Forethought Is Key to Overcoming Construction Calamities
February 10, 2020 —
Mitch Cohen - Construction ExecutiveWithout warning, an under-construction structure in the southern United States suffered a catastrophic collapse. The tragedy resulted in the death of several people. As a result, engineering and construction post-collapse forensics experts engaged in an 18-month investigation.
Those involved in the design and build project included the general contractor hired by the owner, a prime engineer, a consulting peer-review engineer and a prime structural design firm supported by a sub-consulting structural engineer. Although significant cracking was noticed several weeks before the failure, no one sounded the alarm or deemed the cracking worthy of corrective action.
In their findings, forensic experts found the collapse resulted from the combined failure of the general contractor, engineers and even the owner, who all failed to shut down the work once the cracking reached unacceptable levels and/or take the appropriate actions needed to secure the public safety and mitigate the risk. This was even after the general contractor requested that the engineer-of-record and design manager assess the structure’s extreme cracking. Consequently, the choice to not seriously investigate the crack or seek an independent peer review to design a rectification plan contributed directly to the tragedy. This is typically referred to within the industry as a “negligent professional design error.”
Reprinted courtesy of
Mitch Cohen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Cohen may be contacted at
mitch.cohen@rtspecialty.com
In Massachusetts, the Statute of Repose Applies to Consumer Protection Claims Against Building Contractors
January 28, 2019 —
Shannon M. Warren - The Subrogation StrategistIn Bridgwood v. A.J. Wood Construction, Inc., 105 N.E.3d 224 (Mass. 2018), the Supreme Court of Massachusetts determined that the statute of repose barred the plaintiff’s consumer protection claims commenced more than six years after the occurrence of the event that gave rise to the claims. In Bridgwood, the homeowner filed suit against the contractors who had performed renovations 15 years earlier. The homeowner asserted that concealed faulty electrical work caused a fire 11 years after the work was completed. The complaint alleged that the contractors, by violating Mass. Gen. Laws. Chapter 142A §17(10), committed an unfair and deceptive act pursuant to Mass. Gen. Laws Chapter 93A.
Section 17(10) prohibits contractors from violating building laws and specifically states that a violation of Section 17(10) constitutes an unfair and deceptive act as defined by Chapter 93A. Chapter 93A is regarded as one of the most stringent consumer protection statutory schemes in the nation, and allows litigants to seek remedies such as treble damages and attorney fees.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and WilliamsMs. Warren may be contacted at
warrens@whiteandwilliams.com
OSHA Issues New Rules on Injury Record Keeping
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorOn July 28, 2015, OSHA issued proposed rules seeking to clarify an employer’s ongoing obligation to make and maintain accurate records of work-related injuries and illness. The new rules were drafted in response to the U.S. Court of Appeals decision in AKM LLC, d/b/a Volks Constructors v. Secretary of Labor, in which a contractor successfully argued that OSHA’s citation was issued well beyond the six month limitation period.
OSHA’s Injury Record Keeping Obligations
The Occupational Safety and Health Act requires each employer to make, keep and preserve records of workplace injuries and illnesses. 29 U.S.C. § 658(c). OSHA has promulgated a set of regulations which require employers to record information about work-related injuries and illnesses in three ways. Employers must prepare an incident report and a separate injury log “within seven (7) calendar days of receiving information that a recordable injury or illness has occurred,” 29 C.F.R. § 1904.29(b)(3), and must also prepare a year-end summary report of all recordable injuries during the calendar year, id. § 1904.32(a)(2). An employer “must save” all of these documents for five years from the end of the calendar year those records cover. 29 C.F.R. § 1904.33(a).
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
“Incidental” Versus “Direct” Third Party Beneficiaries Under Insurance Policies in Which a Party is Not an Additional Insured
April 18, 2023 —
Garret Murai - California Construction Law BlogAs they say, when it rains, it pours. Indemnity and insurance are the “Big Two” when it comes to risk avoidance on construction projects. The next case,
LaBarbera v. Security National Security Company, 86 Cal.App.5th 1329 (2022), involves both. It’s an interesting case, which I think could have gone either way, involving claims by a higher-tiered party that they were a third party beneficiary under an insurance policy in which they were not named as an additional insured.
The LaBarbera Case
The Indemnity Provision and Insurance Policy
In June 1016, Chris LaBarbera hired Richard Knight doing business as Knight Construction to remodel his house in Carmichael, California. The construction contract included an indemnity provision which provided that Knight would defend and indemnify LaBarbera from all claims arising out the remodeling work except for claims arising from LaBarbera’s sole negligence and willful misconduct.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Dump Site Provider Has Valid Little Miller Act Claim
October 19, 2020 —
Christopher G. Hill - Construction Law MusingsYou may have thought that a Virginia “Little Miller Act” bond claim, like a mechanic’s lien, could only be brought by those that provide materials and labor incorporated into the construction project. If you did, you aren’t alone.
In fact, Safeco Insurance Co. of America, a surety, made exactly the above argument in Yard Works LLC v. GroundDown Constructors LLC. In that case, a debris hauling company failed to pay Yard Works, the company that provided the dumping site for the debris. Yard Works sued pursuant to the Little Miller Act to get paid. In response, the surety sought to have the claim against the payment bond dismissed and argued that because Yard Works did not actually improve the property or provide improvements and that Yard Works only passively provided a dump site, Yard Works could not claim under the payment bond.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
DC Circuit Issues Two Important Clean Air Act and Administrative Law Decisions
December 16, 2019 —
Anthony B. Cavender - Gravel2GavelThe U.S. Court of Appeals or the District of Columbia has recently issued two important rulings on the Clean Air Act in particular and administrative law in general: California Communities Against Toxics, et al., v. EPA and Murray Energy Corporation v. EPA.
The Battle of the Memos: Seitz Makes Way for Wehrum
In the California Communities case, decided on August 20, 2019, the court held, in a 2 to 1 decision, that a petition to review a change in EPA policy announced in an agency memorandum which reversed an agency policy announced nearly 25 years ago in another agency memo must be rejected because the memo at issue was not a “final agency action” subject to the Administrative Procedure Act (APA). In 1995, the “Seitz Memo,” which interpreted Section 112 of the Clean Air Act and addresses the regulation and control of hazardous air pollutants from stationary sources, stated that once a source of toxic emissions is classified as “major,” the facility remains subject to regulation as a major source even if the facility makes changes to the facility to limit its potential to emit such toxics below the major source threshold. Then, in 2018 under a new administration, the “Wehrum Memorandum” was issued which reversed this policy and its interpretation of the law. (Both memos were issued without any kind of advance notice or opportunity to comment.) If a source takes steps to limit its potential to emit, then it may be regulated as an area source, and subject to less rigid regulation. The court majority held that the Wehrum Memo was not a final agency action and was not subject to judicial review when it was measured against both prongs of the “finality test” devised by the Supreme Court in the cases of Bennet v. Spear, 520 US 154 (1997) and US Army Corps of Engineers v. Hawkes, 136 S. Ct. 1807 (2016). While the memo undoubtedly represented the consummation of the agency’s decision-making process, the memo had no direct and appreciable legal consequences, and not therefore being a final action, the case must be dismissed. Judge Rogers filed a strong dissenting opinion.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Real Estate & Construction News Round-Up (08/24/22) – Local Law 97, Clean Energy, and IRA Tax Credits
September 26, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up features the intersection of real estate and energy efficiency, including state efforts surrounding clean energy legislation, Inflation Reduction Act tax credits, hotel & hospitality sectors creating sustainable initiatives to reduce carbon emissions, and more.
- In New York City, building owners try to figure out how to pay for upgrades needed to comply with regulations outlined in Local Law 97 that are intended to fight climate change. (Jane Margolies, The New York Times)
- Maryland, Massachusetts, and New York approve clean energy legislation, enacting laws to promote electric vehicles as well as wind and solar energy. (ACEEE)
- The Inflation Reduction Act (IRA), signed into law by President Biden this week, includes expanded tax credits expected to pivot building owners and property developers to make upgrades geared towards energy efficiency. (Jack Rogers, Globe St.)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Clean Water Act Cases: Of Irrigation and Navigability
January 06, 2020 —
Anthony B. Cavender - Gravel2GavelThe federal courts have recently decided two significant Clean Water Act (CWA) cases: State of Georgia, et al. v. Wheeler, where the US District Court for the Southern District of Georgia held that the 2015 rulemaking proceeding of EPA and the U.S. Army Corps of Engineers redefining the term “Waters of the United States” in the CWA violated the Act as well as the Administrative Procedure Act; and the Ninth Circuit’s decision in Pacific Coast Federation of Fishermen’s Associations, et al. v. Glaser, where the appeals court ruled that the lower court erroneously interpreted a CWA NPDES permitting exception involving agricultural return flows.
An Absence of Navigability: State of Georgia, et al. v. Wheeler
Decided on August 21, 2019, the district court, one of the few courts to grapple with the rule’s compliance with the CWA and the Administrative Procedure Act (APA), held that the agencies’ redefinition of the terms “Interstate Waters,” “Tributaries” and “Adjacent Waters” violated the CWA by reading “navigability” out of the new definitions, or by failing to adhere to the Supreme Court’s rulings in the 2005 case of Rapanos v. United States, in particular Justice Kennedy’s concurrence regarding the application of the “significant nexus” in case-by-case adjudications as to whether a particular body of water was covered by the Act. Moreover, some provisions of the rule conflicted with the APA because they were not a logical outgrowth of the rules proposed by the agencies in 2014, and on which they solicited comments, and other determinations were not supported by a reasonable explanation. In addition, without a clear statement from Congress that it supported the rule’s effect of increasing the nature and extent of enhanced federal jurisdiction over waters subject to the CWA, the court was loathe to approve the rule. Accordingly, the rule was remanded to the agencies for additional review consistent with this decision.
This decision is of particular importance as it may well be the first case to subject this new EPA rule—the linchpin of much of EPA’s regulation under the CWA—to extended review. (Other courts have only been asked to enjoin the rule, which involves a different type of review.)
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com