Denial of Motion to Dissolve Lis Pendens Does Not Automatically Create Basis for Certiorari Relief
November 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate decision out of Florida’s Sixth District Court of Appeal holds that a trial court’s denial of motion to dissolve a lis pendens does NOT automatically give a basis for a petition for a writ of certiorari. Generalized allegations of “irreparable harm” to support the basis for the petition for writ of certiorari are insufficient. Rather, the party moving for the petition MUST clearly demonstrate the irreparable harm; otherwise, the petition for writ of certiorari will fail.
A lis pendens has legal significance. It is a recorded document that notifies the world that there is a pending lawsuit dealing with the real property at issue. This is important because who wants to buy a piece of property that is subject to litigation – that would be a risky transaction!
In CPPB, LLC v. Taurus Apopka City Center, LLC, 48 Fla.L.Weekly D1837a (Fla. 6th DCA 2023), a dispute arose as to a real estate transaction. The owner sold a parcel to a buyer. The owner also owned three adjacent parcels. As part of the transaction, the buyer agreed to perform certain improvements to all of the parcels including those adjacent parcels owned by the owner. The owner deposited funds in escrow for purposes of its share of the improvements. A payment dispute arose regarding the improvements and the buyer sued the seller. The seller filed a counterclaim to rescind the transaction along with a recorded lis pendens on the parcel purchased by the buyer. The buyer moved to dissolve the lis pendens which the trial court denied. This prompted the appeal – a petition for a write of certiorari based on the trial court’s denial of the motion to dissolve the lis pendens.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
A Guide to California’s Changes to Civil Discovery Rules
April 29, 2024 —
Lewis Brisbois NewsroomSan Diego, Calif. (April 10, 2024) - California legislators have changed the rules of discovery in civil cases through the passage of amendments to Code of Civil Procedure sections 2016.090 and 2023.050, effective January 1, 2024.
Section 2016.090 creates a new set of rules for civil litigators in cases filed on or after January 1, 2024, which permits any party to the litigation to demand initial disclosures be provided within 60-days. Such a demand can be made any time after a party has filed a responsive pleading, including a demurrer or motion to strike.
Notably, this rule requires production of all information relevant to any causes of action that are pled at the time of the demand, meaning the parties may be required to disclose information related to claims that are being challenged on demurrer or a motion to strike, such as claims for punitive damages. This statute is only implicated when one of the parties to the action makes a demand and may be modified by stipulation of the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Eight Ways to Protect a Construction Company Before a Claim Is Filed
November 04, 2019 —
Mary Bacon - Construction ExecutiveClaims are inevitable in the construction industry. They can take on a life of their own and come with the burden of legal fees, wasted executive time and a possible judgment. Too often the only winners are the lawyers.
TIPS FOR PROTECTING MANAGEMENT AND THE BUSINESS BEFORE A CLAIM IS FILED
- Respect the business entity’s corporate structure. First and most importantly, respect the business entity’s corporate form. Legal entities have certain formalities like filing an annual list of officers, maintaining separate bank accounts, conducting certain meetings and following bylaws, etc. Respect these formalities. Failure to follow them exposes the owner to personal liability for company debts. And while a business claim has the potential to wipe out a business, owners should not risk having their personal assets on the line as well.
- Get a good contract. In most instances, a contract governs what happens and who is responsible for payment associated when a certain issue or dispute arises. A clear, well-written contract can often avoid a dispute or liability for a dispute. Actively participate in the contract negotiation and drafting process to make sure each party’s role and responsibilities are clearly accounted for.
- Make friends with clients. While it is true that “business is business,” people are often fairer and more willing to work towards a solution for people they are friends with. In most cases, friends will help friends in ways that people would not help mere business associates. When encountering a problem on a job, a friend may be willing to help achieve a more favorable outcome.
Reprinted courtesy of
Mary Bacon, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Bacon may be contacted at
mbacon@spencerfane.com
Manufacturer of Asbestos-Free Product May Still Be Liable for Asbestos Related Injuries
July 30, 2015 —
Kristian B. Moriarty, R. Bryan Martin and Lee Marshall – Haight Brown & Bonesteel LLPIn Sherman v. Hennessy Industries, Inc. (No. B252566, filed June 18, 2015), the Court of Appeal, Second District, reversed a trial court’s grant of summary judgment in favor of a manufacturer of a brake grinding machine. The Court cited an exception to the general rule that manufacturers may not be held liable, under a strict products liability theory, where the plaintiff’s injuries arise from other products that are used in conjunction with the defendant’s product.
Plaintiff and appellant, Michael Sherman, was an automobile mechanic from 1962 to 1977. Mr. Sherman alleged that during this period he used an arcing machine, which abraded brake linings by means of sand paper moving at high speeds. Sherman alleged the machine released asbestos dust, which he then brought home, exposing his wife Debra Sherman to asbestos. Ms. Sherman developed mesothelioma and passed away from exposure to the asbestos dust carried home by her husband.
Reprinted courtesy of
Kristian B. Moriarty,
R. Bryan Martin and
Lee Marshall of Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Mr. Marshall may be contacted at lmarshall@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Contractor License Bonds to Increase in 2016
December 02, 2015 —
Garret Murai – California Construction Law BlogThe post, which originally appeared on
The Surety Bond Insider, was written by Jon Gottschalk, a member of the SuretyBonds.com Educational Outreach team. on
SuretyBonds.com helps contractors fulfill their bonding requirements.
The Contractors State License Board (CSLB) is requiring all California contractors to purchase a $15,000 bond by January 1, 2016— a $2,500 increase from the $12,500 amount that was previously required. The additional $2,500 was previously accounted for by an additional requirement to obtain a contractor’s license. Those applying for the license had to post the $12,500 surety bond and proof of financial solvency in the amount of $2,500. Essentially, contractors were required to show that their current assets were greater than their liabilities by no less than $2,500. By increasing the bond amount to include that additional $2,500, the CSLB has removed the burden of proving financial solvency from those who wish to obtain their license.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Update Regarding New York’s New Registration Requirement for Contractors and Subcontractors Performing Public Works and Covered Private Projects
February 06, 2023 —
Christopher B. Kinzel, K. Greer Kuras, Aaron C. Schlesinger - Peckar & Abramson, P.C.Some significant changes are being made by chapter amendments (S.838 and A.984) to Section 220-i of New York’s Labor Law. Contractors and subcontractors bidding on public contracts and performing work on covered private projects will have two years (by December 30, 2024) to register with the Department of Labor, Bureau of Public Works, rather than one year. The amendments also remove the requirement that a contractor submit registration certificates for all its subcontractors at the time its bid is submitted; amend language with respect to notice and hearing requirements; require re-registration to occur not less than 90 days before expiration; and add language to require a monitor to oversee ongoing work if a contractor or subcontractor is found unfit.
The stated purpose of the law is to help enforce New York’s prevailing wage and other worker protection laws. The DOL will create an online system through which contractors and subcontractors will have to answer questions and submit documents about:
- the business entity and its owners and officers
- unemployment and workers’ compensation insurance
- any outstanding wage assessments
- debarment under New York or federal law, or any other state’s laws
- final determinations of a violation of any labor laws, employment tax laws, or workplace safety standards (including OSHA)
- association or signatory to an apprenticeship program
Reprinted courtesy of
Christopher B. Kinzel, Peckar & Abramson, P.C.,
K. Greer Kuras, Peckar & Abramson, P.C. and
Aaron C. Schlesinger, Peckar & Abramson, P.C.
Mr. Kinzel may be contacted at ckinzel@pecklaw.com
Ms. Kuras may be contacted at gkuras@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Five Types of Structural Systems in High Rise Buildings
November 02, 2020 —
Chris Jackson - Construction ExecutiveToday, many cities in different countries have high-rise buildings or more popularly known as skyscrapers. The concept of skyscraper was first used to define the more than 137-foot-high buildings constructed in Chicago in 1885. It is generally defined as one that is taller than the maximum height that requires mechanical vertical transportation for people. Usually, these buildings only have limited uses and are primarily focused on functioning as residential apartments, hotels and office buildings, though they occasionally include retail and educational facilities. Because high-rise buildings are among the largest buildings built, it is necessary that their commercial and office functions require a high degree of flexibility.
That’s why it is important for high-rise buildings to have structural systems or structural frames—the assembly of interrelated or interdependent elements that forms a complex structure. These structural systems are built and designed for resisting different loads. To further understand how structural systems work, take the human body as a comparison. If human bones are weak and not properly aligned, the human body as a whole will not be able to perform or work well. Structural systems, in the same way, would not be able to take loads if not built properly. After all, no one wants a toppling skyscraper. To give the readers more information about structural systems in high-rise buildings, this article will discuss some of them.
Reprinted courtesy of
Chris Jackson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers & Cressman’s Top 10 Construction Industry Contract Provisions
July 02, 2014 —
Beverley BevenFlorez-CDJ STAFFJames R. Lynch of Ahlers & Cressman, PLLC, has published the first two parts of the four-part “Top 10 Construction Contract Provisions” series: “As a powerful mechanism to control contract risk, increase predictability, and reduce the cost and complexity of potential disputes, we frequently recommend that our clients’ contracts include a mutual waiver of consequential damages.”
The first part “explains the significance of such a clause and the risk a contractor assumes without it,” while the second part discusses “the various categories of damages flowing from a breach of contract and conclude[s] with examples of how parties can limit these damages to reflect their agreed allocation of risk.”
Read the full story, Part 1...
Read the full story, Part 2... Read the court decisionRead the full story...Reprinted courtesy of