SFAA Commends U.S. Senate for Historic Bipartisan Infrastructure Bill
August 16, 2021 —
The Surety & Fidelity Association of AmericaAugust 10, 2021 (WASHINGTON, DC) –
The Surety & Fidelity Association of America (SFAA) commends the U.S. Senate for passing the historic, bipartisan Infrastructure Investment and Jobs Act. The $1.2 trillion deal will lay the foundation for extensive improvements in the nation’s roadways, bridges, railways, waterways and broadband access.
“Investing in infrastructure will create millions of jobs across the country, growing our national and local economies in both the short and long term,” said SFAA president and CEO, Lee Covington. “The surety industry fully supports this investment and will continue to provide the essential protections necessary to support our country’s infrastructure needs through our suite of products and services.”
SFAA also commends the inclusion of the Van Hollen 2354 amendment to the bill, accepted by a unanimous vote of 97-0. The amendment requires payment and performance bonds on all federally-financed infrastructure projects receiving loans and grants under the Transportation Infrastructure Finance and Innovation Act (TIFIA), protecting taxpayers’ dollars, ensuring project completion, protecting local small business contractors and workers, and promoting economic growth.
The Surety & Fidelity Association of America (SFAA) is a trade association of more than 425 insurance companies that write 98 percent of surety and fidelity bonds in the U.S. SFAA is licensed as a rating or advisory organization in all states and it has been designated by state insurance departments as a statistical agent for the reporting of fidelity and surety experience. https://www.surety.org/
Read the court decisionRead the full story...Reprinted courtesy of
Consulting Firm Indicted and Charged with Falsifying Concrete Reports
August 17, 2011 —
CDJ STAFFThe New York Times reports that a company paid to inspect concrete at major public works projects in New York has been charged with falsifying results. They had been hired by the city three years ago after their predecessor was found to have falsified results.
According to the Times, investigators found nothing legitimate in nearly three thousand reports. The owner and five employees of American Standard Testing and Consulting Laboratories have been indicted on twenty-nine counts, including charges under New York’s racketeering law. Prison terms could be up to twenty-five years.
Prior to the city’s contract with American Standard, the city employed a firm called Testwell. Testwell was found in 2008 to have falsified its test results.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Notice of Claim Sufficient to Invoke Coverage
August 06, 2014 —
Tred R. Eyerly – Insurance Law HawaiiIndirect notice to the insurer was sufficient to trigger coverage for the additional insured under a liability policy. Spoleta Constr., LLC v. Aspen Ins. UK Ltd., 2014 N.Y. App. Div. LEXIS 5174 (N.Y. App. Div. July 11, 2014).
An employee of the subcontractor was injured at the construction project on October 20, 2008. The general contractor was named as an additional insured on the subcontractor's CGL policy with Aspen. Under the subcontract, the subcontractor also agreed to defend and indemnify the general contractor for all claims arising out of the subcontractor's work.
The general contractor did not receive notice of the accident until late December 2009 in a letter from the injured employee's attorney. On January 27, 2010, the general contractor's liability carrier sent a letter to the subcontractor giving notice of the employee's claim and requesting that the subcontractor put its carrier on notice. On February 9, 2010, the subcontractor sent to Aspen a claim form with the January 2010 letter attached.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Construction Stitch in Time
October 28, 2015 —
Christopher G. Hill – Construction Law MusingsIt’s a cliche for a reason that “A Stitch in Time Saves Nine.” Why? Because it is almost always cheaper and more efficient in the long run to get something right the first time than to fix it later. This old adage is true in life, and particularly true in the world of construction.
Whether it’s measuring twice before making your bid, checking with your subcontractors and suppliers to be sure they haven’t missed anything when giving you a price, or yes (and you knew this was coming), being sure that your contracts are written as they should be and cover the bases. To use another construction related analogy, these types of basic practices create a great foundation for your construction project(s) that will (hopefully) see you through to a successful and profitable construction project.
Aside from the last of my examples, how can adding a knowledgeable construction attorney help with laying this foundation? We construction lawyers spend our days either dealing with problems that have occurred (not ideal), anticipating risks that could occur (better, though can lead to a relatively cynical world view), and advising clients before the fact of the potential risks and how to best avoid them (best). Speaking from experience, I would much rather spend my time keeping my construction clients making money and avoiding the pitfalls of the “Murphy’s Law” governed world of construction than spend time with them in court.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Cincinnati Team Secures Summary Judgment for Paving Company in Trip-and-Fall Case
February 05, 2024 —
Lewis BrisboisCincinnati, Ohio (January 25, 2024) - In a recent decision by the Oldham County Circuit Court, Lewis Brisbois Partner Andrew Weber and Associate Jason Paskan obtained summary judgment for a paving company client after successfully arguing that their client did not owe the plaintiff a duty at the time leading up to her trip and fall. Although the court concluded that there was a genuine issue of fact as to whether a parking space wheel stop actually caused her fall, the court noted that whether the wheel stop “constituted an unreasonably dangerous condition necessitating a duty to eliminate them or warn of them is an entirely different matter.” Rebecca Reynolds v. Baptist Healthcare System, Inc., et al., Oldham Circuit Court Case No. 21-CI-00236, *6 (Dec. 21, 2023).
The plaintiff in Reynolds drove to the hospital with her sister-in-law for medical testing. Id. at * 2. While both had been to the hospital before, due to COVID and construction in the emergency department, they had to take a different entrance into the hospital. Id. In the plaintiff’s attempt to navigate the parking lot, she allegedly tripped over a black wheel stop that was covered by a shadow. Id. The plaintiff sued the hospital as the landowner and the paving company working in the hospital’s parking lot, among others, under the theory that the failure to stripe the wheel stop, closing off spaces with the black wheel stops, or posting warnings about the condition of the parking lot would have prevented her fall. Id. at *2-3.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Timely Written Notice to Insurer and Cooperating with Insurer
June 21, 2017 —
David Adelstein - Florida Construction Legal UpdatesI harp on notifying a liability insurer in writing once a claim is asserted against you. As soon as possible. I harp on this because as an insured you want to remove any doubt or argument that the insurer was prejudiced due to a lack of timely notice.
In a recent opinion, Zurich American Insurance Co. v. European Tile and Floors, Inc., 2017 WL 2427172 (M.D.Fla. 2017), the insurer moved for summary judgment in a coverage action arguing that its insured failed to provide it timely written notice. Specifically, the insurer argued that the insured violated the clause in the liability policy that states:
2. Duties in the Event of Occurrence, Offense, Claim or Suit
b. If a claim is made or “suit” is brought against any insured, you must:
- Immediately record the specifics of the claim or “suit” and the date received; and
- Notify us as soon as practicable.
You must see to it that we receive written notice of the claim or “suit” as soon as practicable.
c. You and any other insured must:
- Immediately send us copies of any demands, notices, summonses or legal papers received in connection with the claim or “suit”;
- Authorize us to obtain records and other information;
- Cooperate with us in the investigation, settlement or defense of the claim or “suit”; and
- Assist us, upon our request, in the enforcement of any right against any person or organization which may be liable to the insured because of injury or damage to which this insurance may also apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
A Year-End Review of the Environmental Regulatory Landscape
January 11, 2022 —
Anne Idsal Austin & Joel Simon - Gravel2Gavel Construction & Real Estate Law BlogOur guest today is Anne Idsal Austin, a nationally recognized environmental lawyer who has held several high-profile federal and state regulatory roles. As a partner who recently joined Pillsbury’s environmental and natural resources practice, she provides strategic consulting and policy advice, helping clients navigate the dynamic regulatory and legal waters in an era of energy transition, decarbonization and an emphasis on ESG principles. Prior to joining Pillsbury, Anne was the Principal Deputy Assistant Administrator for the U.S. Environmental Protection Agency’s Office of Air and Radiation, known as OAR or OAR, where she had primary oversight over United States clean air policy and regulation. Prior to that, she served as the EPA regional administrator for Region 6, overseeing all federal environmental programs in Texas, Louisiana, New Mexico, Oklahoma and Arkansas. Prior to joining EPA, Anne held several positions where she shaped environmental and energy policy at the highest levels of government in the state of Texas. Welcome to our podcast, Anne.
Anne Austin: Thanks so much. It’s great to be here today, Joel.
Joel Simon: Anne, I’m really excited for this chance to speak with you because there’s so much going on at the federal environmental policy level, and it would be great to have someone really knowledgeable present this to us in an organized fashion. So with that minor task ahead of you, could you start us off with a brief overview of the environmental regulatory landscape?
Reprinted courtesy of
Anne Idsal Austin, Pillsbury and
Joel Simon, Pillsbury