Effectively Managing Project Closeout: It Ends Where It Begins
August 06, 2019 —
William E. Underwood - ConsensusDocsProject closeout is sometimes one of the last things on a contractor’s mind at the beginning of a project, but project closeout can have a huge impact on a contractor’s overall profitability and success. Effectively managing the closeout process is critical, and it all begins with the negotiation and execution of the project contract. This contract can, and should, provide a complete roadmap for project closeout, as addressing these issues on the front end can set up the parties for successful project completion. It is then equally important to re-review the terms of the contract as project closeout approaches to ensure that everyone, including the owner, adheres to all contractual requirements.
This article examines several pertinent issues related to project closeout that should be addressed during the contracting stage, including defining substantial and final completion, inspection and acceptance, punch lists, and warranties.
Defining Substantial and Final Completion
Having clear definitions for both substantial and final completion in your construction contract is an important and necessary early step in achieving successful project closeout.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLPMr. Underwood may be contacted at
wunderwood@joneswalker.com
Impaired Property Exclusion Bars Coverage When Loose Bolt Interferes with MRI Unit Operation
May 16, 2018 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel, LLPIn All Green Electric v. Security National Ins. Co. (No. B279456, filed 3/19/18, ord. pub. 4/17/18), a California appeals court ruled that the impaired property exclusion barred coverage for a claim based on the insured’s failure to tighten a loose bolt that resulted in stray magnetic fields interfering with operation of an MRI machine and allegedly threatening the health of personnel.
All Green was an electrical contractor hired to perform wiring for an MRI unit installation. Stray magnetic fields interfered with the unit’s operation. Efforts to remediate the problem included installing shielding and ultimately relocating the unit to another room. An expert finally determined that a bolt left loose by All Green was causing the magnetic field, which disappeared when the bolt was properly tightened. The facility sought damages for negligence, including costs for unnecessary modifications and repairs, payments to outside sources for substitute mammography testing, operational costs and expenses, damage to reputation, lost profits, and the loss of an HMO contract.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Supreme Court Limits the Powers of the Nation’s Bankruptcy Courts
June 11, 2014 —
Earl Forte – White and Williams LLPOn June 9, 2014, the Supreme Court of the United States issued its much-awaited decision in Executive Benefits Insurance Agency v. Arkison, Chapter 7 Trustee of Estate of Bellingham Insurance Agency, Inc., Case No. 12-1200, in which the court confirmed that the power of the nation’s bankruptcy courts to hear and decide cases involving state-created private rights in which the bankruptcy proof of claim process has not been directly invoked, is severely limited by Article III of the Constitution of the United States.
The decision in Executive Benefits, while providing some clarity to practitioners and the public following the Court’s June 2011 decision in Stern v. Marshall, 131 S. Ct. 2594 (2011), nevertheless will make a substantial portion of bankruptcy litigation matters more cumbersome and potentially more expensive to guide through the bankruptcy system. Clients and practitioners are best advised to hire knowledgeable counsel to help navigate the more complex procedural waters created by this decision.
Although the Court in Executive Benefits did resolve a pending procedural question that had dogged practitioners since Stern was decided in 2011, the Court’s decision in Executive Benefits now makes it abundantly clear that many disputes that were previously heard and decided in the nation’s bankruptcy courts can no longer be decided there and must be submitted to the district courts for full de novo review and entry of a final judgment or order. It is difficult to see how this decision will not make bankruptcy litigation more cumbersome and expensive by adding an additional layer of judicial involvement to many matters, notably to fraudulent transfer and other avoidance “claw back” actions that historically have been decided in the bankruptcy courts and used famously in Madoff and other cases as an efficient device for creating value for creditors.
Read the court decisionRead the full story...Reprinted courtesy of
Earl Forte, White and Williams LLPMr. Forte may be contacted at
fortee@whiteandwilliams.com
A Changing Climate for State Policy-Making Regarding Climate Change
February 18, 2020 —
Sheila McCafferty Harvey - Gravel2Gavel Construction & Real Estate Law BlogIssued by 13 federal agencies, the 2018 Fourth National Climate Assessment presented a stark warning on the consequences of climate change for the United States. The report predicts that if significant steps are not taken to rein in global warming, the damage will reduce the U.S. economy by as much as 10 percent by the end of the century. The report, which was mandated by Congress and made public by the White House, is notable not only for the precision of its calculations and bluntness of its conclusions—the 1,656-page assessment lays out the devastating effects of a changing climate on the economy—but also in how it conflicts with President Donald Trump’s environmental deregulation plan. U.S. policy efforts at the state and local levels are ramping up to address this complex topic. These include:
Targeting Net-Zero Emissions. Hailed as the most aggressive climate law in the nation, New York State’s Climate Leadership and Community Protection Act are targeting 100 percent carbon-free electricity by 2040 and economy-wide, net-zero carbon emissions by 2050. California set a statewide target to reach carbon neutrality by 2045.
Reducing and Renewing. New Mexico established a statewide goal of reducing greenhouse gas emissions by 45 percent below 2005 levels by 2030. Nevada passed a bill to increase the amount of electricity it gets from renewable resources to 50 percent by 2030.
Read the court decisionRead the full story...Reprinted courtesy of
Sheila McCafferty Harvey, PillsburyMs. Harvey may be contacted at
sheila.harvey@pillsburylaw.com
The Anatomy of a Construction Dispute- The Claim
December 02, 2015 —
Christopher G. Hill – Construction Law MusingsA new year brings with it promise and challenges. The promise is a relatively clean slate and the thought that 2015 will be a great year for construction professionals and those that assist them. The challenges come from the almost inevitable issues that can arise on a construction site with its many moving parts and enough potential pitfalls to make even the most optimistic construction attorney, contractor, subcontractor or supplier think that Murphy was an optimist.
In order to assist with the potential challenges, this post will be the first in a series of “musings” on the best way to handle a payment dispute arising from a construction contract. This week’s post will discuss what the first steps should be once a payment dispute or claim arises. We’ll assume that you, as a construction contractor, have taken early advantage of the services of a construction lawyer and have carefully reviewed your contract for issues before signing that contract.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Architect Not Responsible for Injuries to Guests
September 01, 2011 —
CDJ STAFFThe Texas Court of Appeals has ruled, with one dissent, that the architectural firm that designed a home was not responsible to the injuries caused to guests when a balcony collapsed. Judge David Puryear wrote the majority opinion in Black + Vernooy Architects v. Smith.
Black + Vernooy designed a vacation home for Robert and Kathy Maxfield in 2000. The Maxfields hired a general contractor to build the home. The general contractor hired a subcontractor to build a balcony; however, the subcontractor did not follow the architect’s design in building the balcony.
A year after the house was completed; the Maxfields were visited by Lou Ann Smith and Karen Gravely. The balcony collapsed under the two women. Ms. Gravely suffered a broken finger, a crushed toe, and bruises. Ms. Smith was rendered a paraplegic as a result of the fall. They sued the Maxfields, the general contractor, and the architects for negligence. The Maxfields and the general contractor settled. A jury found that the architects held 10% of the responsibility. The architects appealed the judgment of the district court.
The Appeals Court reversed this judgment, noting that “there has been no allegation that the Architects negligently designed the balcony or that the Architects actually created the defects at issue.” Further, “the Smiths allege that the defect was caused by the construction practices of the contractor and subcontractor when the balcony was not built in accordance with the design plans of the Architects.”
The court found that even though the architects had a duty “to endeavor to guard against defects and deficiencies in the construction of the home and to generally ascertain whether the home was being built in compliance with the construction plans,” this duty did not extend to third parties.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania Supreme Court Dismisses Appeal of Attorney Fee Award Under the Contractor and Subcontractor Payment Act
February 16, 2016 —
William J. Taylor – White and Williams LLPIn late December, the Supreme Court of Pennsylvania dismissed, as improvidently granted, the appeal in Waller Corporation v. Warren Plaza, Inc., No. 6 WAP 2015 (December 21, 2015). As a result, the Superior Court’s holding in that case that there is no good faith exception to the attorney fee provision of the Pennsylvania Contractor and Subcontractor Payment Act (CASPA), 73 P.S. §§ 501-516, remains intact.
In its decision in Waller, 95 A.3d 313 (Pa. Super. 2014), the Superior Court considered if there was a “good faith” exception to the interest and penalties provision of CASPA, 73 P.S. § 512(a), and whether there was a similar good faith exception to the attorney fee provision of the statute, 73 P.S. § 512(b). The court held that while an award of interest and penalties under § 512(a) could be denied if a party had a good faith basis for withholding payments due under a construction contract, no such exception exists for an award of attorney fees under § 512(b). Rather, an award of attorney fees is appropriate for the “substantially prevailing party” under a CASPA claim, and a claimant can be the substantially prevailing party even if the other party withheld payments in good faith.
Read the court decisionRead the full story...Reprinted courtesy of
William J. Taylor, White and Williams LLPMr. Taylor may be contacted at
taylorw@whiteandwilliams.com
Application Of Two Construction Contract Provisions: No-Damages-For-Delay And Liquidated Damages
February 14, 2022 —
David Adelstein - Florida Construction Legal UpdatesA recent Florida opinion between a prime contractor and a Florida public body touches upon two important issues: (1) the application of a no-damage-for-delay provision; and (2) the application of a liquidated damages provision. Both provisions find there way into many construction contracts. Unfortunately, the opinion is sparse on facts. Nevertheless, the application of these provisions is worthy of consideration.
In this opinion, Sarasota County v. Southern Underground Industries, Inc., 2022 WL 162977 (Fla. 2d DCA 2022), a county hired a contractor to install sanitary and water piping underneath a waterway. During construction, a nearby homeowner complained that vibration from the drilling caused damage to his home. As a result, the county stopped the contractor’s work to address a potential safety issue, as it was contractually entitled to do. The contractor hired a structural engineer to inspect the house and the engineer issued a report determining that any alleged damage was cosmetic and that there was sufficient monitoring of the vibrations to prevent future damage. The contractor also had an insurance policy to cover any homeowner claim for damage. However, upon receipt of the engineer’s report, the county did not lift its stop work order. Rather, the stop work order remained in place for an additional 71 days.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com