COVID-19 Damages and Time Recovery: Contract Checklist and Analysis
April 27, 2020 —
Patrick J. Greene, Jr. - Peckar & AbramsonThis Alert explores the contract provisions and related rights that are likely to govern time and compensation adjustments for COVID-19 impacts. As parties begin analyzing such rights, this is intended to serve as a useful guide and checklist.
Analysis of relevant contract provisions should start with careful consideration of the specific impacts that have been experienced and the causes of those impacts. The nature of the impact (delay, extra work, disruption, etc.) and the causes of such impacts (owner direction, government order, etc.) will generally govern the analysis and resulting course of action. Listing or creating a matrix of impacts and their causes may be an effective working tool.
Essentially, there are five primary impacts that will likely require critical analysis under the relevant contract provisions, and notably, more than one impact may be present:
a) complete or partial suspension of work,
b) additional work or requirements,
c) added cost,
d) delay, and
e) disruption.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick J. Greene, Jr., Peckar & AbramsonMr. Greene may be contacted at
pgreene@pecklaw.com
Panel Declares Colorado Construction Defect Laws Reason for Lack of Multifamily Developments
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFDennis Huspeni writing for the Denver Business Journal provided reactions from panelists at a ULI Colorado event on January 9th at the Embassy Suites Denver – Downtown/Convention Center hotel regarding a report on “Emerging Trends in Real Estate.” According to Huspeni’s article, panelists discussed “the lack of for-sale multifamily development and attributed it to Colorado’s construction defect laws.”
John Beeble, chairman and CEO of Saunders Construction, one of the panelists, said that Saunders does not build condos because of Denver’s construction defect laws: “We’ve been in business for 42 years and never been sued for construction defects,” Beeble said, according to the Denver Business Journal. “But the odds are close to 100 percent that we’d be in court defending ourselves if we did condos.”
Jeff Hawks, principal at ARA Colorado, claimed, “Colorado has some of the worst construction defect laws in the country. It’s stupid to try and build a condo development until that changes,” as reported by the Denver Business Journal.
Read the court decisionRead the full story...Reprinted courtesy of
Anti-Concurrent Causation Clause Preserves Possibility of Coverage
January 15, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's anti-concurrent causation clause preserved the possibility of coverage when the insurer's motion for summary judgment to disclaim its indemnity obligation for damage caused by Hurricane Sandy was overturned by the Second Circuit. Madelaine Chocolate Novelties, Inc. v. Great Northern Ins. Co., 2018 U.S. App. LEXIS 29821 (Oct. 23, 2018 2nd Cir. )
In 2012, Madelaine Chocolate suffered significant damage to its business due to storm surges created by Hurricane Sandy. Madelaine Chocolate had an "all-risk" policy issued by Great Northern. Madelaine Chocolate filed a claim for property damage of approximately $40 million and business income loss and extra operation expenses of $13.5 million. Great Northern denied most of the claim, reasoning that the storm surge damage was excluded under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Defect Headaches Can Be Avoided
February 21, 2013 —
CDJ STAFFConstruction defect claims can be an avoidable headache, if builders apply some forethought. Mark J. Peschel of Johnson & Lindberg, a Bloomington, Minnesota law firm, points out that simply says that windows should be weatherproofed by appropriate flashing, without any guidance on accomplishing that. He notes that “builders tend not to know the weatherproofing code provisions as well as they should.” Another lawyer, Eric S. Hayes of Brown and Carlson in St. Louis Park extends this, “it’s not just the building codes that need to be followed, but also the standards in the industry.”
Hayes notes that another way builders can avoid headaches is by being proactive. “I often hear, once things have gone sour and moved toward litigation, that the homeowner contacted the contractor a dozen times about a leaking basement and nothing was done, so they were forced to sue.” His advice for builders: “Don’t let it fester.”
Read the court decisionRead the full story...Reprinted courtesy of
Without Reservations: Fourth Circuit Affirms That Vague Reservation of Rights Waived Insurers’ Coverage Arguments
January 09, 2023 —
Lara Degenhart Cassidy & Matthew J. Revis - Hunton Insurance Recovery BlogThe Fourth Circuit recently affirmed insurance coverage for a South Carolina policyholder based on the “axiomatic principle” that an insurer which fails to fully and fairly articulate its potential coverage defenses in a reservation of rights letter loses the right to contest coverage on those grounds.
Stoneledge at Lake Keowee Owner’s Assoc. v. Cincinnati Ins. Co., No. 19-2009, 2022 WL 17592121 (4th Cir. 2022) (quoting Harleysville Group Insurance v. Heritage Communities, Inc., 803 S.E.2d 288 (S.C. 2017)). More particularly, in Stoneledge, the Fourth Circuit affirmed per curiam a South Carolina District Court’s grant of summary judgment in favor of a homeowners association that had successfully sued its general contractors for construction defects and was seeking to recover the damages owed from the contractors’ insurers. The Fourth Circuit agreed that the insurers’ vague reservation of rights letters failed to reserve the defenses on which the insurers purported to deny coverage.
The question before the court in Stoneledge was whether the two insurers that had each agreed to defend their respective general-contractor insureds in the homeowner association’s underlying litigation had sufficiently informed their policyholders of their coverage positions. Specifically, the court considered whether the insurers provided notice of their intention to challenge coverage on specific bases and explained why those bases applied in their respective reservation of rights letters. Both of the insurers’ letters followed the typical approach of identifying various policy provisions and exclusions and outlining the general mechanics of those provisions, but they fell short of applying the provisions or exclusions to the facts in the case at hand. Further, the letters stated that the insurers would reevaluate how the provisions applied as the underlying case progressed. One of the insurer’s letters expressed doubt as to coverage but did not offer any analysis on the reasons for the prospective coverage denial.
Reprinted courtesy of
Lara Degenhart Cassidy, Hunton Andrews Kurth and
Matthew J. Revis, Hunton Andrews Kurth
Ms. Cassidy may be contacted at lcassidy@HuntonAK.com
Mr. Revis may be contacted at mrevis@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Preserving your Rights to Secure Payment on Construction Projects (with Examples)
March 22, 2017 —
David Adelstein – Florida Construction Legal UpdatesAll participants across the construction industry should understand what efforts they should take to maximize and collateralize payment. No one wants to work for free and, certainly, no one in the construction industry wants to work without ensuring there is some mechanism to recover payment in the event they remain unpaid. Being proactive and knowledgeable can go a long way when it comes to recovering your money.
Your Contract – It starts with the contract. You should understand those risks that are allocated to you and those that are allocated to another party. And, you should understand the contractual mechanism to resolve claims and disputes and whether your contract has a prevailing party attorney’s fees provision. In addition to contractual rights, there are tools for you to maximize your collection efforts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
A Court-Side Seat: Butterflies, Salt Marshes and Methane All Around
November 16, 2020 —
Anthony B. Cavender - Gravel2GavelOur latest summary of some recent developments in the courts and the federal agencies includes a unique case involving salt marshes adjacent to San Francisco Bay.
THE FEDERAL COURTS
A Wolf Among the Butterflies
On October 13, 2020, the U.S. Court of Appeals for the District of Columbia Circuit decided the case of North American Butterfly Association v. Chad Wolf, Acting Secretary of the Department of Homeland Security. The National Butterfly Center is a 100-acre wildlife sanctuary located in Texas along the border between the United States and Mexico, and in 2017, the DHS exerted control over a segment of the sanctuary to construct facilities to impede unauthorized entry into the United States. It was alleged that the government failed to provide advance notice to the sanctuary before it entered the sanctuary to build its facilities. The Association filed a lawsuit to halt these actions for several reasons, including constitutional claims and two federal environmental laws (NEPA and the Endangered Species Act), but the lower court dismissed the lawsuit because of the provisions of the Illegal Immigration Reform and Immigrant Responsibility Act of 1996 (IIRIRA). That law forecloses the applicability of these laws if the Secretary of DHS issues appropriate declaration. On appeal, the DC Circuit held, in a 2 to 1 decision, that the lawsuit should not have been dismissed. The plaintiffs had standing to file this lawsuit, but the jurisdiction stripping provisions of the IIRIRA, when invoked, required that the statutory claims be dismissed as well as a constitutional Fourth Amendment search and seizure claim. However, the plaintiff’s Fifth Amendment claim that the government’s actions violated their right to procedural due process must be reviewed. The Center was given no notice of the government’s claims and no opportunity to be heard before these actions were taken. The dissenting judge argued that the court was being asked to review a non-final decision, which it should not do.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Traub Lieberman Attorneys Recognized as 2024 New York – Metro Super Lawyers®
November 11, 2024 —
Traub LiebermanTraub Lieberman is pleased to announce that seven Partners from the Hawthorne, NY office have been selected to the 2024 New York - Metro Super Lawyers list.
2024 New York – Metro Super Lawyers
- Copernicus Gaza – Insurance Coverage
- Jonathan Harwood – Professional Liability
- Lisa Rolle – Construction Litigation
- Hillary Raimondi – Employment Litigation
- Christopher Russo – Professional Liability
- Lisa Shrewsberry – Professional Liability
- Stephen Straus – Insurance Coverage
Lisa Shrewsberry was also selected to the Top 25: 2024 Westchester County Super Lawyers® list.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman