Hurdles with Triggering a Subcontractor Performance Bond
April 05, 2017 —
David Adelstein – Florida Construction Legal UpdatesThere have been a couple of decisions as of late, particularly in federal court, that have gone in favor of a performance bond surety and against a general contractor’s claim against a subcontractor’s performance bond. These decisions have been so unfavorable that they may be swaying certain internal decisions to move to subcontractor default insurance with, perhaps, subcontractors that pose less risk. From the general contractor’s perspective, if they have to stop the management of the job and progress to jump through hoops to trigger the performance bond’s obligations, rightfully or wrongfully, the bond may not provide them the value they need. Performance bonds are an appropriate product in many instances, but there should be more consistency regarding the actual trigger of a subcontractor’s performance bond obligations. Project teams need to absolutely understand what efforts they need to take, and how they need to take such efforts, in order to properly trigger a performance bond’s obligations. This is a must (and I have presented many seminars on this very issue). Or, the general contractor should move away from the traditional AIA /standard performance bond form, which is the direction I always go when I am involved in the drafting of a performance bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
State of Texas’ Claims Time Barred by 1982 Nuclear Waste Policy Act
June 13, 2018 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law Blog On June 1, the U.S. Court of Appeals for the Fifth Circuit decided the case of State of Texas v. U.S., et al. The Court of Appeals held that the petition for mandamus filed by the State of Texas essentially seeking to compel the Nuclear Regulatory Commission (NRC) to establish a schedule for the operation of the Yucca Mountain, NV nuclear waste depository was untimely filed. The depository is very controversial in Nevada, and as a consequence, none of the many deadlines established by Congress have been met.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, Pillsbury Winthrop Shaw Pittman LLPMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
New York Appellate Court Expands Policyholders’ Ability to Plead and Seek Consequential Damages
February 27, 2019 —
Michael S. Levine & Joshua S. Paster - Hunton Andrews KurthIn a huge win for policyholders, a New York appellate court, in D.K. Property, Inc. v National Union Fire Insurance Company of Pittsburgh, Pa., held that an insured need not provide a detailed factual description or explanation for why consequential damages are recoverable at the pleading stage. Rather, an insured’s complaint must only (i) specify the types of consequential damages claimed; and (ii) allege that those damages reasonably were contemplated by the parties prior to contracting.
Here, D.K. Property’s building was damaged as a result of construction on an adjoining building, and it timely filed a claim with National Union under a policy that covers “direct physical loss or damage to” the building. National Union neither paid the claim nor disclaimed coverage. Instead, according to D.K. Property, National Union made unreasonable and increasingly burdensome information demands over a three-year period, which it alleges was a “tactic” to make pursuing the claim so expensive that D.K. Property would abandon the claim. As a result of the delay, D.K. Property alleges the structural damage to its building has worsened.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joshua S. Paster, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Paster may be contacted at jpaster@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Non-compliance With Endorsement Means No Indemnity Coverage
January 15, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's failure to verify that subcontractors had CGL policies and to provide a contract stating that the subcontractors would indemnify the insured as required by the policy's endorsement meant there was no coverage for the insured. Cincinnati Spec. Underwriters Ins. Co. v. Milionis Constr., Inc., 2018 U.S. Dist. LEXIS 199658 (E.D. Wash. Nov. 26, 2018).
The homeowners filed suit against Milionis, the general contractor for construction of a home. The underlying suit alleged that Milionis breached the parties' agreement by leaving the home unfinished. Cincinnati defended Milionis under a reservation of rights.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Courts Take Another Swipe at the Implied Warranty of the Plans and Specifications
December 15, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCImplied warranties are warranties created by law, legislation, or courts. In the construction industry, one of the most prominent implied warranties is that owners who provide plans and specifications to their contractors impliedly warrant the adequacy of their plans and specifications.[i] That implied warranty had its beginning in the 1918 US Supreme Court decision of U.S. v. Spearin[ii] and is, therefore, popularly known as the Spearin Doctrine. Under the Spearin Doctrine, if the contractor completes the work in accordance with the owner’s plans and specifications, but there is a deficiency or failure, the owner, not the contractor, is responsible. When the owner breaches its implied warranty, in most instances, the contractor is entitled to additional compensation for extra work performed, delays experienced, and other additional expense or loss occasioned by the warranty breach. A recent case demonstrates that this implied warranty is not “immunity.” The contractor must still act reasonably and diligently, particularly when the contract provisions so require.
In the recent Fifth Circuit case of Dallas/Ft. Worth International Airport v. INet Airport Systems,[iii] the court, despite the implied warranty that existed, did not grant the contractor summary judgment on claims involving admitted plan deficiencies, since factual issues existed regarding the contractor’s cooperation and participation in the solution to the defects.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman, PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
EPA Announces Decision to Retain Current Position on RCRA Regulation of Oil and Gas Production Wastes
June 03, 2019 —
Anthony B. Cavender - Gravel2GavelAfter much study, EPA has decided against changing its current RCRA Subtitle D rules affecting the state regulation of oil and gas exploration & production waste. Since 1988, EPA has determined that most such wastes should be regulated as only non-hazardous wastes subject to RCRA Subtitle D, and not the more onerous hazardous waste provisions of RCRA Subtitle C. (See the Regulatory Determination of Oil and Gas and Geothermal Exploration, Development and Production Wastes, 53 FR 25,446 (July 6,1988).)
As a result, under the Subtitle D rules, the primary regulators of such waste are state regulatory agencies, which follow the state plan non-hazardous waste guidelines developed by EPA. This regulatory disposition has proven to be fairly controversial, and it was recently challenged in a lawsuit filed in the U.S. District Court for the District of Columbia: Environmental Integrity Project, et al. v. McCarthy. To settle this lawsuit, EPA and the plaintiffs entered into a consent decree by which EPA was to make certain determinations about the future of the program after conducting an appropriate study. That study, Management of Exploration, Development and Production Wastes: Factors Informing a Decision on the Need for Regulatory Action, has been completed, and it concludes, after a fairly comprehensive review of these state regulatory programs, that “revisions to the federal regulations for the management of E&P wastes under Subtitle D of RCRA (40 CFR Part 257) are not necessary at this time.” In a statement released on April 23, 2019, EPA accepted these findings and promised that it would continue to work with states and other stakeholders to identify areas for improvement and to address emerging issues to ensure that exploration, development and production wastes “continue to be managed in a manner that is protective of human health and the environment.”
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Texas Allows Wide Scope for Certificate of Merit
January 07, 2025 —
Lian Skaf - The Subrogation StrategistThe purpose of certificate of merit (sometimes referred to as affidavit of merit) statutes is to identify frivolous claims before the court wastes time and resources during litigation. More common in medical malpractice cases, several states have enacted similar requirements for professional negligence claims dealing with construction-related issues. While a subrogation attorney should not be bringing a frivolous case to suit anyway, the requirement adds another step in the process that plaintiffs need to properly navigate.
Chapter 150 of the Texas Civil Practice and Remedies Code requires that in an action arising out of professional services by a licensed or registered professional, claimants must file an affidavit from a qualified expert attesting to the theories of recovery, the negligence and the factual basis for the claims. The expert must be competent, have the same professional license or registration as the defendant and practice in the area of practice of the defendant.
In Janis Smith Consulting, LLC v. Rosenberg, No. 03-23-00370-CV, 2024 Tex. App. LEXIS 7961, the Court of Appeals of Texas, Third District (Court of Appeals) addressed a challenge from the defendant as to the sufficiency of the plaintiff’s certificate of merit in an interlocutory appeal. The Court of Appeals affirmed the lower court’s dismissal of the defendant’s motion to dismiss based on the allegedly improper certificate of merit, holding that the plaintiff’s expert was sufficiently qualified to certify the legitimacy of the case.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
New Iowa Law Revises Construction Defects Statute of Repose
September 07, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.Starting July 1st of this year, Iowa homeowners now have only ten years to file a claim against the builder instead of the fifteen years that was allowed previously, reported WZAD 8 News. Furthermore, commercial property owners will only have eight years to file their suits.
Scott Webster, Vice President of the Quad Cities Builders and Re-modelers Association, told WZAD 8 News that insurance companies played a part in the change: “[I]nsurance companies were saying, Iowa is at such a long period of time for any kind of defect, that may be hard to prove whether the builder even did it or the homeowner modified the house.”
However, Tom Miller, Iowa Attorney General, disagreed with the change in policy: “We think that it’s unfair to consumers, the defects in buildings and commercial buildings too, can show up very easily between eight and fifteen years out.”
Read the court decisionRead the full story...Reprinted courtesy of