Pre-Judgment Interest Not Awarded Under Flood Policy
January 17, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss state law and extracontractual claims, including pre-judgment interest. Hurley v. Wright Nat'l Flood Ins. Co., 2022 U.S. Distl. LEXIS 203803 (W.D. La. Nov. 8, 2022).
The insured suffered damage from Hurricane Delta. He filed suit, alleging that Wright National Flood Insurance Company breached the Standard Flood Insurance Policy (SFIP). The insured sought damages for state law claims for bad faith, diminution in value, actual repair costs, attorney's fees , litigation costs, and interest. Wright moved to dismiss the extracontractual state law causes of action for bad faith and various claims for damages, other than the damages sought for the alleged breach of the SFIP.
The court explained that the Write-Your-Own (WYO) Program carriers issuing flood insurance under the National Flood Insurance Program (NFIP) arranged for the adjustment, settlement, payment, and defense of all claims arising from the policy. Congress underwrote all operations of the NIFP, including claims adjustment, through United States Treasury funds. A judgment against a WYO Program carrier constituted a judgment against FEMA, and consequently, a direct charge on the United States Treasury.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Another Reason to Love Construction Mediation (Read: Why Mediation Works)
December 02, 2015 —
Christopher G. Hill – Construction Law MusingsI’ll bet you’re thinking by now that I have beaten the mediation drum to death and that I wouldn’t have any more praise for the process than I have heaped upon it here at this corner of the construction law “blawgosphere.” Well, just about every time I am involved with the process, whether acting in my capacity as a Virginia Supreme Court certified mediator, or as counsel to a client seeking to resolve a matter and move on with the business of making money, I become more convinced that mediation can work in even the most contentious of situations.
What do I mean by “work?” The obvious answer is that mediation “works” when the parties come up with a solution to their problem. In most instances, the solution involves money changing hands. After all, it is money that is usually the tangible and outwardly driving force behind a dispute. Money is also what a court or arbitrator (in most cases) will be awarding to one side or the other at the end of what is likely to be an expensive process.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Spearin Doctrine 100 Years Old and Still Thriving in the Design-Build Delivery World
January 09, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe Supreme Court’s ruling in United States v. Spearin, [1] also referred to as the Spearin doctrine, is a landmark construction decision.[2] The Spearin doctrine provides that the Owner impliedly warrants the information, plans and specifications which an Owner provides to a General Contractor. If a Contractor is bound to build according to plans and specifications prepared by the Owner, the Contractor will not be responsible for the consequences of defects in the plans and specifications.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
If You Can’t Dazzle Em’ With Brilliance, Baffle Em’ With BS: Apprentices on Public Works Projects
October 24, 2023 —
Garret Murai - California Construction Law BlogThe “Big Four” when it comes to public works contracting on state and local projects in California are:
- Registration with the California Department of Industrial Relations (“DIR”);
- Payment of prevailing of wages and maintenance and submission of certified payroll;
- Compliance with the “skilled and trained workforce” requirements on certain projects; and
- Hiring apprentices on state and local public works projects with a value of $30,000 or more.
The next case,
GRFCO, Inc. v. Superior Court, 89 Cal.App.5th 1295 (2023), discusses the last of these requirements. The case also reminded me of W.C. Field’s old saying – “If you can’t dazzle em’ with brilliance, baffle em’ with bullshit” – and which ended with expected results.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Nobody Knows What Lies Beneath New York City
August 10, 2017 —
Greg Milner - BloombergBefore a single raindrop fell, Alan Leidner knew the waters could rise and throw the city into darkness. On this point, the maps were as clear as a crystal ball. All you had to do was look.
It was 2010, and Leidner was consulting for the government services company Booz Allen Hamilton Inc., contracted by the U.S. Department of Homeland Security to identify potential threats and vulnerabilities in the nation’s critical infrastructure. Leidner was examining a region that included New York and New Jersey. One day he was thinking about the area’s electrical power grid. He consulted some flood projection maps the Federal Emergency Management Agency had prepared. Then he stared at a map of the grid maintained by Consolidated Edison Inc., the region’s power supplier. And it just jumped out at him: The substation at East 13th Street, on the banks of the East River, was smack in the middle of a flood zone.
Leidner voiced his concerns with utilities, hospitals, and other major facilities. “The reaction was mostly, ‘Eh,’ ” he recalls, as we sit in the Tribeca offices of the Fund for the City of New York, where he directs the nonprofit organization’s Center for Geospatial Innovation.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Milner, Bloomberg
Another Reminder to ALWAYS Show up for Court
July 20, 2020 —
Christopher G. Hill - Construction Law MusingsI have discussed the need to always respond to a lawsuit on multiple occasions here at Construction Law Musings. However, I keep reading cases where the defendant fails to appear either by pleading or in person. Such action is never a good idea as demonstrated once again in the case of Balfour Beatty Infrastructure, Inc. v. Precision Constr. & Mgmt. Group, LLC, a case out of the Eastern District of Virginia.
The basic facts are not a surprise and are taken from the magistrates report that was adopted by the District Court. Balfour Beatty and Precision entered into a subcontract for some electrical work at a project located in Loudoun County. The subcontract included an attorney fees provision and provided for liquidated damages for late performance and the typical damages for default. The project began in July of 2016 with substantial completion July 5, 2018. Precision failed to supply sufficient manpower and sent a letter to Precision stating the same. After an agreement between the parties regarding supplementation by Balfour Beatty and to the accompanying back charge, Balfour Beatty informed Precision by letter that it would be liable for any liquidated damages. The Owner began assessing liquidated damages and Balfour Beatty subsequently terminated the subcontract and discovered defective work by Precision.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
JAMS Announces Updated Construction Rules
June 21, 2021 —
JAMSIrvine, Calif. – JAMS, the largest private provider of
alternative dispute resolution (ADR) services worldwide, is pleased to announce it has revised and updated its
Construction Arbitration Rules & Procedures and
Expedited Construction Arbitration Rules & Procedures, effective June 1. These Rules were updated to reflect the latest developments and trends in
construction arbitration.
In response to the transition to virtual and hybrid proceedings, Rule 22 makes explicit the arbitrator’s full authority to conduct the hearing in person, virtually or in a combined form, as well as with participants in more than one geographic location. To support access to case documents throughout the proceedings, Rule 8 aligns electronic filing and service with the functionality of JAMS Access, a centralized, secure online case management platform.
Additional rules were created or revised to clarify and strengthen the authority of the arbitrator. Key changes include allowing an arbitrator to withhold approval of any intended change in party representation that could compromise the proceedings or the final award, to set a hearing without consulting a party that he or she reasonably believes will not participate and to permit a party to file a motion for summary disposition of a claim if the arbitrator believes that party has demonstrated the motion is likely to succeed.
About JAMS – Local Solutions. Global Reach.
Founded in 1979, JAMS is the largest private provider of alternative dispute resolution services worldwide. JAMS successfully resolves and manages business and legal disputes by providing efficient, cost-effective and impartial ways to overcome barriers at any stage of conflict. JAMS offers customized in-person, virtual and hybrid resolution services locally and globally through a combination of industry-specific experience, first-class client service, the latest technology and highly trained mediators and arbitrators.
Read the court decisionRead the full story...Reprinted courtesy of
JAMS
Hydrogen Powers Its Way from Proof of Concept to Reality in Real Estate
May 10, 2021 —
Victoria Judd, Sidney L. Fowler & Robert G. Howard - Gravel2Gavel Construction & Real Estate Law BlogHydrogen is the new buzzword in every industry, and real estate is no exception. Hydrogen does not emit carbon dioxide when burnt and could therefore help reduce the climate impact of buildings, which in aggregate represent one of the biggest emitters of greenhouse gases after industry and surface transport. To the extent that hydrogen is to become an important power source globally, it will need to enter the domestic power market. The first step appears to be the development of pilot villages.
In the UK, there are several hydrogen trials in uninhabited properties or in closed private networks. There are some uninhabited houses on a Royal Air Force base in Cumbria that are exclusively heated with hydrogen and also a private gas network at Keele University which uses 20 percent hydrogen blended with natural gas. In addition, there is a small village near Newcastle that is being used as a test case: for a period of 10 months starting in spring 2021, up to 20 percent hydrogen will be blended into the natural gas network so that more than 650 homes can be partially heated by hydrogen. It is expected that a small number of additional villages will be able to heat their homes with 100 percent hydrogen as soon as 2022, with a scale up to have a hydrogen town by 2030.
Reprinted courtesy of
Victoria Judd, Pillsbury,
Sidney L. Fowler, Pillsbury and
Robert G. Howard, Pillsbury
Ms. Judd may be contacted at victoria.judd@pillsburylaw.com
Mr. Fowler may be contacted at sidney.fowler@pillsburylaw.com
Mr. Howard may be contacted at robert.howard@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of