Application of Set-Off When Determining Prevailing Party for Purposes of Attorney’s Fees
February 22, 2021 —
David Adelstein - Florida Construction Legal UpdatesThe recent opinion from the Second District Court of Appeal in Hayward Baker, Inc. v. Westfield Ins. Co., 2020 WL 7767859 (2nd DCA 2020) demonstrates that the significant issues test for determining the prevailing party for purposes of attorney’s fees applies to disputes involving payment bonds under Florida’s Lien Law (Florida Statutes Chapter 713). The
significant issues test is more or less a subjective test where the party that is deemed to have prevailed on the significant issues in the case is the prevailing party for purposes of attorney’s fees in the case. A trial court has discretion to determine the prevailing party which will not be disturbed absent an appellate court finding the trial court abused that discretion. This significant issues test is an important consideration so that parties understand just because money ends up going their way does not necessarily mean they prevailed on the significant issues in the case. It could mean that. But it may not based on the claims and moneys involved in the dispute.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Restricts Principles of “General” Personal Jurisdiction
April 01, 2015 —
Kristian B. Moriarty and R. Bryan Martin – Haight Brown & Bonesteel LLPIn BNSF Railway Company v. Superior Court (Kralovetz) (Filed 3/27/2015, No. B260798), the California Court of Appeal, Second District, held a Delaware railroad corporation, with its principal place of business in Texas, was not subject to “general” personal jurisdiction in California, despite California housing 8.1% of the corporation’s total workforce, accounting for 6% of the corporation’s revenue, and containing just under 5% of its total track mileage.
Plaintiff, Vicki Kralovetz, filed suit in California Superior Court against defendant, BNSF Railway Company (“BNSF”), and others, for wrongful death. Plaintiff contended her husband was exposed to asbestos products manufactured by BNSF in Kansas while working at a dismantling facility owned by BNSF’s predecessor in interest. Plaintiff claimed the exposure caused her husband to contract mesothelioma, which resulted in his death.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at mmoriarty@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado SB 15-177 UPDATE: Senate Business, Labor, & Technology Committee Refers Construction Defect Reform Bill to Full Senate
April 01, 2015 —
Derek J. Lindenschmidt – Higgins, Hopkins, McLain & Roswell, LLCOn March 18th, following a lengthy hearing with testimony and questioning for and against Senate Bill 15-177, the Senate Business, Labor & Technology Committee voted 6 to 2 to refer the bill, with new amendments, to the full Senate.
While the main points of the bill remain strongly intact (check here for Senate Bill 177’s particulars), bill sponsors Senators Scheffler and Ulibarri offered four amendments, designed to bring additional compromise and clarity to the bill. The committee ultimately adopted these amendments, described below.
Amendment 16 removed a prior prohibition in the bill that would have prevented attorneys from assisting in the preparation of the notice required to be provided to all homeowners before the commencement of a construction defect claim. Amendment 19 complemented 16 by providing further clarification regarding the contents and specificities required in said notice, including a disclosure of projected attorneys’ fees, costs, duration, and financial impact of pursuing construction defect claims. Amendment 17 permitted homeowners to approve the pursuit of construction defect claims through written consent. Lastly, Amendment 18 provided clarification regarding the bill’s requirement that mediators and arbitrators be selected and approved through mutual agreement of the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Derek J. Lindenschmidt, Higgins, Hopkins, McLain & Roswell, LLCMr. Lindenschmidt may be contacted at
lindenschmidt@hhmrlaw.com
Construction Contract Clauses Which Go Bump in the Night – Part 1
November 10, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The first in a multi-part series, here are some other important construction contract clauses you may (or may not realize you should) be losing sleep over.
Provision: Incorporation and Flow-Down Provisions
- Typical Provision: “The term ‘Contract Documents’ shall include, without limitation, the Prime Contract, drawings, specifications and other agreements between Contractor and Owner, insofar as they relate in any way, directly or indirectly, to Subcontractor’s Work under this Agreement, and are hereby incorporated by reference. Subcontractor agrees to be bound to Contractor in the same manner and to the same extent as Contractor is bound to Owner under the Contract Documents. Where, in the Contract Documents, reference is made to Contractor, and the work and specifications therein pertain to Subcontractor’s trade, craft, or type of work, such work or specifications shall be interpreted to apply to Subcontractor rather than Contractor.”
- What it Means: An incorporation provision literally “incorporates” another document or documents into a contract by merely referring to them by title or description and it is not uncommon for a lower-tiered contractor to never see those documents.
A flow-down provision requires a lower-tiered contractor to comply with all obligations which a higher-tiered contractor, typically a direct contractor, owes to a higher-tiered party, typically, the owner. The intent of the provision to ensure that a lower-tiered subcontractor has no greater rights against a direct contractor has against the owner.
- What You Can Do: Lower-tiered contractors should obtain a copy of all documents to be incorporated into their contract and review them to ensure that they understand the obligations and any limitations to their rights.
Lower-tiered contractors should also seek to include language requiring that a higher-tiered contractor assume toward the lower-tiered contractor all obligations and limitations on their rights that the owner assumes toward or is subject to with respect of the general contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Traub Lieberman Attorneys Recognized in the 2022 Edition of The Best Lawyers in America®
September 13, 2021 —
Traub LiebermanTraub Lieberman is pleased to announce that three Partners have been selected by their peers for inclusion in the 2022 edition of The Best Lawyers in America®. In addition, five attorneys have been included in the 2022 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2022 Best Lawyers®
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants
St. Petersburg, FL
- Scot E. Samis – Appellate Practice
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Suit Limitation Provision Upheld
March 04, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's one year suit limitation provision was upheld, depriving insureds of benefits under the policy. Oswald v. South Central Mut. Ins. Co., 2018 Minn. App. Unpub. LEXIS 1077 (Dec. 24, 2018).
The Oswalds' hog barn burned down on June 21, 2016. Arson was a possible cause.
The Oswalds were insured under a combination policy issued by North Star Mutual Insurance Company and South Central Mutual Insurance Company. Central provided coverage for basic perils, broad perils, and limited perils, which included fire losses. The Central policy required property claims to be brought within one year after the loss. By endorsement, the North Star policy required suits be brought within two years after the loss. Presumably, the claims was denied, although the decision does not state this.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Deescalating Hyper Escalation
July 05, 2023 —
Paul F. Williamson - Construction Executive Recent years have seen the construction industry get hit by a perfect storm of rising costs, workforce shortages, delivery delays, supply-chain issues, inflation, interest-rate hikes and materials price escalation. The cost of construction has become more expensive, leaving all parties to grapple with the sufficiency of their risk-management strategies and the ramifications of contracts that are ill-equipped to deal with unprecedented cost increases. Of particular concern to industry participants are the volatile price fluctuations that construction materials have undergone and how to appropriately mitigate the risks they present.
Although owners, general contractors and subcontractors may seek to mitigate future risks, many who are party to an existing contract all too often must scramble to divine how to absorb significantly more financial risk than they expected pre-pandemic. Contracts that were bid and entered into prior to the pandemic may have seen, in some instances, double- and triple-digit percent increases in prices due to hyper escalation, with little recourse to address such situations. While parties to private contracts are free to mitigate their risk through contract negotiations, parties to federal or state public procurements are somewhat more constrained.
Reprinted courtesy of
Paul F. Williamson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Client Alert: Restaurant Owed Duty of Care to Driver Killed by Third-Party on Street Adjacent to Restaurant Parking Lot
January 07, 2015 —
R. Bryan Martin, Lawrence S. Zucker II, & Kristian B. Moriarty – Haight, Brown, & Bonesteel, LLPIn Annocki v. Peterson Enterprise, LLC, (Filed 11/14/2014, Certified for Publication 12/5/2014, No. B251434) the Court of Appeal, Second District, held a restaurant owed a duty of care to the driver of a motorcycle who died as a result of the negligent driving of a third party exiting the restaurant’s parking lot.
Decedent, Joseph M. Annocki, was driving his motorcycle on Pacific Coast Highway in Malibu, when it collided with the vehicle operated by Terry Allen Turner, who was exiting the parking lot of “Geoffrey’s" restaurant, which was owned and operated by the Defendant, Peterson Enterprise, LLC (“Peterson”).
The parents of the decedent (“Plaintiffs”) filed suit against Peterson, alleging Peterson failed to adequately staff the restaurant parking lot, which caused Turner to become confused and make an illegal left turn onto Pacific Coast Highway, thereby causing the accident that killed decedent. Plaintiffs further alleged Peterson knew, or should have known, that its parking lot and driveway were designed and in such condition as to create a danger of decreased visibility of the adjacent highway, and failed to adequately provide signage directing patrons that only right turns could be made onto Pacific Coast Highway.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
R. Bryan Martin,
Lawrence S. Zucker II and
Kristian B. Moriarty
Mr. Martin may be contacted at bmartin@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of