Serving Notice of Nonpayment Under Miller Act
January 20, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the federal Miller Act, if a claimant is NOT in privity with the prime contractor, it needs to serve a “notice of nonpayment” within 90 days of its final furnishing. In this manner, 40 U.S.C. 3133 (b)(2) states:
A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made. The action must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. The notice shall be served–
(A) by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor’s residence; or
(B) in any manner in which the United States marshal of the district in which the public improvement is situated by law may serve summons.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurer's Attempt to Strike Experts in Collapse Case Fails
February 03, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's efforts to exclude two of the insured's experts in a collapse case were unsuccessful. Hudon Specialty Ins. Co. v. Talex Enterprises, LLC, 2019 U.S. Dist. LEXIS 150148 (S.D. Miss. Sept. 4, 2019).
The insureds' building collapsed. The remaining portions of the building required immediate stabilization. The insureds hired Mr. Laird, an engineer, to prevent further property destruction. The insured designated Mr. Laird as a non-retained expert for trial. Mr. Laird's report claimed that the collapse was caused because the building had been re-roofed many times without removal of the degraded underlying roofing materials, thereby adding additional weight to the roof structure.
The insureds also designated Steve Cox as a non-retained expert. Mr. Cox was an architect who owned property neighboring the building that collapsed. He opined that the building collapsed because of the condition of very old mortar and not because of water standing on the building roof or because of roof repairs.
Hudson sought to strike these two experts because their opinions were inconsistent with the admitted facts. A document produced by the insureds stated that a large amount of rainwater had collected on the roof and the weight of the rainfall was the proximate cause of the collapse. Hudson claimed that this statement qualified as a judicial admission, removing the question of causation from contention. The court disagreed that the statement was a judicial admission because it did not form any part of the pleadings. The statement may have been an evidentiary admission that could be controverted or explained by the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court of Appeals Issues Decision Regarding Second-Tier Subcontractors and Pre-Lien Notice
February 06, 2023 —
Travis Colburn - Ahlers Cressman & SleightVelazquez Framing, LLC (“Velazquez”) v. Cascadia Homes, Inc. (“Cascadia”) is a Court of Appeals, Division 2 case where the primary issue on appeal was whether a second tier subcontractor was required to provide pre-lien notice under RCW 60.04 for its labor.
The defendant, Cascadia, was the general contractor that planned to build a home on property it owned in Lakewood, Washington.[1] High End Construction, LLC (“High End”), submitted a bid to Cascadia for framing work on the home. High End began work on Cascadia’s home, but later subcontracted with Velazquez to complete the framing work.[2] Velazquez did not submit a prelien notice for its work on Cascadia’s home, and Cascadia claimed it was unaware that High End subcontracted with Velazquez for framing at the project.
High End invoiced Cascadia and was paid for its work, but High End never paid Velazquez. Subsequently, Velazquez recorded a lien for both labor and materials, and later filed a complaint to foreclose its lien. Cascadia, due to the fact Velazquez did not provide it with prelien notice, moved for summary judgment, arguing prelien notice was required under RCW 60.04.031(1)[3] and the labor portion of a lien cannot be segregated where a subcontractor’s lien includes both labor and materials. Velazquez argued that no prelien notice was required under RCW 60.04.021[4] and RCW 60.04.031 and claimed that subcontractors can segregate the labor portion from the materials portion. The trial court granted Cascadia’s motion and ruled Velazquez did not fall within one of the exceptions for prelien notice in RCW 60.04.031(2), and therefore, could not enforce the lien. Velazquez appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
RCW 82.32.655 Tax Avoidance Statute/Speculative Building
August 29, 2018 —
Scott R. Sleight - Ahlers Cressman & Sleight PLLC BlogWith land prices increasing, developers are looking for opportunities to save on development costs, including cost saving tax strategies. Thus, we have seen increasing interest in development strategies that offer tax savings. One strategy is speculative building: Owners of property who self-perform construction avoid sales tax and B&O tax on the self-performed scope. See Blog Article Posted April 9, 2013, titled What Is A Speculative Builder? In addition, the Department of Revenue has provided an explanation of speculative building.
Read the court decisionRead the full story...Reprinted courtesy of
Scott R. Sleight, Ahlers Cressman & Sleight PLLCMr. Sleight may be contacted at
scott.sleight@acslawyers.com
Overtime! – When the Statute of Limitations Isn’t Game Over For Your Claim
August 07, 2022 —
Bradley E. Sands, Jones Walker LLP - ConsensusDocsStatutes of limitations establish the period of time within which a claimant must bring an action after it accrues. An action can be filing a lawsuit and, in some instances, filing a demand for arbitration. But a multi-year construction project could be longer than the applicable statute of limitations. For example, under Delaware or North Carolina law, the statute of limitations for a breach of contract is only three years.1 So a claim for breach of a construction contract that occurred (i.e. accrued) at the beginning of a four-year project under Delaware or North Carolina law may expire before the project is completed.
Generally, a claim accrues at the time of the breach (however, it is important to note that this is not always the case and claim accrual could be the subject of an entirely different article). During the course of a multi-year construction project, proposed change orders or claims for additional compensation can sit, unanswered or unpursued, for months. Or, the parties may informally agree as part of regular project communications to put off dealing with a claim head-on until the end of the project. On certain projects, slow-walking a claim is understandable, as a contractor may be hesitant to sue an owner in the middle of a multi-year project and risk upsetting an otherwise good working relationship. But a delay in formally asserting a put-off claim after it accrues could result in the claim falling subject to a statute of limitations defense.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley E. Sands, Jones Walker LLP (ConsensusDocs)Mr. Sands may be contacted at
bsands@joneswalker.com
PulteGroup Fires Exec Accused of Defamation By Founder’s Heir
January 17, 2023 —
Patrick Clark - BloombergPulteGroup Inc. fired a senior executive for violating the company’s code of conduct two days after the grandson of the homebuilder’s founder sued the executive for alleged defamation.
The company, which is the third-largest US homebuilder, said in a statement Friday that it had terminated Brandon Jones after the results of an independent investigation. Jones had been slated to assume the role of chief operating officer in January.
Bill Pulte, 34, filed a lawsuit on Wednesday in Palm Beach County, Florida, alleging that Jones had used anonymous Twitter accounts to smear members of the Pulte family. The lawsuit accused the executive of impersonating a business journalist and making a false claim that Pulte manipulated his grandfather.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
San Francisco Museum Nears $610 Million Fundraising Goal
June 26, 2014 —
Dan Levy – BloombergThe biggest museum fundraising campaign in San Francisco history is nearing its $610 million goal two years before the opening of a new wing that will more than double the space for artworks by Andy Warhol, Mark Rothko and David Hockney.
About $570 million, or 94 percent, has been raised by the San Francisco Museum of Modern Art for its 235,000-square-foot (21,800-square-meter) expansion and to add $245 million to the museum’s endowment. The $305 million wing designed by the Snohetta architecture firm is rising behind SFMOMA’s current home, opened two decades ago in the technology-heavy South of Market area, or SOMA.
“In 1995, we were the pioneers when SOMA was pretty run-down, and the tech boom followed us,” Neal Benezra, the museum’s director, said June 20 in a presentation at Bloomberg LP’s San Francisco offices. “Our expansion will solidify the neighborhood as a cultural hub.”
Read the court decisionRead the full story...Reprinted courtesy of
Dan Levy, BloombergMr. Levy may be contacted at
dlevy13@bloomberg.net
Arbitration is Waivable (Even If You Don’t Mean To)
February 16, 2016 —
Christopher G. Hill – Construction Law MusingsBe careful with how you act with arbitration clauses in your contracts. If you are not careful in how you act to enforce these clauses, you could find yourself stuck in court whether you like it or not.
As I stated in a recent update to a post last month, the Fourth Circuit Court of Appeals recently weighed in on the issue of a contractor’s waiver of its rights to arbitration under a contract. Briefly, the facts of Forrester v. Penn Lyon Homes, et. al., No. 07-2171 are as follows. The Forrester’s sued Penn Lyon and its warranty company alleging among other things a breach of express warranty based upon a warranty contract containing a mandatory arbitration clause. Instead of immediately alleging an affirmative defense based upon the arbitration clause, the defendants removed the case to federal court and litigated for 18 months before raising the arbitration defense for the first time.
The 4th Circuit (correctly in my opinion) affirmed the lower court and held that the defendants defaulted their right to arbitration because of their actions in defense of the court action and the prejudice to the plaintiffs caused by those actions.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com