More (and Simpler) Options Under New Oregon Retention Law
October 21, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCSimilar to the changes made by the Washington Legislature last year, the Oregon Legislature recently changed its retention law. Oregon public works agencies and large commercial project owners are now required to accept surety bonds in lieu of withholding retainage on construction projects. There is also no longer a requirement to deposit retention funds in an interest-bearing escrow account.
The owner or public agency must accept the bond in lieu of retainage unless specific grounds exist. For example, public agencies must find there is “good cause” for rejection of the bond based on the “unique project circumstances. Private owners have less discretion to reject a bond and if the bond meets the statutory requirements, per ORS 701.435(1)(a) “the owner and lender shall accept” the bond “in lieu of all or any portion of the retainage…”
Courts have not analyzed when “good cause” exists for public agencies to reject bonds or exactly what will allow a private owner to reject a bond. However, an agency or owner cannot have a general policy to reject retention bonds. The statute does not provide next steps if the contractor disagrees with a decision to reject the bond. It may be necessary to proceed under the contract’s dispute resolution procedure or it may be more appropriate to take the issue directly to the courts.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com
COVID-19 Business Interruption Claims Four Years Later: What Have We Learned?
September 23, 2024 —
Patrick McKnight - The Dispute ResolverFour and half years ago the COVID-19 pandemic spread around the globe, bringing with it interesting, but challenging, legal problems for construction attorneys. Construction projects ground to a halt. Ever-changing guidance from authorities ranging from the U.S. Department of Labor to local health authorities resulted in a web of evolving obligations for general contractors and subs alike. One of the most closely watched legal questions was the wave of business interruption claims filed by plaintiffs, many of whom owned businesses impacted by government shutdowns. During the opening months of the pandemic, I
noted that hundreds of business interruption claims had been filed by insureds across the country. At that time, the only thing certain was that although the outcome remained unknown, virus exclusions were likely to become more likely in the future. Needless to say, much has happened since early 2020.
What does the data say about the outcome of business interruption claims?
In sum, plaintiffs have had an uphill battle. A helpful resource for analyzing the outcome of business interruption suits is the
Covid Coverage Litigation Tracker (“Tracker”), an insurance law analytics tool offered by Penn Carey Law of the University of Pennsylvania. According to its website, “[t]he Covid Coverage Litigation Tracker is a multi-sourced database and dashboard through which to view the unfolding insurance litigation arising out of the pandemic in federal and state courts. Widely cited in briefs, judicial opinions, and the press, the tracker also serves as a proof of concept for new methods to identify, track, and understand emerging case congregations in real time.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Coverage Denied for Faulty Blasting and Improper Fill
October 08, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found coverage was properly denied based on the subcontractor's failure to follow contract specifications in blasting at the job site. Westfield Ins. Co. v. Carpenter Reclamation, Inc., 2014 U.S. Dist. LEXIS 130752 (S.D. W. Va. Sept. 18, 2014).
Carpenter was hired by the Board of Education (BOE) to perform preliminary site clearing, demolition, rock excavation, and establishment of sub-grade for a building. Carpenter was to excavate to 3.5 feet below the floor subgrade so that plumbing and other utilities could be installed.
Carpenter, however, blasted to depths deeper than required, including some areas that were up to nine feet. The BOE sued, alleging over-blasting and having to pay the cost of remediating the problem, along with breach of contract issues.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Defect Suit Can Continue Against Plumber
June 28, 2013 —
CDJ STAFFThe Kansas Court of Appeals has reversed a district court ruling that a homeowner’s suit against a plumber was barred under the economic loss doctrine. However, subsequently the Kansas Supreme Court “refused to extend the economic loss doctrine to homeowner claims against construction contractors.” In light of this, the appeals court sent the case back to the lower court.
The case, Coker v. Siler, was brought by Gregory Coker, who had bought a home from J.M.C. Construction. JMC purchased an unfinished house from Michael D. Siler in August 2006. As part of the completion process, John M. Chaney, the president of JMC, installed the water line into the residence. Mr. Coker bought the home in September 2007.
Starting in April 2008, Mr. Coker noticed that his water bills had increased. Mr. Coker could find “no evidence of a leak above the ground,” so he contacted JMC Construction. Mr. Chaney had R.D. Johnson Excavation dig up the water line, after which a gap was discovered that had been allowing water to flow under the foundation. In addition to the higher water bills, an engineer determined that the water “resulted in cracks in the wall and uneven doors.”
Mr. Coker sued, Siler, J.M.C. and Chaney for negligence, breach of implied warranty, strict liability, and breach of express warranty. J.M.C. and Chaney requested a summary judgment. The court dismissed Mr. Coker’s claims of negligence, strict liability, and breach of implied warranty on the basis of the economic loss doctrine, rejecting a petition from Mr. Coker to reconsider. The court, however, allowed Mr. Cocker to proceed with his claim of express warranty. In December, 2011, Mr. Coker accepted an offer from J.M.C. of $40,000.
Mr. Coker then appealed the summary judgment, making the claim that while the court’s decision was based on Prendiville v. Contemporary Homes, Inc., this has now been overruled by David v. Hett. In this case, “the court ultimately found the rationale supporting the economic loss doctrine failed to justify a departure from a long time of cases in Kansas that establish a homeowner’s right to assert claims against residential contractors.” The appeals court concluded that “although the district court properly relied on the law as it existed at the time of its ruling, the intervening change in the law necessarily renders the conclusion reached by the district court erroneous as a matter of law.”
In sending this case back to the district court, the appeals court noted that the lower court will need to determine if the “defendant accused of negligence did not have a duty to act in a certain manner towards the plaintiff,” in which case “summary judgment is proper. Mr. Coker claims that Mr. Chaney did indeed have this duty.
Further, Mr. Coker claimed that Mr. Chaney had a duty arising out of implied warranty. The appeals court questioned whether the district court properly applied the economic loss doctrine to this claim, because despite being president of the construction company, Mr. Chaney “in his individual capacity as a plumber performing work for Coker, was not a party to the J.M.C. contract.” The court found that “Coker’s claim that Chaney breached an implied duty within such a contract fails as a matter of law.”
However, the court did uphold Cocker’s claim of a contractor liability for injury to a third party, noting that “Chaney owed Coker a legal duty independent of Coker’s contact with J.M.C.” The appeals court left it to the district court to determine if the defect that caused the damage was present when the house left J.M.C.’s possession.
The case was reversed and remanded “with directions to reinstate Coker’s claim of negligence against Chaney in his individual capacity as a plumber.”
Read the court decisionRead the full story...Reprinted courtesy of
Privette: The “Affirmative Contribution” Exception, How Far Does It Go?
August 10, 2020 —
Courtney Arbucci, Peter A. Dubrawski & Austin F. Smith - Haight Brown & BonesteelIn Horne v. Ahern Rentals, Inc. (No. B299605, filed 6/10/2020 ord. publ. 6/10/2020), Plaintiffs filed a wrongful death action against Defendant Ahern Rentals, Inc. (“Ahern”) arising out of the fatal incident involving Ruben Dickerson (“decedent”), while employed by independent contractor 24-Hour Tire Service, Inc. Decedent was ultimately crushed on Ahern Rentals, Inc.’s property when a forklift that was improperly placed on uneven ground collapsed as decedent laid under the raised forklift as he performed tire maintenance.
Plaintiffs’ suit would normally be barred by the Privette line of decisions which arise out of the foundational principle that an independent contractor’s hirer presumptively delegates to the contractor its tort law duty to provide a safe workplace for the contractor’s employees. (Privette v. Superior Court (1993) 5 Cal.4th 689 (Privette).) The Privette rule is subject to a number of exceptions including the “peculiar risk” exception, the “nondelegable duty” exception and the “affirmative contribution” exception. (See Privette, supra.) Here, Plaintiffs’ claimed that their suit against Ahern arose out of the “affirmative contribution” exception to Privette as defined by Hooker v. Department of Transportation (2002) 27 Cal.4th 198, 202 (Hooker). Hooker allows suits otherwise barred by Privette to go forward if the hirer of the independent contractor “exercised control over safety conditions at the worksite in a way that affirmatively contributed to the employee’s injuries.”
Reprinted courtesy of Haight Brown & Bonesteel attorneys
Courtney Arbucci,
Peter A. Dubrawski and
Austin F. Smith
Ms. Arbucci may be contacted at carbucci@hbblaw.com
Mr. Dubrawski may be contacted at pdubrawski@hbblaw.com
Mr. Smith may be contacted at asmith@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
MBS’s $500 Billion Desert Dream Just Keeps Getting Weirder
August 29, 2022 —
Vivian Nereim - BloombergOne day last September, a curious email arrived in Chris Hables Gray’s inbox. An author and self-described anarchist, feminist, and revolutionary, Gray fits right into Santa Cruz, Calif., where he lives. He’s written extensively about genetic engineering and the inevitable rise of cyborgs, attending protests in between for causes such as Black Lives Matter.
While Gray had taken some consulting gigs over the years, he’d never received an offer like this one. The first shock was the money: significantly more than he’d earned from all but one of his books. The second was the task: researching the aesthetics of seminal works of science fiction such as Blade Runner. The biggest surprise, however, was the ultimate client: Mohammed bin Salman, the 36-year-old crown prince of Saudi Arabia.
MBS, as he’s known abroad, was in the early stages of one of the largest and most difficult construction projects in history, which involves turning an expanse of desert the size of Belgium into a high-tech city-region called Neom. Starting with a budget of $500 billion, MBS bills Neom as a showpiece that will transform Saudi Arabia’s economy and serve as a testbed for technologies that could revolutionize daily life. And as Gray’s proposed assignment suggested, the crown prince’s vision bears little resemblance to the cities of today. Intrigued, Gray took the job. “If I can be honest with how I see the world, I’ll pretty much put my work out to anyone,” he says.
Read the court decisionRead the full story...Reprinted courtesy of
Vivian Nereim, Bloomberg
Virginia Chinese Drywall “property damage” caused by an “occurrence” and number of “occurrences”
August 04, 2011 —
CDCoverage.comIn Dragas Management Corp. v. Hanover Insurance Co., No. 2:10cv547 (E.D. Va. July 21, 2011), claimant residential home general contractor and developer DMC filed for arbitration against insured drywall supply and install subcontractor Porter-Blaine seeking damages for (1) the replacement of defective Chinese drywall, and (2) the repair of resulting property to other components of the DMC homes and homeowners’ personal property in seventy-four homes. Porter-Blaine’s CGL insurer Citizens and excess insurer Hanover defended Porter-Blaine in the DMC arbitration.
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
Denial of Motion to Dissolve Lis Pendens Does Not Automatically Create Basis for Certiorari Relief
November 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate decision out of Florida’s Sixth District Court of Appeal holds that a trial court’s denial of motion to dissolve a lis pendens does NOT automatically give a basis for a petition for a writ of certiorari. Generalized allegations of “irreparable harm” to support the basis for the petition for writ of certiorari are insufficient. Rather, the party moving for the petition MUST clearly demonstrate the irreparable harm; otherwise, the petition for writ of certiorari will fail.
A lis pendens has legal significance. It is a recorded document that notifies the world that there is a pending lawsuit dealing with the real property at issue. This is important because who wants to buy a piece of property that is subject to litigation – that would be a risky transaction!
In CPPB, LLC v. Taurus Apopka City Center, LLC, 48 Fla.L.Weekly D1837a (Fla. 6th DCA 2023), a dispute arose as to a real estate transaction. The owner sold a parcel to a buyer. The owner also owned three adjacent parcels. As part of the transaction, the buyer agreed to perform certain improvements to all of the parcels including those adjacent parcels owned by the owner. The owner deposited funds in escrow for purposes of its share of the improvements. A payment dispute arose regarding the improvements and the buyer sued the seller. The seller filed a counterclaim to rescind the transaction along with a recorded lis pendens on the parcel purchased by the buyer. The buyer moved to dissolve the lis pendens which the trial court denied. This prompted the appeal – a petition for a write of certiorari based on the trial court’s denial of the motion to dissolve the lis pendens.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com