Contractual Impartiality Requires an Appraiser to be Unbiased, Disinterested, and Unswayed by Personal Interest
June 01, 2020 —
Frank Ingham - Colorado Construction Litigation BlogOn June 24, 2019, the Colorado Supreme Court held that when a contract or insurance policy requires an “impartial” appraisal, the appraiser for a party cannot be an advocate for that party.[1] In this situation, the appraiser must be unbiased, disinterested, without prejudice, and unswayed by personal interest. Id.
Owners Insurance Company (“Owners”) issued a policy to the Dakota Station II Condominium Association, Inc. (“Association”) that represents a 49-building multifamily residential property in Jefferson County, Colorado. Concerning loss conditions, the policy includes an appraisal provision requiring that, in the event of property appraisal, “each party will select a competent and impartial appraiser.” The parties would then select an umpire or have one appointed by the court. Any agreement as to the values reached by two of the three would bind them all.
On May 24, 2012, the Association made a storm-damage roofing claim to Owners for $1.33 million. The parties could not agree on the amount of the loss and the Association invoked the policy’s appraisal process. The Association retained Scott Benglen as its contingent-fee cap appraiser. Mr. Benglen retained Laura Haber as a policy and damage expert, who appraised the roof loss at $2.55 million and the total replacement at $4.3 million.[2] Owners’ appraiser, Mark Burns, submitted the loss at $1.86 million with the replacement cost award of $2.3 million. The umpire, Honorable James Miller, adopted Owners’ estimates in four of the six categories, awarding just over $3 million to the Association. Id.
Read the court decisionRead the full story...Reprinted courtesy of
Frank Ingham, Higgins, Hopkins, McLain & RoswellMr. Ingham may be contacted at
ingham@hhmrlaw.com
Federal Miller Act Payment Bond Claim: Who Gets Paid and Who Does Not? What Are the Deadlines?
September 16, 2019 —
William L. Porter - Porter Law GroupWhen working on federal public works construction projects there are no Stop Payment Notice or Mechanics Lien remedies available to protect subcontractors’ and suppliers’ right to payment. Instead, unpaid subcontractors and suppliers must resort to making a claim for payment under a federal law known as the AMiller Act@ (40 USCS 3131 et seq.). Many claimants however, do not realize that the right to make a Miller Act claim is not available to all subcontractors and suppliers. Before committing to performing work on a federal project it is important for subcontractors and suppliers to understand whether or not a Miller Act claim will be available. For those who have no Miller Act rights, careful consideration must be given to whether it is worth the risk to take on the project. For those who have valid Miller Act claim rights, important deadlines must be considered.
Who Gets Paid Under a Miller Act and Who Does Not
For federal projects in excess of $100,000, contractors who have a contract directly with the Federal Government must obtain Miller Act Payment Bond intended for the protection of Subcontractors, laborers and material suppliers to the project.
As a general rule, every subcontractor, laborer, or material supplier who deals directly with the prime contractor and is unpaid may bring a lawsuit for payment against the Miller Act Payment Bond. Further, every unpaid subcontractor, laborer, or material supplier who has a direct contractual relationship with a first-tier subcontractor may bring such an action. The deadlines for these claims are described below.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Assert a Party’s Noncompliance of Conditions Precedent with Particularity
July 26, 2017 —
David Adelstein - Florida Construction Legal UpdatesConstruction contracts oftentimes and should contain conditions precedent to payment. Conditions precedent apply to both progress payments and final payment. The conditions precedent operate such that payment is NOT due until the conditions are satisfied. The satisfaction of the conditions precedent triggers the payor’s obligation to pay.
If a dispute arises due to the payee’s noncompliance with conditions precedent to payment, the noncompliance should be asserted with particularity in the answer and affirmative defenses. For example, if a subcontractor was required to provide lien waivers and releases as a condition precedent to payment, then this should be asserted with particularity as an affirmative defense. If the contractor’s receipt of payment from the owner was a condition precedent to payment to the subcontractor (pay-when-paid), then this should be asserted with particularity as an affirmative defense. Any noncompliance with a condition precedent should be identified as an affirmative defense.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Were Quake Standards Illegally Altered for PG&E Nuclear Power Plant?
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFAn environmental group has brought a lawsuit alleging that “[f]ederal regulators secretly and illegally revised the license for California’s last nuclear power facility — PG&E’s Diablo Canyon — to mask the aging plant’s vulnerability to earthquakes,” according to SF Gate.
Friends of the Earth’s “suit claims that the Nuclear Regulatory Commission and Pacific Gas and Electric Co. last year changed a key element of the plant’s license related to seismic safety without allowing public input as required by law — or even notifying the public at all.”
However, spokesman Blair Jones claimed that “Friends of the Earth continues to mischaracterize the facts regarding seismic safety at Diablo Canyon. The facts are Diablo Canyon was built with earthquake safety at the forefront, is a seismically safe facility, and is in compliance with NRC licensing requirements.”
Read the court decisionRead the full story...Reprinted courtesy of
Contract Not So Clear in South Carolina Construction Defect Case
November 07, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has reversed a partial summary judgment issued by one of the lower courts in the case of The Retreat at Edisto Co-Owners Association v. The Retreat at Edisto. The underlying issues of the case deal with a construction defect complaint.
The lower court had concluded “Developer’s ‘First Amendment’ to the Master Deed required the Developer to satisfy the provision in the paragraph labeled ‘Master Deed Amendment or Phase II’ as a condition precedent to its election to proceed with the development of Phase II.”
The appeals court found that “the language of the First Amendment to the Master Deed is susceptible to more than one interpretation.” The court additionally concluded that the “Developer presented the requisite scintilla of evidence on the question of its intent in order to establish a genuine issue of material fact. As the material facts were in dispute, the appeals court reversed the summary judgment and remanded the case to the circuit court for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
New York State Trial Court Addresses “Trigger of Coverage” for Asbestos Claims and Other Coverage Issues
January 21, 2019 —
Paul Briganti - White and WilliamsOn November 21, 2018, the New York Supreme Court, Onondaga County, issued a summary-judgment ruling on a number of coverage issues arising from asbestos-related bodily injury claims against plaintiffs Carrier Corporation (Carrier) and Elliott Company (Elliott). See Carrier Corp., et al. v. Travelers Indem. Co., et al., Index No. 2005-EG-7032 (N.Y. Sup. Ct. Nov. 21, 2018).
First, the court held that under New York’s “injury in fact trigger of coverage,” injury occurs from the first date of exposure to asbestos through death or the filing of suit. The court primarily relied on: (1) New York federal court decisions and the Delaware Supreme Court’s decision in In re Viking Pump, Inc., 148 A.3d 633 (Del. 2016) holding that injury continues from first exposure through death or the assertion of a claim; and (2) medical and scientific evidence that the plaintiffs had submitted in support of their motion. The court specifically declined to follow Continental Cas. v. Wausau, 60 A.D.3d 128 (1st Dep’t 2008) (Keasbey), in which the New York Appellate Division found a question of fact whether injury occurs from exposure to asbestos through manifestation and that summary judgment was therefore inappropriate. The Carrier court stated that Keasbey was distinguishable because it “involved operations coverage, a non-product claim, and thus the [Keasbey] Court required a more stringent proof of injury in fact than is necessary here, in a products case.” Carrier, op. at 8. The Carrier court was also dismissive of affidavits offered by the defendant-insurer’s medical experts, finding that the affidavits did not create an issue of fact. See Op. at 2-9.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Briganti, White and WilliamsMr. Briganti may be contacted at
brigantip@whiteandwilliams.com
Ahlers & Cressman’s Top 10 Construction Industry Contract Provisions
July 02, 2014 —
Beverley BevenFlorez-CDJ STAFFJames R. Lynch of Ahlers & Cressman, PLLC, has published the first two parts of the four-part “Top 10 Construction Contract Provisions” series: “As a powerful mechanism to control contract risk, increase predictability, and reduce the cost and complexity of potential disputes, we frequently recommend that our clients’ contracts include a mutual waiver of consequential damages.”
The first part “explains the significance of such a clause and the risk a contractor assumes without it,” while the second part discusses “the various categories of damages flowing from a breach of contract and conclude[s] with examples of how parties can limit these damages to reflect their agreed allocation of risk.”
Read the full story, Part 1...
Read the full story, Part 2... Read the court decisionRead the full story...Reprinted courtesy of
The Leaning Tower of San Francisco
January 24, 2018 —
Dave Suggs - CDJ STAFFThe Millennium Tower located at 301 Mission Street in San Francisco, California opened in 2009 and is fifty-eight stories high. It is comprised of expensive apartments with price tags in the millions. “Yet for all its curb appeal, the building has, quite literally one fundamental problem: it’s sinking into mud and tilting towards its neighbors” reports John Wetheim of CBS News in the
60 Minutes segment about the condition of the tower “San Francisco’s Leaning Tower of Lawsuits.”
In the Tower’s basement along columns that protrude from the foundation of the building there are stress gauges lining the walls illustrating cracks with slow growth which is cause for concern. The tower is tilting a total of 14 inches toward the northwest and has sunk 17 inches so far. Petar Marinkovic, an engineer for the European Space Agency estimates that the tower is sinking 1.5 to 2 inches per year.
Jerry Cauthen, a local engineer, weighs in on what he believes is the cause of the sinking and leaning; it was built from concrete instead of steel. “Concrete is often cheaper. And it’s just as good, but it is a lot heavier. And so you got to design your foundation and your sub-surface to support that higher weight.” A local geotechnical engineer, Larry Karp agrees stating that the foundation of a building of this size and weight should be on solid rock (bedrock). The Millennium Tower is sitting on layers debris from the 1906 earthquake, a gold rush landfill, as well as clay, mud, and sand.
There over 20 parties involved in the Millennium Tower lawsuits so far. Solutions to “fix” the tower’s issues range from removing 20 stories from the top of the building to perpetually freezing the ground beneath the building. There are also ongoing mediation talks to determine the feasibility of drilling down to bedrock under a building where a thousand residents are still upstairs.
Read the court decisionRead the full story...Reprinted courtesy of