Homeowner’s Policy Excludes Coverage for Loss Caused by Chinese Drywall
November 18, 2011 —
Tred R. Eyerly - Insurance Law HawaiiExclusions barred the homeowners from recovering for losses caused by Chinese drywall in their home. Ross v. C. Adams Const. & Design, L.L.C., 2011 La. App. LEXIS 769 (La. Ct. App., released for publication Oct. 5, 2011).
Two years after purchasing their home, the Rosses began experiencing chronic malfunctions in the heating, ventilation and air conditioning system. After discovering the presence of gypsum drywall, or "Chinese drywall", they submitted a claim to their insurer, Louisiana Citizens Property Insurance Company, for damages caused by the Chinese drywall. Louisiana Citizens denied the claim.
The Rosses sued. The trial court granted summary judgment to Louisiana Citizens based upon exclusions in the policy.
On appeal, the appellate court first agreed the Rosses had sustained a direct physical loss. The inherent qualities of the Chinese drywall created a physical loss to the home and the drywall had to be removed and replaced.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Subcontractor Not Estopped from Enforcing Lien Not Listed In Bankruptcy Petition
March 01, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPIn Stock Building Supply, Inc. v. Platte River Insurance Co.,[1] the Court of Appeals dealt with issues of judicial estoppel, bankruptcy, retroactive application of statutory lien amendments, and the full payment defense.
The owner, Madison Retail-Suwanee, LLC (“Madison”) hired Cannon/Estapa General Contractors, Inc. (“Cannon”) to be the general contractor for the construction of a shopping center (“the Project”). Cannon subcontracted with Stock Building Supply (“Stock”) to supply labor, materials, and services for the Project. Cannon failed to complete the project and Madison had yet to pay Cannon the full contract price. In 2007, Stock timely filed a lien on the Project and obtained a judgment against Cannon for the amount due under the subcontract. Platte River Insurance Company (“Platte”), the surety, issued a bond to discharge Stock’s lien. Consequently, Stock pursued an action against Platte to collect the judgment in the amount of $93,865.27.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Pancakes Decision Survives Challenge Before Hawaii Appellate Court
March 12, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn 1997, the Hawaii Intermediate Court of Appeals (ICA) decided Pancakes of Hawaii, Inc. v. Pomare Prop. Corp., 85 Haw. 286, 944 P.2d 83 (Haw. Ct. App. 1997). Although not an insurance coverage case, Pancakes addressed the duty to defend in terms of a contractual indemnity obligation. Under challenge in a recent appeal before the ICA, the Court reaffirmed the holding in Pancakes. Arthur v. State of Hawaii, Dept. of Hawaiian Home Lands, 2015 Haw. App. LEXIS 109 (Haw. Ct. App. Feb. 27, 2015).
The decision is long with detailed facts complicated and many indemnities running in favor of various parties. This post focuses on the decision's discussion of Pancakes.
A resident, Mona Arthur, of the Kalawahine Streamside Housing Development, was killed when she apparently slipped and fell from a hillside adjacent to the project. She was on the hillside tending to her garden there. At the bottom of the hill was a two foot fence in front of a drainage ditch, where Mona allegedly hit her head.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Navigating Construction Contracts in the Energy Sector – Insights from Sheppard Mullin’s Webinar Series
October 01, 2024 —
Cesar Pereira - Sheppard MullinConstruction contracts in the energy sector involve unique challenges and risks, particularly with respect to bonds and mechanic’s liens.
Understanding how to navigate these challenges is key to protecting your projects from disputes with general contractors, subcontractors and suppliers.
In our recent webinar, “
Construction Contracts: Bond and Mechanic’s Lien Primer for Energy Projects,” I was joined by my Sheppard Mullin colleagues Chris Kolosov and Emily Anderson to discuss navigating common contract pitfalls and negotiation strategies to protect your interests.
Here are our key takeaways.
- Know Local Mechanic’s Lien Laws: Mechanic’s liens are statutory and vary significantly from state to state. It is critical to understand the local laws and regulations at play in your project’s jurisdiction.
Read the court decisionRead the full story...Reprinted courtesy of
Cesar Pereira, Sheppard MullinMr. Pereira may be contacted at
cpereira@sheppardmullin.com
Waiver of Consequential Damages: The Most Important Provision in a Construction Contract
March 08, 2021 —
Jeremy P. Brummond - Construction ExecutiveConstruction agreements can be lengthy. They often include terms covering everything from logistics for working on the project site to complicated provisions regarding intellectual property. Many provisions in a construction agreement deal with risk and who is going to pay for damage claims if or when they occur.
However, not all risk-shifting provisions are equally important. While provisions that impose obligations on the contractor to maintain confidentiality, indemnify for personal injury or property damage, or correct defective work can expose a contractor to substantial damage claims and are thus important, contractors can significantly control the amount of damages the owner can claim by including a well-drafted waiver of “consequential damages” provision in the agreement.
Because the waiver of consequential damages can significantly control the amount of damages for which a contractor is assuming risk and greatly limit the owner’s ability to recoup many damages, it is arguably the most important provision in a construction contract. Therefore, it is essential for contractors and owners to carefully consider the waiver of consequential damages before entering into any construction agreement.
Reprinted courtesy of
Jeremy P. Brummond, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Brummond may be contacted at
jbrummond@lewisrice.com
FEMA Administrator Slams Failures to Prepare, Evacuate Before Storms
October 23, 2018 —
Christopher Flavelle - BloombergFederal Emergency Management Agency Administrator Brock Long angrily criticized the failure of citizens to heed evacuation warnings and leaders to better prepare for natural disasters such as Hurricane Michael.
"It's frustrating to us because we repeat this same cycle over and over again," Long said during a press briefing Friday at FEMA headquarters in Washington. "If you want to live in these areas, you've got to do it in a more resilient fashion."
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Flavelle, Bloomberg
Supreme Court Addresses Newly Amended Statute of Repose for Construction Claims
June 26, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPWe have been following the protracted legal battle concerning
Southern States Chemical, Inc. v. Tampa Tank & Welding, Inc. This case had been litigated at the Supreme Court and resulted in legislation. In the latest round, the Supreme Court answered whether Georgia’s statute of repose for construction claims applies to claims arising or brought before the statute was amendment in 2020.
What is a Georgia’s statute of repose? Under the statute, “[n]o action to recover damages: (1) For any deficiency in the survey or plat, planning, design, specifications, supervision or observation of construction, or construction of an improvement to real property; (2) For injury to property, real or personal, arising out of any such deficiency; or (3) For injury to the person or for wrongful death arising out of any such deficiency shall be brought against any person performing or furnishing the survey or plat, design, planning, supervision or observation of construction, or construction of such an improvement more than eight years after substantial completion of such an improvement.”
The case began ten years ago when Southern States suited Tampa Tank and Corrosion Control for alleged defects in renovating a 24-foot tall, 130-foot wide storage tank. The tank renovation was completed in 2002, and in 2011, the tank was found to leak sulfuric acid.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Real Estate Developer Convicted in $1.3 Billion Tax Case After Juror Removed
October 17, 2023 —
David Voreacos - BloombergA real estate developer was convicted for promoting $1.3 billion in fraudulent tax deductions after a judge removed a deliberating juror who told the judge she was “standing up for White people.”
Jack Fisher was found guilty Friday in Atlanta federal court of selling tax deductions to wealthy individuals using so-called syndicated conservation easements, which offer tax breaks for the promise to avoid developing land. Prosecutors said Fisher relied on exaggerated appraisals and backdated documents in the scheme, which earned him tens of millions of dollars.
Jurors also convicted a lawyer who worked with Fisher, James Sinnott. Attorneys for Fisher and Sinnott didn’t immediately respond to a request for comment.
The nine-week trial nearly came undone by conflicts over race and class within the jury, which began deliberating on Sept. 14. Last week, jurors told US District Judge Timothy Batten they were “hopelessly hung.” Jurors also complained that Juror 26, a White woman, refused to deliberate.
Read the court decisionRead the full story...Reprinted courtesy of