Town Sues over Defective Work on Sewer Lines
January 13, 2014 —
CDJ STAFFThe Handy Sanitary District in North Carolina has filed a lawsuit against one of the subcontractors on the Badin Lake Sewer Project, which the Lexington Dispatch describes as “delay riddled.” The town claims that the materials used by Hobbs, Upchurch and Associates “were not adequate for the project.” Additionally, the town claims that valves were improperly installed or damaged, and that pipes were of the incorrect type and improperly connected.
The Sanitary District Board of Commissioners has additionally settled a lawsuit over non-payment for work on the sewer project. The Handy Sanitary District has settled claims brought by Monroe Roadways Contractors and Young Construction with a payment of $250,000.
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Updates: You May Be Affected
July 19, 2017 —
Louis “Dutch” Schotemeyer – Newmeyer & Dillion LLPGovernor Brown Signs Legislation Increasing Cal/OSHA Fines
Cal/OSHA has increased its maximum fines for the first time in more than twenty years pursuant to legislation recently signed into law by Governor Brown. The changes nearly double the maximum fines and have brought California in line with the Federal standard. The increase in fines will not be isolated to this year, as fines will now be automatically increased annually based on the percentage increase in the Consumer Price Index for All Urban Consumers (CPI-U). Additionally, any employer who repeatedly violates any occupational safety or health standard, order, or special order, or Section 25910 of the Health and Safety Code, can no longer receive any adjustment of a penalty assessed based on the good faith or the history of previous violations. Such adjustments were previously commonplace.
Specific increases are listed below (all increases refer to maximum fines, Cal/OSHA has discretion as to the amount of the fine when issuing the citation):
- Section 6427 of the Labor Code was amended to increase fines, not of a serious nature, from $7,000 for each violation to $12,471 for each violation.
- Section 6429 of the Labor Code has increased fines for repeat violations; raising the maximum fine from $70,000 to $124,709 for each violation. Additionally, Section 6429 also raised the minimum fine for repeat violations from $5,000 to $8,908.
- Section 6431 raised fines for posting or recordkeeping violations from $7,000 to $12,471 per violation.
Full text of the penalty section of the labor code may be found
here
California OSHA Emergency Action Plan elements revised; California now more consistent with Federal Standards
Revisions to General Safety Orders section 3220(b) became effective on June 5, 2017 and contain two minor changes for California employers with regards to Emergency Action Plans (EAP).
The first change requires that an employer’s EAP be more detailed in describing the type of evacuation that is to be performed, not just the route for an evacuation. The previous element of the EAP simply required that the plan contain, “[e]mergency escape procedures and emergency escape route assignments.” The current element of the EAP requires that, “[p]rocedures for emergency evacuation, including type of evacuation and exit route assignments,” be identified.
The second change clarifies the language surrounding employees performing rescue or medical duties. Previously the only requirement in the EAP regarding rescue and medical duties was for employees that performed rescue and medical duties. The current version requires that the EAP contain, “[p]rocedures to be followed by employees performing rescue or medical duties. The use of the word and created potential gaps in plans as it is likely that employees may not be performing both rescue and medical duties, instead performing just rescue or medical duties. Plans must now include procedures to be followed by employees who perform either rescue or medical duties.
It is recommended that your EAP be in writing and updated to comply with the revised General Safety Orders section 3220. The full text of General Safety Orders section 3320 can be seen
here. Please contact us if you would like further details regarding your Emergency Action Plan.
Deadline for Electronic Submission of OSHA 300 Log Records for Injuries and Illnesses Delayed
On May 12, 2016, the Federal Occupational Safety and Health Administration (OSHA) published a rule entitled “Improve Tracking of Workplace Injuries and Illnesses” which required certain employers subject to Federal OSHA regulations to submit the information from their completed 2016 Form 300A to OSHA via electronic submission no later than July 1, 2017. On June 28, 2017, OSHA, via a
Notice of Proposed Rule Making, has proposed a December 1, 2017 deadline for the electronic reporting; the electronic reporting system is scheduled to be available on August 1, 2017.
Per the California Department of Industrial Relations, California employers are not required to follow the new requirements and will not be required to do so until "substantially similar" regulations go through formal rulemaking, which would culminate in adoption by the Director of the Department of Industrial Relations and approval by the Office of Administrative Law.
Cal/OSHA drafted a proposed rulemaking package to conform to the revised federal OSHA regulations by amending the California Code of Regulations, title 8, sections 14300.35, 14300.36, and 14300.41; these are currently under review with the State.
It is currently unclear what, if any, impact the delay by OSHA will have on the proposed amendments to the California Code.
We will keep you posted as to the changes in California recordkeeping requirements. Please contact Louis “Dutch” Schotemeyer with any questions regarding Cal OSHA or your safety program. Dutch is located at Newmeyer & Dillion’s Newport Beach office and can be reached at dutch.schotemeyer@ndlf.com or by calling 949.271.7208.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Agreement Authorizing Party’s Own Engineer to Determine Substantial Compliance Found Binding on Adverse Party
August 30, 2021 —
Garret Murai - California Construction Law BlogWhen it comes to resolving construction disputes it’s a bit like the “31 Flavors” of Baskin Robins. There’s a flavor for nearly everyone. From mediation, to arbitration, to litigation, to dispute resolution boards (DRBs), to the architect as the “initial decision maker” under AIA contracts, parties and their counsel have developed numerous ways to resolve disputes on construction projects, including by expert review.
But if you’re going to agree to a dispute resolution procedure, make sure it’s one you can live with, because if you don’t, it’s often going to be too late to go back to the proverbial drawing board as the parties in the next case discovered.
The Coral Farms Case
In December 2010, a mudslide impacted three properties in San Juan Capistrano, California. One of the properties was owned by Coral Farms, L.P., another by Paul and Susan Mikos, and the third by Thomas and Sonya Mahony.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Is The Enforceability Of A No-Damage-For-Delay Provision Inappropriate For Summary Judgment
February 24, 2020 —
David Adelstein - Florida Construction Legal UpdatesIs the enforceability of a no-damage-for-delay provision inappropriate for resolution on a summary judgment? The recent decision in U.S. f/u/b/o Kingston Environmental Services, Inc. v. David Boland, Inc., 2019 WL 6178676 (D. Hawaii 2019), dealing with Florida law, suggests that it is inappropriate for a summary judgment resolution, particularly when there is a right to a jury trial.
In this case, a prime contractor was hired on a federal construction project in Hawaii. The prime contractor hired a subcontractor and the subcontractor sued the prime contractor and its surety under the Miller Act. Of interest, the subcontractor was seeking to recover for the costs it incurred due to construction delays. The prime contractor moved for summary judgment as to the no-damage-for-delay provision in the subcontract. The no-damages-for-delay provision read as follows (and it is a well-written no-damage-for-delay provision):
The Subcontractor expressly agrees that the Contractor shall not be liable to the Subcontractor for any damages or additional costs, whether foreseeable or unforeseeable, resulting in whole or in part from a delay, hindrance, suspension, or acceleration of the commencement or execution of the Work, caused in whole or in part by the acts or omissions, whether negligent or not, of the Contractor including other subcontractors or material suppliers to the Project, its agents, employees, or third parties acting on behalf of the Contractor. The Subcontractor’s sole remedy for any such delay, hindrance, suspension, or acceleration shall be a noncompensable time extension.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Illinois Legislature Passes Bill Allowing Punitive Damages In Most Wrongful Death Actions
June 05, 2023 —
John Hackett & Jarred Reed - Lewis BrisboisMadison County, Ill. (May 19, 2023) – On May 18, 2023, the Illinois legislature passed House Bill 0219, amending the Illinois Wrongful Death Act to allow for the recovery of punitive damages in wrongful death actions. The bill will soon be sent to the Governor’s desk for signature. If signed into law, the statutory change will allow heirs of decedents to recover punitive damages in wrongful death actions.
The proposed amendment to the Illinois Wrongful Death Act is underlined below:
Whenever the death of a person shall be caused by wrongful act, neglect or default, and the act, neglect or default is such as would, if death had not ensued, have entitled the party injured to maintain an action and recover damages including punitive damages when applicable, in respect thereof, then and in every such case the person who or company or corporation which would have been liable if death had not ensued, shall be liable to an action for damages, including punitive damages when applicable, notwithstanding the death of the person injured, and although the death shall have been caused under such circumstances as amount in law to felony. Nothing in this Section affects the applicability of Section 2-1115 of the Code of Civil Procedure or Section 2-102 or 2-213 of the Local Governmental and Governmental Employees Tort Immunity Act. Punitive damages are not available in action for healing art malpractice or legal practice or in an action against the State or unit of local government or an employee of a unit of local government in his or her official capacity. The changes made to this Section by this amendatory Act of the 103rd general Assembly apply to actions filed on or after the effective date of this amendatory Act.
Reprinted courtesy of
John Hackett, Lewis Brisbois and
Jarred Reed, Lewis Brisbois
Mr. Hackett may be contacted at John.Hackett@lewisbrisbois.com
Mr. Reed may be contacted at Jarred.Reed@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
FIFA Inspecting Brazil’s World Cup Stadiums
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFRepresentatives from FIFA have returned to Brazil to conduct inspections of the World Cup stadiums, according to the San Francisco Chronicle. Even though Brazil had told FIFA they would have all twelve done by the end of 2013, only nine are finished. Furthermore, “infrastructure work in many of the 12 host cities remains far from completed.”
“This is the last occasion for the organizers to take stock of the operational preparations before the respective FIFA World Cup installations begin to be implemented in all 12 host cities,” FIFA said in a statement, as quoted in the San Francisco Chronicle.
Read the court decisionRead the full story...Reprinted courtesy of
Judgment for Insurer Reversed Due to Failure to Establish Depreciation
August 01, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court erred in placing the burden on the policyholder to establish depreciation in determining the actual cash value of the loss. SFR Serv., LLC v. Tower Hill Prime Ins. Co., 2023 Fla. App. LEXIS 3570 (Fla. Ct. App. May 26, 2023).
The insureds' roof was damaged by Hurricane Irma. They submitted their claim to their insurer, Tower Hill. The cost of repair was assessed at $7,726.94, below the amount of the deductible. Therefore, there was no recovery under the policy. The insureds assigned their claim to SFR Services, LLC, their roofing contractor. SFR submitted a claim to Tower Hill for $162,083.84. Tower Hill refused to pay and SFR sued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Brown Paint Doesn’t Cover Up Construction Defects
April 25, 2012 —
CDJ STAFFIn a decision that describes the case as illustrating “the perils that real estate brokers and their agents assume when acting as a dual listing agent to both the buyers and sellers of the same house,” the California Court of Appeals has issued a decision in William L. Lyon & Associates v. The Superior Court of Placer County. Lyon & Associates sought summary judgment to dismiss the claims of the Henleys who bought a home in a transaction where a Lyon agent represented both sides.
The prior owners of the home, the Costas, had used a Lyon agent in purchasing their home. When they later sought to sell it, that agent “became aware of some of the house’s defects and problems.” In response, the Costas sought the help of another agent, Connie Gidal, also of Lyons & Associates. Photos taken in the presence of Ms. Gidal show defects of the paint and stucco. The Costas also took the step of painting the house dark brown. During the sale process, “rain caused many of the painted-over defects to reappear.” The Costas “purchased more dark brown paint and covered up the newly visible damage prior to inspection by the Henleys.”
With the damage concealed, the Henleys bought the home in May 2006. The agreement with Lyons & Associates noted that “a dual agent is obligated to disclose known facts materially affecting the value or desirability of the property to both parties.” Escrow closed on May 9, 2006. The contract with the broker included a two-year limit on the time to bring legal action.
The Henleys moved in during June 2006, and “began to discover construction defects that had been concealed by the Costas.” In addition to the painted-over stucco problems, the Henleys found that the Costas had “installed quartzite stone overlays on the backyard steps in a manner that caused water intrusion on the house’s stucco walls.”
In May 2009, the Henleys sued the Costas, Ron McKim Construction, Lyons & Associates, and Ms. Gidal. Their complaint alleged that Lyons & Associates had committed breach of contact, negligence, fraud, breach of fiduciary duty, and negligent nondisclosure in connection with the construction defects. The Costas named Lyons in a cross complaint. Lyons moved for summary judgments on the grounds that the two-year statute of limitations had expired before the complaint and cross-complaint were filed. Both the Henleys and the Costas opposed this claim. The court denied the motion and Lyons appealed.
The appeals court upheld the denial, noting that the both California Supreme Court decision and later action by the legislature compels real estate brokers and salespersons “to conduct a reasonably competent and diligent visual inspection of the property offered for sale.” The court noted that under California law, brokers have responsibilities to both sellers and buyers. The section of law cited by Lyons applies to seller’s agents. The court rejected the contention by Lyons that they were “cooperating brokers.” The Henleys were “not constrained by the two-year statute of limitations.”
Lyons contended that even if California’s statute did not apply, there was a contractual limit of two years. The court also rejected this, agreeing with the Henleys that “the two-year limitation period must be extended by the discovery rule.”
The court noted that “Lyon & Associates may not reap the benefit of a shortened contractual limitation period when its own alleged malfeasance contributed to the delay in the discovery of the buyer’s injury.” The court found that the Henleys could proceed with their breach of contract claim, because, “when a breach of contract is committed in secret, such as the intentional nondisclosure of a real estate broker regarding a previously visible construction defect, the contractual limitations period is properly held subject to the discovery rule.” The court felt that the interpretation favored by the California Association of Realtors would “halve the applicable statute of limitations period.”
In addition to rejecting Lyon request for summary judgment on the claims made by the Henleys, the court also rejected the request of summary judgment on the claims made by the Costas, concluding that neither claim is time-barred. Costs were awarded to both the Henleys and Costas.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of