Craig Martin – Construction Contractor AdvisorContractors often ask if they should include a one year warranty in their subcontracts. I tell them that they can, but it may be more effective to include a one-year correction period. If a contractor does include a warranty in the contract, it may actually extend the time in which a contractor may be sued. I recommend instead a Correction Period.
Typical Construction Warranties
Form construction contracts, like the AIA forms, often times contain warranty language. The AIA A201, General Conditions, contains a warranty section that covers materials, but it does not address how long the work is warranted:
“3.5 WARRANTY
The Contractor warrants to the Owner and Architect that materials and equipment furnished under the Contract will be of good quality and new unless the Contract Documents require or permit otherwise. The Contractor further warrants that the Work will conform to the requirements of the Contract Documents and will be free from defects, except for those inherent in the quality of the Work the Contract Documents require or permit.”
Instead, the AIA A201, section 13.7, limits the time by which claims must be brought to 10 years or the applicable statute of limitations.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
New Defendant Added to Morrison Bridge Decking Lawsuit
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Morrison Bridge in Multnomah County, Oregon, has added a new company to their lawsuit regarding problems with the slip-resistant FRP decking, according to The Oregonian. The county has already named the installer, the supplier, and the manufacturer. Now, they have added Hardesty & Hanover, LLP, the company “that contracted with the decking manufacturer to provide engineering and design for the project.”
The Oregonian reported that “the county has identified a construction design professional who can testify that Hardesty & Hanover made errors that contributed to the Morrison Bridge's damage,” according to the amended complaint.
First, Conway construction (the deck installer) filed suit against the decking manufacturer and supplier. Then, the “county inserted itself into the suit last fall,” stated The Oregonian, and “is seeking more than $2 million to repair or replace the decking, plus damages.” A trial is scheduled for February 2015.
Read the court decisionRead the full story...Reprinted courtesy of
San Francisco Sues Over Sinking Millennium Tower
November 17, 2016 —
Beverley BevenFlorez-CDJ STAFFDennis Herrera, San Francisco’s city attorney, filed a lawsuit against the developer of the Millennium Tower, “for failing to inform buyers that it was sinking ‘much faster than expected,’” reported the New York Times. Mission Street Development sold more than 400 units in the skyscraper.
“They went ahead and sold condominiums for a handsome profit without telling the buyers about the situation,” Mr. Herrera told the New York Times. “This is every homeowner’s worst nightmare.”
The spokesman for the development, P.J. Johnson, stated that “the allegations by the city attorney had ‘no merit,’ and that the “building had sunk within ‘predicted, safe ranges’ during the entire sales process,” according to the New York Times. Furthermore, Johnson asserted that the problem derived from the nearby railroad station removing water from the ground, which “had caused the building to ‘settle beyond the 12 inches it was predicted to settle.’”
Read the court decisionRead the full story...Reprinted courtesy of
Three Key Takeaways from Recent Hotel Website ADA Litigation
April 26, 2021 —
Shane Singh & Grace Mehta - Lewis BrisboisDespite the COVID-19 pandemic and its chill on the hospitality industry, ADA-related digital lawsuits increased by approximately 23% in 2020. Many of these lawsuits are filed against hotels. The complaints allege that a hotel’s online reservation system failed to provide enough detail for individuals with disabilities to decide if the hotel meets their accessibility needs.
These plaintiffs will often claim that it is insufficient to describe an aspect of a hotel or room as “accessible” because the term is an opinion or conclusion. Plaintiffs argue that a hotel’s reservation system must report specific information, such as the dimensions of space under accessible desks and sinks, the slopes of surfaces, doorway clearance, and numerous other technical requirements under the ADA.
Many hotels are fighting back, arguing that the detail provided is sufficient and in compliance with the ADA. So far this year, in February 2021, two judges in the U.S. District Court for the Central District of California, Judge Percy Anderson and Judge Cormac Carney, agreed with the defendants, dismissing three cases with prejudice.
Reprinted courtesy of
Shane Singh, Lewis Brisbois and
Grace Mehta, Lewis Brisbois
Mr. Singh may be contacted at Shane.Singh@lewisbrisbois.com
Ms. Mehta may be contacted at Grace.Mehta@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Maximizing Contractual Indemnity Rights: Components of an Effective Provision
December 02, 2015 —
William Kennedy – White and Williams LLPTort law is aimed at providing compensation to the victims of negligence. Tort law encourages plaintiffs to cast a wide net, pursuing claims or suits against not only those whose fault seems manifestly primary, but also against defendants whose causal exposure is minimal, against those whose exposure is purely by operation of law. As discussed in the first installment of this series, "Maximizing Contractual Indemnity: Problems with Common Law," three common law principles – vicarious liability, joint and several liability, and common law indemnity – cause some parties to pay in excess of their actual degree of causal fault. Contractual indemnity can remedy that harsh result.
Part Two: Components of an Effective Provision
Properly composed, “broad form” contractual indemnity provisions permit an Indemnitee to shift the full range of financial consequences from tort exposure, including civil damages, defense fees, expert fees, and litigation expenses. Such contracts permit indemnity even where the underlying damage was incurred due to a degree of negligence or fault on the part of the Indemnitee. Such contracts can also allow an Indemnitee to shift to the Indemnitor the risk of loss for someone from whom the Indemnitor would otherwise be immune from suit (e.g., the Indemnitor’s employees). A well-written contract can even convert an entity which is an Indemnitor as to one party (e.g., a general contractor which has to indemnify a property owner) into an Indemnitee as to another party (e.g., a subcontractor) for the very same risk.
Read the court decisionRead the full story...Reprinted courtesy of
William Kennedy, White and Williams LLPMr. Kennedy may be contacted at
kennedyw@whiteandwilliams.com
Nevada Assembly Passes Construction Defect Bill
October 30, 2013 —
CDJ STAFFThe Nevada Speaker says that AB401 gives contractors what they want, but a contractors’ group has asked a Senate committee to kill the bill. Supporters of AB 401 say that it clarifies what qualifies as a construction defect and shortens the statute of limitations.
Read the court decisionRead the full story...Reprinted courtesy of
SEC Climate Change Disclosure Letter Foreshadows Anticipated Regulatory Changes
November 08, 2021 —
Karen C. Bennett & Jane C. Luxton - Lewis BrisboisWashington, D.C. (October 13, 2021) - In late September 2021, the Division of Corporation Finance of the Securities and Exchange Commission (SEC) issued a Sample Letter providing guidance to companies on how their climate disclosures will be analyzed for compliance with material risk reporting obligations. The Sample Letter precedes the SEC’s issuance of mandatory climate-related disclosure rules anticipated by year-end and signals a greater focus on specific information used to support securities filings, a development that businesses should take seriously.
The Sample Letter builds on climate change guidance the SEC issued in 2010 and identifies nine categories of disclosures the SEC suggests may be material risks that must be disclosed. These include:
- Consistency between a company’s corporate social responsibility report and its SEC filings;
- Risks associated with climate-related legislation, regulation, or policy, and resulting compliance costs;
- Litigation risks related to climate change; and
- Risks linked to an array of operational and market factors, including capital expenditures, continuity of business operations, supply chain stability, changing demand, reputation, availability of credit and insurance, and other climate-change related potential impacts on the financial condition of the company.
Reprinted courtesy of
Karen C. Bennett, Lewis Brisbois and
Jane C. Luxton, Lewis Brisbois
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Senate Minority Leader Gets Construction Defect Bill to Committee
April 03, 2013 —
CDJ STAFFThe Las Vegas Sun reports that Michael Roberson, the lead Republican in the Nevada Senate, managed to get his construction defect reform bill scheduled for a hearing. Previously, the Senate Democrats had determined that all bills pertaining to construction defect legislation would be heard by the Senate Judiciary Committee. However, Roberson managed to convince Kelvin Atkinson, the chair of the Senate Commerce and Labor Committee, to add his bill to the text a mortgage lending measure under consideration by that committee.
Roberson had previously submitted his bill to the Judiciary Committee. Senator Tick Segerblom has not scheduled the bill for a hearing and is reported to be an opponent of the bill. While Roberson characterizes the bill as making things better for homebuilders, Segerblom sees it as making things worse for homeowners. “That’s not going to happen,” Seberblom told the Las Vegas Sun.
Although the senate voted to send the bill to the Commerce and Labor committee, it still may not get a hearing. Segerblom said he did not know if the bill would be heard in his committee. “We’ve got 60 or more bills to hear and if there’s nothing new in there to change the world, I don’t know why we would hear it.” Atkinson said he has “no appetite to hear the bill.”
Read the court decisionRead the full story...Reprinted courtesy of