Warning! Danger Ahead for Public Entities
July 30, 2019 —
Michael J. Baker - Snell & Wilmer Under Construction BlogPublic entities are known to assert False Claims actions “to up the ante” to intimidate and aggressively address contractor construction claims. This strategy in the case of John Ross of Industrial Sheet Metal, Inc. (JRI) V. City of Los Angeles Department of Airports (LAWA), 29 Cal. App. 5th 378 (2018), backfired on the public entity, LAWA, in a big way and should serve as a warning to public entities about expanding claims to include False Claim actions. In this case, LAWA was awarded $1 in contract damages, its California False Claims Act (CFCA) claim was rejected by the jury as were JRI’s claims against LAWA. Despite losing on the substantive contract claims, the trial court found that JRI “prevailed in the action” under the relevant CFCA fee provision, Government Code 12652, subd. (g)(9)(B), regardless of JRI’s failure to prevail in the action as a whole. The California Appellate Court (hereinafter “Court”) affirmed the trial court’s finding.
The CFCA is analogous to the federal False Claims Act (FFCA; 31 U.S.C. 3729 et seq.). Since the CFCA is patterned on similar federal legislation, it was appropriate for the Court to look to precedent construing this similar federal act in interpreting the CFCA provisions. Accordingly, the Court looked at the False Claims Act cases for guidance in upholding the trial court’s decision in its determination that JRI was the “prevailing party” for determining an attorney’s fees award against LAWA.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Baker, Snell & WilmerMr. Baker may be contacted at
mjbaker@swlaw.com
Does Stricter Decertification Mean More “Leedigation?”
August 04, 2015 —
Christopher G. Hill – Construction Law MusingsRecently, my friend and fellow construction attorney/consultant, Chris Cheatham (@chrischeatham) posted the news that USGBC will be more stringent on the de-certification front. This statement relates to the continued energy performance of LEED certified buildings and increases the likelihood that energy performance (as opposed to mere reporting) could lead to de-certification.
I have discussed on several occasions the potential legal risks relating to green building. One of the big potential sources for such litigation (or “leedigation” as coined by Mr. Cheatham) is the possible de-certification of a previously certified building. With this latest statement by USGBC the specter of such de-certification seems even stronger.
Couple this potential with the fact that anyone can challenge the certification of a building at any time and contractors, subcontractors and other construction professionals face potential liability for the performance of a building in ways well beyond their control.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
New ConsensusDocs 242 Design Professional Change Order Form Helps Facilitate Compensation for Changes in Design Services
November 05, 2024 —
Brian Perlberg - ConsensusDocsConsensusDocs is publishing a new ConsensusDocs 242 Change in Services and Compensation, a change order for design services by a design professional. In the design and construction industry, one thing is certain – change. The work scope included in basic design services an architect or engineer provides occurs somewhat regularly. Previously, ConsensusDocs did not have a standard contract document for changing design professionals’ prices. As a result of user feedback, the ConsensusDocs Contract Content Advisory Council (CCAC) drafted this new architect/engineer change order. The CCAC unanimously approved the new contract document and publication is set for October 14, 2024. The document will be available for most ConsensusDocs subscribers. The full, owner, design-professional, and short-form subscription packages will include the document. A subscription package can be purchased through ConsensusDocs here.
The design professional change order helps owners of construction projects keep track of additional services their design professionals perform. The design professional must provide itemized labor breakdowns for each invoice. The new ConsensusDocs 242 has options for compensation to be actual hours at the billing rate or a lump sum. The new contract document form also has a table for the remaining project deliverables and their respective due dates.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Perlberg, ConsensusDocs CoalitionMr. Perlberg may be contacted at
bperlberg@ConsensusDocs.org
New York Instructs Property Carriers to Advise Insureds on Business Interruption Coverage
April 13, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe New York Department of Financial Services (DFS) took the unusual step last week of instructing all property/casualty insurers to provide information on commercial property insurance and details on business interruption coverage in light of the COVID-19 outbreak. The notice is
here.
The notice recognizes that policyholders have urgent questions about the business interruption coverage under their policies. Insurers must explain to policyholders the benefits under their policies and the protections provided in connection with COVID-19.
The explanation to policyholders is to include the following relevant information.
What type of commercial property insurance or otherwise related insurance policy does
the insured hold?
Does the insured's policy provide "business interruption" coverage? If so, provide the
"covered perils" under such policy. Please also indicate whether the policy contains a
requirement for "physical damage or loss" and explain whether contamination related
to a pandemic may constitute "physical damage or loss." Please describe what type of
damage or loss is sufficient for coverage under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
South Carolina Law Clarifies Statue of Repose
July 11, 2011 —
CDJ STAFFA new law in South Carolina, H 3375, fixes a loophole in that state’s statute of repose. State law puts a cap of eight years on construction defects, but the 2008 law that set that limit had a loophole that would allow for construction defect claims to start thirteen years after construction. The law also provides a cap on punitive damages.
The measure was backed by the Carolinas Association of General Contractors. Their spokesperson said that the legislation “increases our state’s ability to be economically competitive and helps protect our members from frivolous lawsuits.”
Read the full story…
Read South Carolina H 3375…
Read the court decisionRead the full story...Reprinted courtesy of
Las Vegas Sphere Lawsuits Roll On in Nevada Courtrooms
October 02, 2023 —
Richard Korman - Engineering News-RecordBig concerts have yet to start at Las Vegas’ distinctive new ball-shaped entertainment venue, but the legal noise over its construction has been heard in Clark County courtrooms for more than two years.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Reverses Summary Judgment Award to Insurer on Hurricane Damage Claim
December 18, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit reversed the district court's grant of summary judgment to the insurer on a property damage claim arising from Hurricane Harvey. Advanced Indicator and Manufacturing, Inc. v. Acadia Ins. Co., 50 F.4th 469 (2022).
After Hurricane Harvey struck southern Texas in 2017, Advanced submitted a claim to Acadia for damage to its building that it claimed was caused by the hurricane's winds. Acadia sent an adjuster, Nick Warren, as well as an engineer, Jason Watson. Watson determined that pre-existing conditions - including ongoing leaks from deterioration and poor workmanship - caused the damage, rather than winds from Hurricane Harvey. Warren adopted these conclusions in his recommendations to Acadia. Acadia denied Advanced's claim based on these reports.
Advanced sued Acadia, alleging breach of contract and bad faith. Advanced filed a motion to remand to state court which was denied. Acadia moved for summary judgment arguing that it did not breach the policy and that Advanced could not segregate any damages caused by hurricane from pre-existing damage. The district court granted Acadia's motion, finding that Acadia's denial of Advanced's claim was based on "extensive consideration of the evidence." Further, Advanced failed to carry its burden of showing that covered and non-covered damages could be segregated as required by Texas's concurrent causation doctrine. Finally, the bad faith claim was dismissed because there was no breach of contract.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Devil is in the Details: The Texas Construction Trust Fund Pitfalls Residential Remodelers (and General Contractors) Should Avoid
December 26, 2022 —
Rochelle Cabe & Roni Most - Kahana FeldA tale of Texas Construction Trust Account woe. You’re a contractor running a business doing interior remodels for clients in a major metropolitan Texas area. You sign up clients with a contract developed by our friends at LegalZoom and get your team to work. Three months into your remodeling project with Mr. and Mrs. “you thought they were happy” Clients, you get this letter:
“Consistent with the requirements of §162.006 and §162.007 of the Texas Property Code, Mr. and Mrs. “you thought they were happy” Clients demand a full and complete accounting of all funds you have received from any source relating to this project.”
What should you do? Should you ignore it? Should you respond? Fear sets in, you call your crew, and you stop the work. Mr. and Mrs. “you thought they were happy” Clients become Mr. and Mrs. “irate and angry” Clients and they sue you alleging breach of fiduciary duty, breach of contract, and perhaps fraud.
Reprinted courtesy of
Rochelle Cabe, Kahana Feld and
Roni Most, Kahana Feld
Ms. Cabe may be contacted at rcabe@kahanafeld.com
Mr. Most may be contacted at rmost@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of