New York Revises Retainage Requirements for Private Construction Contracts: Overview of the “5% Retainage Law”
January 22, 2024 —
Levi W. Barrett, Patrick T. Murray, Skyler L. Santomartino & Mark A. Snyder - Peckar & Abramson, P.C.On November 17, 2023, the State of New York enacted the “5% Retainage Law.” This legislation effectively limits the amount of retainage that can be held from general contractors and subcontractors to no more than 5%. It applies to many but not all construction contracts. In addition, the new law revises late stage billing requirements, enabling contractors to invoice for retainage at substantial completion. Previously, the parties to a construction contract were free to negotiate any retainage amount, limited only by an unspecified “reasonable amount” that would be released as the parties contractually set forth.
Summary
The new law amends Sections 756-a and 756-c of the General Business Law (part of Article 35E of the GBL, known as the “Prompt Pay Act”), and applies to private construction contracts “where the aggregate cost of the construction project, including all labor, services, materials and equipment to be furnished, equals or exceeds one hundred fifty thousand dollars.”
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Patrick T. Murray, Peckar & Abramson, P.C.,
Skyler L. Santomartino, Peckar & Abramson, P.C. and
Mark A. Snyder, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Murray may be contacted at pmurray@pecklaw.com
Mr. Santomartino may be contacted at ssantomartino@pecklaw.com
Mr. Snyder may be contacted at msnyder@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Builder Exposes 7 Myths regarding Millennials and Housing
January 12, 2015 —
Beverley BevenFlorez-CDJ STAFFBuilder Magazine discussed seven myths regarding Generation Y and housing, and stated whether it was fact or fiction. First, they answered whether “Millennials Carry Historically High Student Debt Levels,” (True), and second they concluded it was true that “Millenials Can’t Afford Down Payment at Today’s Standards.” However, Builder was split on whether “Millennials Will Pay a Premium for Green and Tech Features.”
Read the court decisionRead the full story...Reprinted courtesy of
Collapse Claim Dismissed
December 04, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe complaint alleged collapse, but the claimed cause of the collapse was not a covered cause under the insured's policy, mandating a dismissal of the complaint. Coonce v. CSSA Fire & Cas. Ins. Co., 2018 U.S. App. LEXIS 25010 (10th Cir. Sept. 4, 2018).
The ceiling in the insured's living and dining areas caved in. An engineering survey determined that the nails used in the construction had failed to hold. The insured made a claim on her policy issued by CSAA. Coverage was denied and the insured sued.
The insured was given two opportunities to amend her complaint by the district court, but the motion to dismiss for failure to state a claim was eventually granted.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Appellate Court reverses district court’s finding of alter ego in Sedgwick Properties Development Corporation v. Christopher Hinds (2019WL2865935)
August 13, 2019 —
Frank Ingham - Colorado Construction LitigationDivision V of the Colorado Court of Appeals addressed, for the first time, corporate veil-piercing in the context of a single-member, single-purpose LLC that is managed under a contract by another company. On July 3, 2019, the Court of Appeals reversed the order of the Honorable Ross B. Buchannan, Denver District Court Judge (17CA2102), who held that Plaintiff/Appellee Christopher Hinds satisfied the elements required to pierce the corporate veil of Sedgwick Properties Development Corporation (“Sedgwick”).
Background
Defendant 1950 Logan, LLC (“1950 Logan”) was the developer of a building located at 1950 Logan Street, in Denver, called The Tower on the Park (“Project”), which contained 141 individually owned condominium units. The Project was completed in 2006. 1950 Logan was a single-purpose entity created for the construction of the Project, which is a common practice in the construction industry. After the units were sold in 2006, the LLC wrapped up operations.
Read the court decisionRead the full story...Reprinted courtesy of
Frank Ingham, Higgins, Hopkins, McLain & Roswell, LLCMr. Ingham may be contacted at
ingham@hhmrlaw.com
Measure Of Damages for Breach of Construction Contract
October 18, 2021 —
David Adelstein - Florida Construction Legal UpdatesHow do you determine damages for a breach of a construction contract? If you are interested in pursing a breach of a construction contract action, this is something you NEED TO KNOW!
The recent Fourth District Court of Appeal’s decision in Cano, Inc. v. Judet, 46 Fla. L. Weekly D2083b (Fla. 4th DCA 201) explains:
Where a contractor breaches a construction contract, and the owner sues for breach of contract and the cost to complete, the measure of damages is the difference between the contract price and the reasonable cost to perform the contract. See Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037, 1039-40 (Fla. 1982). In Grossman, the supreme court adopted subsection 346(1)(a) of the Restatement (First) of Contracts (1932), which it concluded was “designed to restore the injured party to the condition he would have been in if the contract had been performed.” Id. at 1039. In other words, the owner will obtain the benefit of his bargain [and this is known as benefit of the bargain damages]. But where there is a total breach of the contract as opposed to a partial breach, an injured party may elect to treat the contract as void and seek damages that will restore him to the position that he was in prior to entering into the contract or the party may seek the benefit of his bargain. See McCray v. Murray, 423 So. 2d 559, 561 (Fla. 1st DCA 1982).
In Judet, an owner entered into a fixed price contract with a contractor to repair damage from a lightning strike. The contract amount was $300,000 payable in $30,000 installments. A few months after the contractor commenced performance, the owner terminated the contractor because the owner learned the contractor had not obtained required electrical and plumbing permits. At this time, the owner had paid the contractor $90,000. The contractor recorded a $40,000 lien for an amount it claimed it was owed and filed a lawsuit to foreclose its construction lien. The owner counter-sued the contractor to recover a claimed over-payment and a disgorgement of monies for unpermitted work. The owner was NOT claiming benefit of the bargain damages, but rather, damages for the contractor’s total breach “to restore him to the position that he was in prior to entering into the contract.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Contract Clauses That May or May Not Have Your Vote – Part 3
November 23, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The third in a multi-part series, here are some other important construction contract clauses that may determine whether you come out a winner.
Provision: Supervisory Personnel, Employees, and Authority to Bind Provisions
- Typical Provision: ”At all times during performance of the Work, Subcontractor shall have at the job site a competent supervisor approved by Owner. Subcontractor’s supervisor shall be deemed a representative of Subcontractor and all communications given to Subcontractor’s supervisor shall be as binding as if such communications were given to Subcontractor. Should Contractor object to Subcontractor’s supervisor’s presence at the job site, or the presence at the job site, or the presence at the job site of any other employee or agent of Subcontractor or any employee or agent of Subcontractor of Subcontractor, Subcontractor shall cause such persons to be replaced immediately as directed by Contractor.”
- What it Means: Higher-tiered parties have a legitimate interest in ensuring that only competent individuals are allowed to perform work on a project and in ensuring that there are peaceable relations at a job site. Higher-tiered parties also have an interest in ensuring that directives and agreements made and reached in the field are followed. However, it is unreasonable for higher-tiered party or to require that such personnel be able to bind that lower-tiered party to agreements best decided by others.
- What You Can Do: Lower-tiered parties should seek to include language which provides that only “reasonable” changes to personnel are allowed and, as necessary, limit by category or issue the types of items on-site personnel can bind the lower-tiered party to.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Dispute Over Amount Insured Owes Public Adjuster Resolved
January 14, 2025 —
Tred R. Eyerly - Insurance Law HawaiiThe court addressed a dispute over fees that the insureds allegedly owed the public adjuster. Public' Adjuster's, LLC v. Mark Gottesdiener & Co., et al., 2024 Conn. Super. LEXIS 2352 (Conn. Super. Ct. Nov. 6. 2024).
The insureds owned an apartment building that was substantially damaged by a fire. The building was insured by Quincy Mutual Group. The insureds signed a Public Adjuster Employment Contract with The Public's Adjuster, LLC (Adjuster). The contract authorized Adjuster to negotiate the reimbursable damages with Quincy on the insureds' behalf. Adjuster was to recover 8 1/2% of any amounts received by the insureds.
Because of the extent of the fire damage, the work of negotiating a settlement with Quincy proved to be complex. Adjuster meticulously prepared several detained written estimates to by submitted to Quincy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Environmental Justice Update: The Justice40 Initiative
April 29, 2024 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law BlogSoon after taking office, President Biden issued Executive Order 14008, entitled, “Tackling the Climate Crisis at Home and Abroad.” This is an unusually long and complex executive order and includes many provisions relating to environmental justice and the plight of “disadvantaged communities” that are overwhelmed by many environmental threats. Section 223 of the Order describes the President’s “Justice40 Initiative,” which is designed to ensure that 40% of Federal benefits flow to disadvantaged communities through an “all of government approach.” There is a recognition that some disadvantaged communities lack the personnel and resources to take advantage of this Initiative, so technical training funds will be made available. The Order establishes new offices throughout the Federal bureaucracy to handle and expedite environmental justice matters.
The Office of Management and Budget (OMB) and the Council on Environmental Quality (CEQ) play a large role in implementing the Initiative by issuing appropriate guidance and assisting the Federal agencies to locate, among the thousands of programs they supervise, suitable programs that will assist disadvantaged communities. At last count, 518 Federal programs administered by 19 distinct Federal agencies could be a good source for the resources needed by disadvantaged communities to cope with air and water pollution and solid waste issues. Direct grants will be made in many cases, and other programs require the community to apply for the funds promised by the Executive Order. In addition, the Order requires participating Federal agencies to assess the value and effectiveness of the benefits bestowed. OMB and the CEQ have issued guidance documents and conducted many meetings with key personnel and members of the disadvantaged communities.
Read the court decisionRead the full story...Reprinted courtesy of