Government’s Termination of Contractor for Default for Failure-To-Make Progress
July 10, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhenever you elect to terminate the other party for cause or for default, you need to JUSTIFY the basis of the cause or default. The reason being is that a termination for default or cause is the harshest contractual remedy. This is why the other party will typically either (i) convert the termination for default into one for convenience, or (ii) if there is no termination for convenience provision in the contract, argue the terminating party breached the contract by terminating the contract without rightful justification.
The key is if you are going to terminate a party for cause of default, make sure you have memorialized the persuasive reasons for exercising the termination, and can otherwise reasonably support the justification. Do not, and I repeat, do not haphazardly exercise a termination for default and think you do not have to justify the basis for the termination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New York Appellate Court Holds Insurers May Suffer Consequences of Delayed Payment of Energy Company Property and Business Interruption Claims
March 16, 2020 —
Syed S. Ahmad & Geoffrey B. Fehling - Hunton Andrews KurthA New York appellate court recently held that renewable bio-diesel fuel manufacturer BioEnergy Development Group LLC may pursue tens of millions of dollars in damages from its insurers under two all-risk insurance policies, including amounts in excess of the policy limits, where the insurers refused to pay claims in a timely manner.
BioEnergy purchased two all-risk property policies from Lloyd’s to provide coverage for its manufacturing plant in Memphis, Tennessee. A fire destroyed the Memphis plant in March 2016, eliminating BioEnergy’s production capacity and sole source of revenue. BioEnergy made claims under the policies and sought to rebuild its plant. The insurers acknowledged coverage and eventually made approximately $8 million in interim payments, but the parties disagreed over the value of the total property damage claim, which BioEnergy contended was in excess of $24 million. The disputed claim was submitted to appraisal, which resulted in the insurers agreeing to pay the full business interruption limit of $15.1 million.
The insurers filed a declaratory judgment lawsuit, however, seeking to limit BioEnergy’s recovery to the policy limits of $15.1 million. BioEnergy alleged that the insurers failed to make interim payments in a timely manner after the fire and, as a result, the company suffered increased losses because it could not rebuild without the insurance proceeds. BioEnergy sought actual and consequential damages, plus attorneys’ fees, arising from the delayed payments, including payment of its business interruption losses in excess of the policy limits.
Reprinted courtesy of
Syed S. Ahmad, Hunton Andrews Kurth and
Geoffrey B. Fehling, Hunton Andrews Kurth
Mr. Ahmad may be contacted at sahmad@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Powering Goal Congruence in Construction Through Smart Contracts
February 22, 2021 —
Michael Matthews - Construction ExecutiveThe $814 billion U.S. commercial construction market requires a unique assembly of designers, contractors, subcontractors and suppliers to work together in a highly orchestrated manner to make sure that the right labor, material, equipment, tools and information all comes together at the right place and time. Alignment and coordination between companies is critical for a project to be successful; completed safely, on time, on budget and resulting in an asset that performs as designed.
Yet the industry is slowed by an operating model bogged down by transactional and informational barriers that destroys value across the construction supply chain. Companies are connected through contracts and purchase orders that are undercut by mistrust that yields adversarial relationships and conflicting priorities that result in restricted transparency, elongated payment cycles and an abundance of resource-sucking reconciliations, audits and disputes.
With margins already razor thin, company protectionism cascades down from owners, developers and operators to contractors, subcontractors and suppliers with each player focused on optimizing their piece at the expense of the whole. Perhaps this is part of the reason 98% of megaprojects experience cost overruns or delays, 95% of projects are unable to meet even one business objective; and 70% of all construction projects are not completed within 10% of the proposed budget.
Reprinted courtesy of
Michael Matthews, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Keep it Simple with Nunn-Agreements in Colorado
June 28, 2021 —
Jean Meyer - Colorado Construction LitigationOn May 24, 2021, the Colorado Supreme Court published its decision in Auto-Owners Ins. Co. v. Bolt Factory Lofts Owners Ass'n.[1] There, the Colorado Supreme Court was tasked with answering whether an insurer, who is defending its insured under a reservation of rights, is entitled to intervene as of right under C.R.C.P. 24(a)(2) where the insured enters into a Nunn agreement with a third-party claimant, but rather than entering into a stipulated judgment, agrees with the third party to proceed via an uncontested trial to determine liability and damages. Interestingly, however, while the Court ultimately answered the above question in the negative, the real lesson from the Colorado Supreme Court’s decision is that Colorado litigants should not seek a trial court’s blessing as to liability and damages through non-adversarial proceedings when using Nunn-Agreements. Or, as articulated in Justice Carlos Samour’s vociferous dissenting opinion, Colorado litigants desiring to enter into a Nunn-Agreement should not proceed with a non-adversarial hearing, as doing so is “offensive to the dignity of the courts,” constitutes a “bogus,” “faux,” “sham” and “counterfeit” proceeding, and the hearing provides “zero benefit.”
By way of background, the case arrived in front of the Colorado Supreme Court based on the following fact pattern. A homeowner association (Bolt Factory Lofts Owners Association, Inc.) (“Association”) brought construction defect claims against a variety of prime contractors and those contractors subsequently brought third-party construction defect claims against subcontractors. One of the prime contractors assigned their claims against a subcontractor by the name Sierra Glass Co., Inc. (“Sierra”) to the Association. The other claims between the additional parties settled. On the eve of trial involving only the Association’s assigned claims against Sierra, the Association made a settlement demand to Sierra for $1.9 million. Sierra asked its insurance carrier, Auto-Owners Insurance, Co. (“AOIC”), which had been defending Sierra under a reservation of rights letter, to settle the case for that amount, but AOIC refused. This prompted Sierra to enter into a “Nunn-Agreement” with the Association whereby the case would proceed to trial, Sierra would refrain from offering a defense at trial, the Association would not pursue any recovery against Sierra for the judgment, and Sierra would assign any insurance bad faith claims it may have had against AOIC to the Association.
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Altman Contractors, Inc. v. Crum & Forster Specialty Ins. Co.
December 20, 2017 —
John Chiocca - Florida Construction Law NewsThe Florida Supreme Court issued its opinion in Altman Contractors, Inc. v. Crum & Forster Specialty Ins. Co., Case No., SC16-1420, which answered the following certified question from the United States Court of Appeals for the Eleventh Circuit: Is the notice and repair process set forth in Chapter 558 of the Florida Statutes a “suit'” within the meaning of the CGL policies issued by C&F to ACI?
Read the court decisionRead the full story...Reprinted courtesy of
John Chiocca, Cole Scott & Kissane P.A.Mr. Chiocca may be contacted at
john.chiocca@csklegal.com
Colorado Court of Appeals Finds Damages to Non-Defective Property Arising From Defective Construction Covered Under Commercial General Liability Policy
December 20, 2012 —
HEIDI GASSMAN, HIGGINS, HOPKINS, MCLAIN & ROSWELLThe recently decided case of Colorado Pool Systems, Inc. v. Scottsdale Insurance Company (Colo. Ct. App. 10CA2638, October 25, 2012), confirms that absent specific exclusions in the policy, a commercial general liability (“CGL”) policy covers damages to non-defective property arising from a builder’s own defective workmanship.
Colorado Pool Systems, Inc. (“Colorado Pool”) was hired as a subcontractor to install a swimming pool at Founders Village Pool and Community Center (“Founders Village”) in Castle Rock, Colorado. After the concrete shell of the pool was placed, some of the rebar frame was found to be too close to the surface. Founders Village demanded that Colorado Pool remove and replace the pool, and Colorado Pool contacted its insurance carrier, Scottsdale Insurance Company (“Scottsdale”), with which Colorado Pool held a CGL policy. After inspecting the pool, Scottsdale’s claims adjuster stated that the insurance policy would cover losses associated with removing and replacing the pool.
Read the court decisionRead the full story...Reprinted courtesy of
Heidi Gassman, Higgins, Hopkins, McLain & Roswell, LLC.Ms. Gassman can be contacted at
gassman@hhmrlaw.com
You May Be Able to Dodge a Bullet, But Not a Gatling Gun
November 16, 2020 —
Garret Murai - California Construction Law BlogIn the days before cable, and long before Netflix, I watched my fair share of spaghetti westerns on lazy weekend afternoons. Bullets zinging past cowboys, knocking off hats, and ricocheting off rocks. But while you might get lucky and dodge a bullet, not so with a Gatling gun.*
In the next case, C. W. Johnson & Sons, Inc. v. Carpenter, Case No. B300187 (August 7, 2020), a contractor who was unlicensed during a portion of a project dodged a bullet. However, I’m not so sure that he’s going to be able to dodge the hail of bullets that are coming after.
The C. W. Johnson & Sons Case
As cases go, the C. W. Johnson & Sons case is pretty straightforward. In March 2016, Contractor C. W. Johnson & Sons, a family owned flooring company, was contracted to install flooring at Randall Carpenter’s house for a total contract price of $68,343. Work was performed between March and September 2016 including some warranty, repair and corrective work after September 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Arizona Purchaser Dwelling Actions Are Subject to a New Construction
September 04, 2019 —
William L. Doerler - The Subrogation StrategistArizona recently amended its Purchaser Dwelling Action statute to, among other things, involve all contractors in the process, establish the parties’ burdens of proof, add an attorney fees provision, establish procedural requirements and limit a subcontractor’s indemnity exposure. The governor signed the bill—2019 Ariz. SB 1271—on April 10, 2019, and the changes go into effect and apply, retroactively “to from and after June 30, 2019.” The following discussion details some of the changes to the law.
Notice to Contractors and Proportional Liability
Under the revised law, a “Seller” who receives notice of a Purchaser Dwelling Action (PDA) from a residential dwelling purchaser pursuant to A.R.S. § 12-1363* has to promptly forward the notice to all construction professionals—i.e. architects, contractors, subcontractors, etc., as defined in A.R.S. § 12-1361(5)—that the Seller reasonably believes are responsible for an alleged construction defect. A.R.S. § 12-1363(A). Sellers can deliver the notice by electronic means. Once construction professionals are placed on notice, they have the same right to inspect, test and repair the property as the Seller originally placed on notice. A.R.S. § 12-1362(B), (C).
To the extent that the matter ultimately goes to suit, A.R.S. § 12-1632(D) dictates that, subject to Arizona Rules of Court, construction professionals “shall be joined as third-party defendants.” To establish liability, the purchaser has the burden of proving the existence of a construction defect and the amount of damages. Thereafter, the trier of fact determines each defendant’s or third-party defendant’s relative degree of fault and allocates the pro rata share of liability to each based on their relative degree of fault. However, the seller, not the purchaser, has the burden of proving the pro rata share of liability for any third-party defendant. A.R.S. § 12-1632(D).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com