Difficult Task for Court to Analyze Delay and Disorder on Construction Project
August 23, 2021 —
David Adelstein - Florida Construction Legal UpdatesOne of my favorites quotes from a case, and I am sure others in the construction industry feel the same way or can relate, is from the District of Columbia Court of Appeals in Blake Construction Co., Inc. v. C.J. Coakley Co., Inc., 431 A.2d 569, 575 (D.C. 1981):
We note parenthetically and at the outset that, except in the middle of a battlefield, nowhere must men coordinate the movement of other men and all materials in the midst of such chaos and with such limited certainty of present facts and future occurrences as in a huge construction project such as the building of this 100 million dollar hospital. Even the most painstaking planning frequently turns out to be mere conjecture and accommodation to changes must necessarily be of the rough, quick and ad hoc sort, analogous to ever-changing commands on the battlefield. Further, it is a difficult task for a court to be able to examine testimony and evidence in the quiet of a courtroom several years later concerning such confusion and then extract from them a determination of precisely when the disorder and constant readjustment, which is to be expected by any subcontractor on a job site, become so extreme, so debilitating and so unreasonable as to constitute a breach of contract between a contractor and a subcontractor.
Do you agree with this sentiment? The reality is that retrospectively analyzing delay on a complicated construction project with numerous moving parts on a day-by-day, hour-by-hour, basis is no easy feat. It is not easy for the parties and certainly not easy for courts to unravel. With every party claiming delay based on a retrospective analysis there will be another party with either a different delay analysis or providing credible cross examination as to flaws with the delay analysis. The same bodes true with loss of productivity / inefficiency claims and the particular case-specific facts are important, preferably with evidence such as photos, videos, notifications, daily reports, manpower reports, etc., supporting the facts. But the facts are complicated, and the delay analysis is complicated, and it is a difficult task for a trier of fact to unravel these facts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Statutes of Limitations May be the Colorado Contractors’ Friend
April 18, 2011 —
Beverley BevenFlorez CDJ STAFFAlbert Wolf, a principal in Wolf Slatkin & Madison P. C., has written an interesting article on statutes of limitations in construction defect claims in Colorado. While Wolf states that in most cases, “construction defect claims against construction industry participants (contractors, subcontractors, architects, engineers, etc.) requires that suits be started within two years after construction defects have been or should have been—in the exercise of reasonable diligence (care)—discovered,” if a project used the AIA General Conditions (AIA Document A2010) before the 2007 edition, the “statutes of limitations begin to run (accrue) at either substantial completion or breach by the contractor (installation of defective work), depending on the circumstances.”
“That’s a huge difference,” Wolf writes in his article. “For example, if the structural defect caused by faulty foundation work is not discovered or discoverable until walls begin to exhibit cracking more than two years after the building is completed, the owner’s claim against the contractor may be barred if the AIA provision is applied.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Billionaire Behind Victoria’s Secret Built His Version of the American Heartland
June 25, 2019 —
Sophie Alexander - BloombergBeyond emerald-green golf links, over snow-white fences, and past tree-lined cul-de-sacs rises the American fantasyland of billionaire Les Wexner.
Here in the middle of Ohio, of all places, Wexner—the man behind Victoria’s Secret and its push-up-bra notions of female beauty—has brought to life his singular vision of the heartland.
Read the court decisionRead the full story...Reprinted courtesy of
Sophie Alexander, Bloomberg
A New Statute of Limitations on Construction Claims by VA State Agencies?
March 27, 2019 —
Christopher G. Hill - Construction Law MusingsI have discussed the Hensel Phelps case and the potential issues caused by both poorly drafted indemnity clauses and the lack of a statute of limitations applicable to the Commonwealth of Virginia and its agencies in 2017. New legislation (supported by various contractor groups including my friends at the AGC of Virginia) has been proposed for the 2019 General Assembly session that seeks to address at least part of this issue. While the indemnity provisions of your construction contracts can be addressed by careful drafting with the help of an experienced construction attorney, the proposed legislation (found in HB1667) seeks to address the statute of limitations issue.
The proposed legislation is described as follows:
Provides that no action may be brought by a public body on any construction contract, including construction management and design-build contracts, unless such action is brought within five years after substantial completion of the work on the project and that no action may be brought by a public body on a warranty or guarantee in such construction contract more than one year from the breach of that warranty, but in no event more than one year after the expiration of such warranty or guarantee. The bill also limits the time frame during which a public body, other than the Department of Transportation, may bring an action against a surety on a performance bond to within one year after substantial completion of the work on the project.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Design and Construction Defects Not a Breach of Contract
February 14, 2013 —
CDJ STAFFThe California Court of Appeals tossed out a breach of contract award in Altman v. John Mourier Construction. The decision, which was issued on January 10, 2013, sent the construction defect case back to a lower court to calculate damages based on the conclusions of the appeals court.
The case involved both design issues and construction issues. According to the plaintiffs’ expert, the design plans did not make the buildings sufficiently stiff to resist the wind, and that the framing was improperly constructed, further weakening the structures, and leading to the stucco cracking. Additionally, it was alleged that the roofs were improperly installed, leading to water intrusion. The contractor’s expert “agreed the roofs needed repair, but disputed what needed to be done to repair the roofs and the cost.”
The jury rejected the plaintiffs’ claims of product liability and breach of warranty, but found in their favor on the claims of breach of contract and negligence. The plaintiffs were awarded differing amounts based on the jury’s conclusions about their particular properties.
Both sides sought new trials. JMC, the contractor, claimed that the jury’s verdicts were “inconsistent in that the relieved JMC of liability for strict products liability and breach of warranty, but found JMC liable for breach of contract and negligence.” The plaintiffs “opposed the setoff motion on the ground that the jury heard evidence only of damages not covered by the settlements.” Both motions were denied. After this, the plaintiffs sought and received investigative costs as damages. JMC appealed this amended judgment.
The appeals court rejected JMC’s claims that evidence was improperly excluded. JMC sought to introduce evidence concerning errors made by the stucco subcontractor. Earlier in the trial, JMC had insisted that the plaintiffs not be allowed to present evidence concerning the stucco, as that had been separately settled. When they wished to introduce it themselves, they noted that the settlement only precluded the plaintiffs from introducing stucco evidence, but the trial court did not find this persuasive, and the appeals court upheld the actions of the trial court. Nor did the appeals court find grounds for reversal based on claims that the jury saw excluded evidence, as JMC did not establish that the evidence went into the jury room. Further, this did not reach, according to the court, a “miscarriage of justice.”
The court rejected two more of JMC’s arguments, concluding that the negligence award did not violate the economic loss rule. The court also noted that JMC failed to prove its contention that the plaintiffs were awarded damages for items that were covered in settlements with the subcontractors.
The appeals court did accept JMC’s argument that the award for breach of contract was not supported by evidence. As the ruling notes, “plaintiffs did not submit the contracts into evidence or justify their absence; nor did plaintiffs provide any evidence regarding contract terms allegedly breached.”
The court also did not allow the plaintiffs to claim the full amount of the investigative costs. Noting that the trial court had rational grounds for its decision, the appeals court noted that “the jury rejected most of the damages claimed by plaintiffs, and the trial court found that more than $86,000 of the costs itemized in plaintiffs’ invoices ‘appear questionable’ as ‘investigation’ costs/damages and appeared to the trial court to be litigation costs nonrecoverable under section 1033.5.”
Read the court decisionRead the full story...Reprinted courtesy of
Old Case Teaches New Tricks
March 16, 2017 —
Angela A.L. Connor & Curtis W. Martin - Peckar & Abramson, P.C.Eight years after completion of the wharf project, Zachry and the Port of Houston continue to slug
it out in the appellate courts and continue to refi ne Texas construction law along the way. In the
latest appellate opinion, the Court of Appeals details the general contractor’s control of the means
and methods of their work without interference from a governmental entity. It also supports a
subcontractor’s use of a pass-through claim as a cost efficient way to recover damages.
By now most of us are familiar with the project and the previous decisions. Zachry sued the Port
claiming breach after the Port denied Zachry the right to continue construction using its frozen
cutoff wall. The Texas Supreme Court upheld the jury’s $20 million verdict for Zachry, ruling that
the Port’s “no damages for delay” clause would not bar Zachry’s claim in light of the Port’s active
interference with Zachry’s work. The Supreme Court then sent the case back to the Court of
Appeals to consider other arguments that the Port had made.
That led to the most recent decision. In December, 2016, the Houston Fourteenth Court of Appeals
ruled in favor of Zachry on all issues and affirmed the jury verdict. In doing so, the Court of Appeals
provides several lessons or reminders on Texas Construction law.
Reprinted courtesy of
Angela A.L. Connor, Peckar & Abramson, P.C. and
Curtis W. Martin, Peckar & Abramson, P.C.
Ms. Connor may be contacted at aconnor@pecklaw.com
Mr. Martin may be contacted at cmartin@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
5 Questions about New York's Comprehensive Insurance Disclosure Act
February 14, 2022 —
Richard W. Brown & Michael V. Pepe - Saxe Doernberger & Vita, P.C.On December 31, 2021, New York enacted the Comprehensive Insurance Disclosure Act (“CIDA”), requiring defendants to provide plaintiffs with “complete” information for any insurance policy through which a judgment could be satisfied, within sixty (60) days after serving an answer. The stated goal is to reduce delay tactics by compelling disclosures of all policies implicated by a claim as well as other claims, contracts, or agreements that may deplete available coverage or residual limits of policies that have already been eroded by other payments. The impact of CIDA’s disclosure requirements may be scaled back by proposed amendments currently pending before the New York state legislature.
1. What does CIDA Require?
CIDA requires the automatic disclosure of insurance information to plaintiffs. New York’s Civil Practice Law & Rules (“CPLR”) 3101(f) permits civil discovery of the contents of existing insurance agreements by which an insurer may be liable for all or part of a judgment. However, CIDA amends the CPLR to mandate that defendants must automatically disclose the following information in all pending cases starting March 1, 2022, or within sixty (60) days of filing an answer to a complaint going forward:
- Complete copy of all insurance policies that are available to satisfy all or part of a potential judgment.
- This includes Primary, Excess, and Umbrella policies.
- The relevant applications for insurance.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita and
Michael V. Pepe, Saxe Doernberger & Vita
Mr. Brown may be contacted at RBrown@sdvlaw.com
Mr. Pepe may be contacted at MPepe@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
What Construction Firm Employers Should Do Right Now to Minimize Legal Risk of Discrimination and Harassment Lawsuits
October 07, 2024 —
Anthony LaPlaca, Dawn Solowey, Andrew Scroggins & Adrienne LeeSeyfarth Synopsis: In June 2024, Seyfarth published a blog article warning construction industry employers of recent anti-harassment guidelines issued by the EEOC. We predicted that the EEOC has “put the construction industry squarely in its sights.”[1] In this follow-up Alert, we discuss recent cases confirming the renewed regulatory focus on the construction sector, which demonstrate the need to put in place sound practices for non-discriminatory recruitment, hiring, and training of the work force in order to be prepared for this heightened risk of government scrutiny.
Recent EEOC Settlements
The U.S. Equal Employment Opportunity Commission (EEOC) has indicated, in no uncertain terms, that over the next five years it intends to prioritize the mitigation of systemic workplace problems and the historical underrepresentation of women and workers of color in the construction sector.[2] Two recent cases confirm that the EEOC is true to its word when it comes to tackling racial and gender disparities in the construction work force.
In August 2024, the EEOC secured two consent decrees with two separate construction firms in Florida, totaling nearly $3 million.
Reprinted courtesy of
Anthony LaPlaca, Seyfarth,
Dawn Solowey, Seyfarth,
Andrew Scroggins, Seyfarth and
Adrienne Lee, Seyfarth
Mr. LaPlaca may be contacted at alaplaca@seyfarth.com
Ms. Solowey may be contacted at dsolowey@seyfarth.com
Mr. Scroggins may be contacted at ascroggins@seyfarth.com
Ms. Lee may be contacted at aclee@seyfarth.com
Read the court decisionRead the full story...Reprinted courtesy of