Supreme Court of New Jersey Reviews Statutes of Limitation and the Discovery Rule in Construction Defect Cases
July 18, 2018 —
David Suggs – Bert L. Howe & Associates, Inc.Robert Neff Jr. of Wilson Elser analyzed the recent case, Palisades at Fort Lee Condo. Ass’n v. 100 Old Palisade, LLC, 2017 N.J. Lexis 845, 169 A.3d 473 (Supreme Court of New Jersey, September 14, 2017), and states that this ruling “gives defendants the ability to defend against the assertion that the statute of limitations was tolled until the most recent owner (and plaintiff) discovered the cause of action.”
Neff concludes that a statute of limitations test needs to be conducted at the beginning of each case: “In Palisades, the motions to dismiss based on the statute of limitations were filed at the conclusion of all discovery. While an initial analysis might yield the conclusion that certain discovery will be needed to ascertain the appropriate accrual date (or dates, in the case of multiple defendants), counsel will then know what discovery to seek during the discovery period.”
Read the court decisionRead the full story...Reprinted courtesy of
Look to West Africa for the Future of Green Architecture
May 16, 2022 —
Kriston Capps - BloombergIn 2014, a crowd of demonstrators stormed Burkina Faso’s National Assembly building, setting it ablaze and ending the nearly 30-year rule of President Blaise Compaoré.
A year later, Burkenabè architect Diébédo Francis Kéré was asked to imagine a new parliamentary building — one that would reflect a more democratic future for the West African nation. Kéré conceived a six-story stepped pyramid that slopes up gently from the ground, inviting citizens to gather, climb and take in views of the capital city, Ouagadougou. The ruins of the former parliament building next door would be transformed into a rainwater-collecting memorial park.
The project remains a ways off: Burkina Faso continues to struggle with political unrest, including a coup d’état in January 2022. But Kéré’s fast-growing prominence may improve the odds that his vision will eventually materialize. In March, he became the first African architect to win the Pritzker Architecture Prize, the design field’s top honor.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Construction Case Alert: Appellate Court Confirms Engineer’s Duty to Defend Developer Arises Upon Tender of Indemnity Claim
January 27, 2010 —
Steven M. CvitanovicIn the recent case of UDC-Universal Development, L.P. v. CH2M Hill, 2010 Cal.App.LEXIS 47 (filed January 15, 2010), the Sixth District Court of Appeal provided a stunning illustration of the far-reaching effects of the California Supreme Court’s holding in Crawford v. Weather Shield Manufacturing Inc. (2008) 44 Cal.4th 541. In Crawford, the Court held the duty to defend under an indemnity agreement arose upon the mere tender of defense of a claim covered by the indemnity.
In the UDC case, CH2M Hill provided engineering and environmental planning services to developer UDC on a project that ultimately wound up in a construction defect lawsuit by the homeowners association ( HOA ). UDC tendered its defense to CH2M Hill, the tender was rejected, and UDC filed a cross-complaint for negligence, breach of contract and indemnity against CH2M Hill and others. After the HOA’s construction defect claims were settled, UDC proceeded to trial against CH2M Hill. The jury found in favor of CH2M Hill on the claims for negligence and breach of contract. At the request of the parties prior to trial, the trial court ruled on the application of the indemnity agreement in light of Crawford and, in so doing, found that the defense obligation arose upon the tender and that CH2M Hill breached that duty despite the jury finding in favor of CH2M Hill.
The Court of Appeal affirmed, noting that the defense obligation arose as soon as the defense was tendered and did not depend on the outcome of the litigation, and that the HOA’s general description of the defects along with an allegation that Doe engineers were negligent triggered the duty to defend.
Although this case did not expand the crushing impact of Crawford’s holding, it is
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Safe Commercial Asbestos-Removal Practices
April 18, 2023 —
Emily Newton - Construction ExecutiveContractors must proceed with caution to safely remove asbestos and protect employees and commercial buildings. Only contractors licensed by the Environmental Protection Agency (EPA) in abatement should dispose of it, because the best asbestos-removal practices require high degrees of care and safety.
Asbestos is a stealthy material, quickly becoming airborne and contaminating other areas of the building and humans. No matter a contractor's tenure in the field, it's vital to remember the top practices in the industry as people learn more about elusive, toxic asbestos-containing materials (ACMs).
Wait for Technician and Inspector Feedback
It’s important to find out if a jobsite contains asbestos. Proceed with caution if the structure was built before the 1990s. The removal process shouldn't start immediately if a business suspects asbestos and reaches out to a company. Inspectors scope the situation and grab samples for lab testing to determine how abaters should handle the case. They will need to know every potential hiding place for the asbestos, analyzing everything from caulking to wiring for asbestos coatings and other variants of the substance. This may take time, but commercial contractors must wait until they receive this information before proceeding.
Reprinted courtesy of
Emily Newton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations 2016 DE, MA, NJ, NY and PA Super Lawyers and Rising Stars
October 27, 2016 —
White and Williams LLPThirty-two White and Williams lawyers have been named by Super Lawyers as a Delaware, Massachusetts, New Jersey, New York or Pennsylvania "Super Lawyer" while fourteen received "Rising Star" designations. Each lawyer who received the distinction competed in a rigorous selection process which took into consideration peer recognition and professional achievement. The lawyers named to this year's Super Lawyer list represent a multitude of practices throughout the firm.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Build, Baby, Build. But Not Like This, Britain.
March 04, 2024 —
Matthew Brooker - BloombergThe UK needs to do a lot more building. A lack of access to physical and digital connections is holding back the economy, the government says. Besides tackling the housing crisis, the country has to construct more roads, railways, wind farms and reservoirs to open up opportunity and drive productivity. The only problem is that Britain is notoriously inept at delivering infrastructure projects on time and within budget.
The advantage of doing things badly is that at least you get to learn from your mistakes — in theory. Updates this month have offered some illuminating insights into two of the biggest civil-engineering undertakings in the country: High-Speed Rail 2, better known as HS2, and Hinkley Point C, which will be Britain’s first new nuclear power station since 1995. Here are five lessons that can be drawn from the issues encountered by two projects with a combined bill that’s likely to exceed £100 billion ($127 billion):
Don't take budgets too seriously — especially at the start. Fixing an initial budget that was too low may have done much to feed later perceptions that HS2’s costs were spiraling out of control. The original estimate for the expanded train network was set too early and based on “very immature data,” Jon Thompson, appointed executive chair of High Speed 2 Ltd. in February last year, told the House of Commons transport committee. Numbers get more accurate and reliable as work progresses and the quality of information improves. What were viewed as cost blowouts partly reflected this process. The effect was unfortunate, undermining political support for HS2 and providing cover for cutbacks that have reduced the network to a single line between London and Birmingham that fails to fulfill most of its original purpose. To avoid this problem: Stick to a range rather than a single figure, and make sure people understand the uncertainties inherent in early-stage estimates.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Brooker, Bloomberg
Florida Court Gives Parties Assigned a Subrogation Claim a Math Lesson
August 04, 2021 —
Lian Skaf - The Subrogation StrategistAlthough the focus of most subrogation cases is usually on proving liability, determining the appropriate measure of damages is just as important. Sometimes turning on a nuanced argument for recoverability, an adverse holding can significantly boost or reduce the total damages in a case. The Court of Appeal of Florida, Fourth District (Court) recently decided such an issue in a case involving subrogation, holding that the defendants owed much more than they originally anticipated.
In Five Solas v. Ram Realty Servs., No. 4D19-2211 2021, 2021 Fla. App. LEXIS 7546, the Court reviewed the appropriate setoff in damages that the defendants were entitled to when measuring the recoverable damages. The Court reversed the lower court’s holding, which held that the defendants were entitled to a setoff that limited the jury’s award to $104,481.75. Instead the Court held that the defendants were only entitled to a setoff equal to the excess recovery over replacement cost.
The case involves, among other things, property damage sustained by building owner Five Solas (Owner) and its lessee William Price, P.A. from a collapsed wall originating from the property of the defendants, Ram Realty Services, LLC and Sodix Fern, LLC d/b/a Alexander Lofts (collectively referred to as Defendants). Owner’s carrier, Foremost Insurance Company (Foremost), paid out its policy limit of $430,518.25 to Owner for damage to the building. Owner then pursued its claim against the tortfeasors for the remaining damages not paid by its carrier.[1] Foremost also pursued a subrogation claim, but settled its subrogation claim with Defendants, assigning its subrogation rights to Defendants.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Homeowner’s Claims Defeated Because “Gravamen” of Complaint was Fraud, not Breach of Contract
September 29, 2021 —
Garret Murai - California Construction Law BlogBe careful what you wish for or, as in the next case, what you plead. In Vera v. REL-BC, LLC, Case Nos. A155807, A156823, and A159141 (June 30, 2021) 1st District Court of Appeal, a the buyer of a remodeled home who asserted breach of contract and fraud claims against a developer discovered that her claims, including her breach of written contract claim, was subject to a shorter 3 year statute of limitations because the “gravamen” of her complaint was fraud.
The REL-BC Case
Homeowner Adriana Vera purchased a remodeled home in Oakland, California from developers REL-BC, LLC and SNL Real Estate Solutions, LLC. The developers had purchased the home in July 2011, remodeled it, and sold it to Vera in November 2011.
As is typical in such transactions, the purchase agreement for the house required that the sellers disclose known material facts and defects affecting the property. In their disclosure, the sellers stated that they were not aware of any significant defects or malfunctions with respect to the property. The disclosure also stated that the sellers were not aware of any water intrusion issues with respect to the property.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com