Tuesday was one of the costliest school construction referendums in New Jersey history. The bond was failing 66% to 34%, with 35 out of 42 precincts reporting, according to unofficial results posted by Hudson County as of Wednesday morning. About 7,500 ballots had been cast, translating to a roughly 17% turnout, which is strong for a school bond vote.
Read the court decisionRead the full story...Reprinted courtesy of
Nic Querolo, Bloomberg
Water Seepage, Ensuing Mold Damage Covered by Homeowner's Policy
August 13, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe appellate court reversed the trial court's determination that the policy covered only mold damage, but not damage caused by water seepage. Henderson v. Georgia Farm Bureau Mut. Ins. Co., 2014 Ga. App. LEXIS 539 (Ga. Ct. App. July 16, 2014).
The homeowner's policy covered losses caused by constant seepage or leakage of water or the presence of condensation or moisture over a period of time. The insureds also paid for additional coverage for "ensuing mold . . . caused by or resulting from" one of the covered risks, including water seepage.
Ms. Henderson discovered a puddle of water in her kitchen and contacted Georgia Farm Bureau. The insurer's contractor tore out a section of the floor, but found no other problems of water seepage. Later, the Hendersons removed another part of the floor and discovered standing water and black mold underneath. The Hendersons had to vacate their house for one year.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Appeals Court Rekindles the Spark
March 16, 2017 —
Lian Skaf - White and Williams LLPIn John Trimble, et al. v. City of Albany, et al., 2016, 144 A.D.3d 1484; 42 N.Y.S. 3d 432 (N.Y. App. Div.), the Supreme Court of New York, Appellate Division, addressed the issue of governmental immunity for municipal fire companies. The court held that the plaintiff, John Trimble (Trimble), had sufficient evidence related to the four-pronged test for establishing a “special relationship” between a municipality and a citizen for liability to attach. In addition, the court held that the defendants were not entitled to summary judgment on the issue of governmental immunity. Specifically, regarding the latter holding, the court stated that, when there is no actual choice made on the part of the government, the government’s actions cannot be considered discretionary and immunity will not apply.
In the case at hand, a fire occurred at Trimble’s home on the evening of February 2, 2013. Trimble called 911 and the Department of Fire and Emergency Services for the City of Albany (the Department) responded. After extinguishing the fire, the Department conducted an investigation and cleared the home. The Department’s investigators then told Trimble that the fire was extinguished and it was safe to enter the home. Trimble did so, removing some items so that he could stay with relatives that night. Several hours later, there was a rekindle and the rekindled fire destroyed the home.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
2018 Update to EPA’s “Superfund Task Force Report”
September 04, 2018 —
Anthony B. Cavender - Gravel2GavelThe U.S. Environmental Protection Agency (EPA) recently released its Superfund Task Force Recommendations 2018 Update (the Update). The Superfund Task Force was established by former EPA Administrator Scott Pruitt to “provide recommendations on an expedited timeframe on how the agency can restructure the cleanup process, realign incentives of all involved parties to promote expeditious remediation, reduce the burden on cooperating parties, incentivize parties to remediate sites, encourage private investment in cleanups of sites and promote the revitalization of properties across the country.” Over the years, thousands of sites have been listed on EPA’s National Priority List (NPL) of Superfund sites, but the process by which listed sites are cleaned up and finally removed from the NPL has been agonizingly slow. The process is governed by the National Contingency Plan rules. The Update states that, as of July 3, 2018, there are 1,346 sites listed on the NPL, and overall, 399 sites have been removed from the NPL.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Revisiting Termination For Convenience Clauses In Uncertain And Ever-Changing Economic Times
February 27, 2023 —
Adam M. Tuckman & Brittney M. Wiesner - ConsensusDocsIn these times of persistent inflationary forces and efforts to tame the consequences through rising interest rates, economic uncertainty abounds in the United States and around the world. As an approximately $1 trillion contributor to the economy in the United States (4.2% of GDP in 2021) alone according to the Associated General Contractors of America, the health and the growth of the construction industry is certainly susceptible to these rapidly changing macroeconomic conditions.
Presently, an unanswered question is how project developers will react to unpredictable fluctuations in project costs and interest rates. Although it seems unlikely to be a prevalent response, it is possible that substantial increases in borrowing, labor, or material costs would cause owners to pull the plug on projects that are in the advanced stages of construction. For projects in the nascent stages of development or construction, however, the calculous for owners becomes more tenuous. Both public and private owners may find it more prudent to indefinitely suspend or cancel pending or ongoing projects due to any, or a combination of, forecasted increases in project costs, shrinking funding, higher borrowing costs, or macro-economic uncertainty. Facing this quandary, how would an owner already under contract with a constructor and design team suspend or cancel its project? One potential approach is to invoke a termination for convenience clause found in the parties’ contract.
Reprinted courtesy of
Adam M. Tuckman, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs) and Brittney M. Wiesner, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)
Mr. Tuckman may be contacted at atuckman@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
A Tort, By Any Other Name, is Just a Tort: Massachusetts Court Bars Contract Claims That Sound in Negligence
March 20, 2023 —
Gus Sara - The Subrogation StrategistIn University of Massachusetts Building Authority v. Adams Plumbing & Heating, Inc., 2023 Mass. App. Unpub. LEXIS 28, 102 Mass. App. Ct. 1107, the Appeals Court of Massachusetts (Appeals Court) considered whether the lower court properly held that the plaintiff’s breach of contract and indemnification claims were time-barred by the statute of repose because they sounded in tort. The Appeals Court held that while the six-year statute of repose only applies to tort claims, they can also bar claims for breach of contract and indemnification if they sound in tort. The Appeals Court affirmed the lower court’s ruling, finding that the plaintiff’s breach of contract and indemnification claims were just negligence claims disguised as non-tort claims.
In 2013 and 2014, the University of Massachusetts (UMass) retained various contractors to renovate the dining hall for one of its campus buildings, which included the installation of new ductwork for the kitchen’s exhaust system. The dining hall opened for service in September 2014. In the Spring of 2018, it was discovered that the ductwork for the kitchen had collapsed. Further investigation revealed other deficiencies with the exhaust system. On December 1, 2020, UMass filed a lawsuit against various contractors, asserting negligence, breach of contract, and indemnification. The breach of contract claims alleged breach of express warranties.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com