Reminder: The Devil is in the Mechanic’s Lien Details
February 16, 2017 —
Christopher G. Hill – Construction Law MusingsAs readers of Construction Law Musings are well aware, mechanic’s liens and their picky and at times overly form oriented nature are near and dear to my heart as a construction attorney here in Virginia. I recently had the opportunity to meet this head on in Hanover County, Virginia Circuit Court. I was defending a suit to enforce a mechanic’s lien in the context of a lien that had been released pursuant to a bond deposited with the court under Va. Code 43-71 on behalf of my client, the defendant in that suit.
The case, G.H. Watts Construction, Inc. v. Cornerstone Builders, LLC, involved a memorandum of lien recorded by G. H. Watts without the assistance of an attorney in which the claimant was identified as “G. H. Watts Construction, Inc.” while the signatory on the memorandum of lien and the claimant identified in the notary block were identified as “Gary H. Watts” and “Gary Watts” respectively. Nowhere on the memorandum was Gary Watts’ capacity as it related to the company, nor did it state that Gary Watts was an agent for claimant.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Checking the Status of your Contractor License During Contract Work is a Necessity: The Expanded “Substantial Compliance” under B&P 7031 is Here
June 05, 2017 —
Ivo G. Daniele – Newmeyer & Dillion LLP News AlertIt is paramount that a contractor diligently maintains its license prior to and during the performance of any contract work. Failure to do so could result in barring a contractor from receiving payment and/or disgorgement of profits received under the construction contract.
California Business and Professions Code section 7031 is part of the Contractors State License Law (Business & Prof. section 700 et seq.), and is both feared and loathed by all contractors performing work in the state of California. This draconian statute is known as the “Shield” and was enacted over 70 years ago for the singular purpose to bar all actions by contractors seeking compensation for unlicensed contract work – even precluding a contractor from enforcing his or her mechanic’s lien rights. However, a contractor could potentially avoid the harshness of B&P 7031 by establishing that he or she had substantially complied with the appropriate licensing requirements.
SUBSTANTIAL COMPLIANCE WITH LICENSE REQUIREMENTS PRIOR TO 2017 AMENDMENT
The substantial compliance exception is found in section B&P 7031(e), which authorizes the court to determine that there has been substantial compliance with licensure requirements, if the contractor has shown at an evidentiary hearing that he or she engaged in the unlicensed work had:
- Been duly licensed as a contractor in this state prior to the performance of the act or contract;
- Acted reasonably and in good faith to maintain the license;
- Did not know or reasonably should not have known that he or she was not licensed when he or she performed the work; and
- Acted promptly and in good faith to reinstate the license once it learned the license had lapsed.
Although not impossible, satisfying all four requirements of the exception was challenging for the contractor, specifically, requirement # (3) – the lack of knowledge that he or she was unlicensed during performance of work.
SUBSTANTIAL COMPLIANCE POST 2017
Fortunately, Governor Brown heard the collective cry for relief and signed Assembly Bill 1793 (“AB 1793”) into law. The new bill revises the criteria for the court to determine if a contractor is in substantial compliance with the licensing requirements by deleting requirement # (3) in its entirety and modestly amending requirement # (4) to require the contractor to act promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.
As a result, the substantial compliance exception under B&P 7031(e) reads as follows:
(e) The judicial doctrine of substantial compliance shall not apply under this section where the person who engaged in the business or acted in the capacity of a contractor has never been a duly licensed contractor in this state. However, notwithstanding subdivision (b) of Section 143, the court may determine that there has been substantial compliance with licensure requirements under this section if it is shown at an evidentiary hearing that the person who engaged in the business or acted in the capacity of a contractor
(1) had been duly licensed as a contractor in this state prior to the performance of the act or contract, (2) acted reasonably and in good faith to maintain proper licensure, and (3) acted promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.
This new legislation has tempered the burden of proof born by the contractor in establishing substantial compliance, although be it minor in its modification, the fact of the matter remains the same – be diligent in maintaining your license during all phases of contract work.
Ivo Daniele is a seasoned associate in the Walnut Creek office focusing his practice on commercial transactions and business and construction litigation. For questions regarding California Business and Professions Code section 7031, please feel free to contact Ivo Daniele at (925) 988-3222 or ivo.daniele@ndlf.com.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Case-Shiller Redo Shows Less Severe U.S. Home-Price Slump
September 03, 2014 —
Lorraine Woellert – BloombergThe collapse in U.S. home prices that stoked the worst recession since the Great Depression wasn’t quite as severe as initially estimated, according to data from S&P/Case-Shiller.
Property values nationally fell 26 percent from the February 2007 peak to the December 2011 trough, not 34 percent as previously reported, revised data showed last week. The index will now be issued monthly rather than quarterly.
The change is the result of CoreLogic Inc. (CLGX)’s $6 million purchase of the S&P/Case-Shiller index from technology company Fiserv Inc. in March 2013. Case-Shiller has spent more than a year retrofitting its model with CoreLogic’s bigger, higher-quality data set, leading to a change in how the index looks.
Read the court decisionRead the full story...Reprinted courtesy of
Lorraine Woellert, BloombergMs. Woellert may be contacted at
lwoellert@bloomberg.net
Hawaii Supreme Court Tackles "Other Insurance" Issues
February 25, 2014 —
Tred Eyerly – Insurance Law HawaiiResponding to four certified questions from the Ninth Circuit, the Hawaii Supreme Court addressed various issues raised by competing "other insurance" provisions in two CGL policies. Nautilus Ins. Co. v. Lexington Ins. Co., 2014 Haw. LEXIS 59 (Haw. Feb. 13, 2014).
Coverage for a development on Maui was at issue. The developer, VP & PK (ML) LLC, was insured by Lexington. The other insurance provision in Lexington's policy provided it was excess over "any other primary insurance available to you covering liability for damages arising out of the premises . . . for which you have been added as an additional insured."
Kila Kila Construction was one of VP & PK's subcontractors. Kika Kila was not an additional insured under Lexington's policy. Kila Kila had its own CGL policy with Nautilus. The Nautilus other insurance clause stated the insurance was excess over "any other primary insurance available to you covering liability arising out of the premises or operations for which you ahve been added as an additional insured." An endorsement added VP & PK as an additional insured, but only for liability arising out of Kila Kila's negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Want More Transit (and Federal Funding)? Build Housing That Supports It
January 08, 2024 —
M. Nolan Gray - BloombergAfter
decades of planning (and $2.1 billion spent), Los Angeles’ newest light rail line opened in October 2022. Joined by geeky rail obsessives and chaperoned children, I rode the K Line on opening day. A blend of underground, elevated and at-grade track, it’s a route only a politician could love. Stations were lavished with public art, and when the train wasn’t stuck in traffic, it glided through the sprawl.
Yet one year later, it is Los Angeles’ least-used line, averaging
just over 2,000 riders on an average weekday this fall.
It isn’t hard to see why: The line begins at a vacant patch in Crenshaw and ends in a low-slung industrial park about six miles away, lined by strip malls the entire way. Walk one block east or west from any given station, and you’ll find yourself amid single-story postwar bungalows on 7,500-square-foot lots — all illegal to redevelop into apartments, thanks to local zoning. The Hyde Park Station deposits riders into a cluster of gas stations and drive-thru fast-food joints.
Read the court decisionRead the full story...Reprinted courtesy of
M. Nolan Gray, Bloomberg
Lenders Facing Soaring Costs Shutting Out U.S. Homebuyers
October 29, 2014 —
Alexis Leondis and Clea Benson – BloombergClem Ziroli Jr.’s mortgage firm, which has seen its costs soar to comply with new regulations, used to make about three loans a day. This year Ziroli said he’s lucky if one gets done.
His First Mortgage Corp., which mostly loans to borrowers with lower FICO credit scores and thick, complicated files, must devote triple the time to ensure paperwork conforms to rules created after the housing crash. To ease the burden, Ziroli hired three executives a few months ago to also focus on lending to safe borrowers with simpler applications.
“The biggest thing people are suffering from is the cost to manufacture a loan,” said Ziroli, president of the Ontario, California-based firm and a 22-year industry veteran. “If you have a high credit score, it’s easier. For deserving borrowers with lower scores, the cost for mistakes is prohibitive and is causing lenders to not want to make those loans.”
Reprinted courtesy of
Alexis Leondis, Bloomberg and
Clea Benson, Bloomberg
Ms. Leondis may be contacted at aleondis@bloomberg.net; Ms. Benson may be contacted at cbenson20@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Convicted of Additional Fraud
November 18, 2011 —
CDJ STAFFA Pennsylvania contractor in prison for fraud has been convicted with insurance fraud. The York Daily Record reports that Steven D. Gebhart was already in jail for fraud for about $350,000 for work he either failed to finish or even start or by using substandard materials and practices when he was convicted of insurance fraud. Gebbert’s offices were destroyed in a fire that was later determined to be arson. He was not charged with this, but instead for overestimating his losses to the insurance company. Sentencing for the fraud charge will be on December 21.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
#10 CDJ Topic: Carithers v. Mid-Continent Casualty Company
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFCraig Martin of
Lamson Dugan and Murray, LLP on his
Construction Contractor Advisor blog used the Carithers case to demonstrate how “[w]hen you are involved in construction litigation, you have battles on several fronts, including those against subcontractors, owners, insurers and the court. Shoring up your defenses on each of these fronts is imperative, or you may lose the battle or, worse yet, the war.” Martin discusses the various “battle fronts” including the “Claim Against Contractor,” “Where Are You Litigating,” “Claim Against Insurance Company,” and “Damages.”
Read the full story...
In the article, “Duty to Defend Construction Defect Case Affirmed, Duty to Indemnify Reversed In Part,” attorney
Tred R. Eyerly also covered the Carithers case. Eyerly explained, “Determining whether there was coverage for the damages awarded required the court to decide which trigger applied. Examining the policy language, the court determined that property damage occurred when the damage happened, not when the damage was discovered or discoverable. Therefore, the district court did not err in applying the injury in fact trigger.”
Read the full story...