Cumulative Impact Claims and Definition by Certain Boards
June 21, 2024 —
David Adelstein - Florida Construction Legal UpdatesWhat is a cumulative impact claim? This is commonly referred to as the unforeseeable ripple effect of changes, i.e., the death by a thousand cuts. Cumulative impact claims refer to a disruption on productivity based on the cumulative impact of changes and their impact on unchanged work. Cumulative impact claims are difficult claims to prove, particularly based on the causation standpoint (and argument they could be released based on change order language). If pursuing or considering a cumulative impact claim, you will need to work with a consultant(s) and lawyer that understand the dynamic of these claims to best maximize your arguments and recovery from a causation and damages standpoint. Cumulative impact damages are real. They occur. But they are not damages you can just throw out there or use loosely and expect to develop traction on compensation.
Below is how cumulative impact claims are defined by certain Boards of Contract Appeals. The definitions are important.
In Appeal of Centex Bateson Construction, Co., Inc., 9901 BCA P 30153, VABCA 4613 (VABCA 1998), the Board explained:
Direct impact, as the immediate and direct effect of a change on unchanged work, is considered foreseeable.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Labor Shortages In Construction
December 04, 2023 —
Jason Feld & Chris Bates - Kahana FeldSimilar to other industries, the ongoing labor shortage crisis in the United States is detrimentally impacting construction activities in both the residential and commercial sector. According to the Bureau of Labor Statistics, the turnover rate for the construction industry since 2021 has risen to 56%. And while the national unemployment rate ranges between 0.4% to 7.5%, the unemployment rate for construction is roughly four times the national average (See, Associated Builders and Contractors, Markenstein Advisors Report dated July 28, 2023). 73% of workers preferred to stay in a remote work environment, and another 40% of the global workforce has elected to voluntarily remove themselves from the workplace. (See, 2021 Microsoft Work Index). In particular with the construction industry, employment rates have returned to pre-pandemic levels hovering around 12% unemployment in 2020 to 6% in 2022. (See, Joint Center for Housing Studies at Harvard University, Carlos Martin).
So where did all the workers go? During the height of the 2020 Covid-19 Pandemic and for the next few years, the county experienced what most people are calling “The Great Resignation”. May people took jobs with better pay and better alignment with their values. Approximately 40% stated a new business. Many elected to become stay-at-home parents forgoing a paycheck to raise their families while the other spouse works, especially due to the rising costs of childcare. About 1 in every 4 baby-boomers retired. Others took part-time employment, entered military service or left the workforce due to disability or injury. (See, Bloomberg Businessweek).
Reprinted courtesy of
Jason Feld, Kahana Feld and
Chris Bates, Kahana Feld
Mr. Feld may be contacted at jfeld@kahanafeld.com
Mr. Bates may be contacted at cbates@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Thanks for My 6th Year Running as a Construction Litigation Super Lawyer
May 16, 2022 —
Christopher G. Hill - Construction Law MusingsIt is with humility and a sense of accomplishment that I announce that I have been selected for the sixth straight year to the Virginia Super Lawyers in the Construction Litigation category for 2022. Add this to my recent election to the Virginia Legal Elite in Construction and I’ve had a pretty good year. As always, I am thrilled to be included on these peer-elected lists.
So without further ado, thank you to my peers and those on the panel at Virginia Super Lawyers for the great honor. I feel quite proud to be part of the
5% of Virginia attorneys that made this list for 2020.
The full lists of Virginia Super Lawyers will appear in the May edition of Richmond Magazine. Please check it out.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Performance Bonds: Follow the Letter of the Bond and Keep The Surety Informed
December 06, 2021 —
Bill Shaughnessy, Jones Walker, LLP - ConsensusDocsConstruction surety bonds are risk management tools utilized by parties on large construction projects. However, bonds are not insurance, and a surety is not an “insurer” of the project. Different from insurance, a surety’s obligation to act typically arises if the principal fails to perform in accordance with the construction contract, and if the claimant satisfies the conditions precedent to enforcing the bond.[1]
This article focuses exclusively on performance bonds on private projects,[2] and highlights practical considerations and surety defenses to enforcement of the performance bond.[3] Spoiler alert – the party making a claim on the bond must strictly adhere to the conditions precedent set forth in the bond throughout the construction project and when calling upon the surety to take action, otherwise the performance bond may be rendered void and unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Shaughnessy, Jones Walker, LLPMr. Shaughnessy may be contacted at
bshaughnessy@joneswalker.com
The Ghosts of Baha Mar: How a $3.5 Billion Paradise Went Bust
January 06, 2016 —
John Lippert & Dawn McCarty – BloombergBeyond the tropical waters, across palm-fringed sands and behind locked gates, looms Baha Mar -- the largest and, at $3.5 billion, priciest resort in the Caribbean.
Here, no one frolics pool-side, pina colada in hand, or hits irons on the Jack Nicklaus golf course. No slot machines jingle-jangle in the casino. The Flamingo Bar, the Brasserie des Arts and the Cartier boutique lie dark. On this bright October morning in the Bahamas, all 2,200 guest rooms are empty.
The quiet is almost spooky here on the outskirts of Nassau, where the waterscape frills of nearby Paradise Island give way to the vast ghost-resort that is Baha Mar.
Just how the place ended up like this -- in a bankruptcy so colossal that it’s jeopardizing the Bahamas’s credit rating -- is the biggest business story to hit this Caribbean nation for as long as anyone here can remember. It stretches far beyond the white beaches and across time zones, to none other than the State Council of China.
Reprinted courtesy of
John Lippert, Bloomberg and
Dawn McCarty, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Unqualified Threat to Picket a Neutral is Unfair Labor Practice
January 08, 2019 —
Wally Zimolong - Supplemental ConditionsOn December 27, 2018, the National Labor Relations Board enforced a decades old policy that a union’s unqualified threat to picket a neutral employer at a “common situs” a/k/a a construction site is a violation of the National Labor Relations Act.
Background
The case involved area standards picketing by the IBEW of a project owned by the Las Vegas Convention and Visitors Authority (LVCVA). The IBEW sent a letter to various affiliated unions who were working on the project advising them of its intent to engage in area standards picketing at the project directed to the merit shop electrical subcontractor performing work there. The IBEW also sent a copy of the letter to the LVCVA.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
EPA Seeks Comment on Clean Water Act Section 401 Certification Rule
July 19, 2021 —
Karen Bennett - Lewis BrisboisThe Environmental Protection Agency (EPA) announced that it will revise a 2020 final rule clarifying requirements for water quality certification under the Clean Water Act (CWA). 85 Fed. Reg. 42210 (June 2, 2021). CWA Section 401 requires states and tribes to certify that any discharges associated with a federal permit will comply with applicable state or tribal water quality requirements.
In an effort to eliminate 401 certification being used as a tool for delaying or imposing conditions unrelated to protecting water quality on federal permits, the 2020 rule established limits on the scope and timeline for review and required any conditions on certification to be water-quality related. State and Tribal governments and environmental groups challenged the rule, arguing it constrained state and tribal decision-making authority by limiting the term “other appropriate requirements of State law” in CWA Section 401(d) to “water quality requirements” and “point source discharges.”
With EPA’s decision to revise the rule, many believe these same scope and timing limitations will be targets for change. Clients with experience, positive or negative, under the 2020 rule should consider submitting comments by the August 2, 2021 deadline.
Read the court decisionRead the full story...Reprinted courtesy of
Karen Bennett, Lewis BrisboisMs. Bennett may be contacted at
Karen.Bennett@lewisbrisbois.com