Recommendations and Drafting Considerations for Construction Contingency Clauses Part III
December 27, 2021 —
Samantha Schacht & Josh Levy - Construction ExecutiveThe best contracts provide the parties with a clear allocation of risks and responsibilities, and a process for handling inevitable project challenges. Contract negotiations can enable parties to have the difficult conversations allocating risks before the start of a project. An effective negotiation, in turn, aligns the parties’ expectations and helps avoid costly disputes born out of misunderstandings of the parties’ respective rights and responsibilities on the project.
This final installment of a three-part series on contingencies in construction contracts addresses factors that should be discussed and considered when drafting a contingency clause in a construction contract with the goal of helping to set clear expectations and avoid disputes.
Part I The Best Laid Plans: Contingency in a Construction Contract explained what a construction contingency is and
Part II The Best Laid Plans: Contingency in a Construction Contract discussed the two primary schools of thought on how a construction contingency fund should be used and managed.
Reprinted courtesy of
Samantha Schacht, Construction Executive and Josh Levy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Schacht may be contacted at samantha.schacht@huschblackwell.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractor’s Burden When It Comes to Delay
October 26, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen a contractor is challenging the assessment of liquidated damages, or arguing that it is entitled to extended general conditions, the contractor bears a burden of proof to establish there were excusable delays that impacted the critical path and, in certain scenarios, the delays were not concurrent with contractor-caused delay:
When delays are excusable, a contractor is entitled to a time extension, such that the government may not assess liquidated damages for those delays. The government bears the initial burden of proving that the contractor failed to meet the contract completion date, and that the period of time for which the government assessed liquidated damages was correct. If the government makes such a showing, the burden shifts to the contractor to show that its failure to timely complete the work was excusable. To show an excusable delay, a contractor must show that the delay resulted from “unforeseeable causes beyond the control and without the fault or negligence of the Contractor.” “In addition, the unforeseeable cause must delay the overall contract completion; i.e., it must affect the critical path of performance.” Further, the contractor must show that there was no concurrent delay.
Ken Laster Co., ASBCA No. 61292, 2020 WL 5270322 (ASBCA 2020) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Anatomy of a Construction Dispute Stage 2- Increase the Heat
January 21, 2015 —
Christopher G. Hill – Construction Law MusingsLast week we discussed the groundwork and circumstances of a construction claim. This week’s post will discuss the next steps, hopefully short of full blown arbitration or litigation that you, as a construction company, can pursue presuming your claim has been properly preserved.
If your contract requires certain steps such as informal resolution attempts or other items, these are the first things that must be done while still preserving your rights to pursue all remedies available. Instituting such contractually required resolution steps can and should be the first “notch” on the dial of increased pressure on the Owner, General Contractor or possibly Subcontractor against whom you have a claim.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
California Attempts to Tackle Housing Affordability Crisis
December 22, 2019 —
Garret Murai - California Construction Law BlogIt’s a bit too early yet for our 2020 Construction Law Update but here’s a preview of some of the new laws taking effect next year. Earlier this month, Governor Gavin Newsom signed a slate of 18 bills to boost housing production in an effort to tackle the state’s housing affordability crisis.
First, a bit of background.
California currently ranks 49th among the states in housing units per resident. Experts say that the state needs to double its current rate of housing production of 85,000 unit per year just to keep up with population growth and four times the current rate to reduce housing costs. Anecdotally, here in the San Francisco Bay Area, the median rent for a one-bedroom apartments in San Francisco is currently $3,690 per month or $44,280 per year. However, as of May 2018, according to the U.S. Bureau of Statistics, the annual mean wage of a teller is just $32,840, for farmworkers $34,700, and for teachers $48,250. And that’s before taxes. Let that sink in for a moment.
The result is one in five Californians live in poverty, the highest rate in the nation, when factoring in the cost of living.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Direct Contractors In California Should Take Steps Now To Reduce Exposure For Unpaid Wages By Subcontractors
February 07, 2018 —
Nora Stilestein, Candace Matson , and Mercedes Cook - Construction & Infrastructure Law BlogAs of January 1, 2018, direct contractors in California who make or take a contract “for the erection, construction, alteration, or repair of a building, structure, or other private work” are jointly and severally liable with their subcontractors for any unpaid wages, fringe benefits and other benefit payments or contributions owed to wage claimants. Governor Brown approved
AB 1701 on October 14, 2017. The new law puts the onus on direct contractors to not only monitor their own payroll practices, but to ensure that their subcontractors and lower tier subcontractors are engaging in proper payroll practices.
Reprinted courtesy of Sheppard Mullin attorneys
Nora Stilestein,
Candace Matson and
Mercedes Cook
Ms. Stilestein may be contacted at nstilestein@sheppardmullin.com
Ms. Matson may be contacted at cmatson@sheppardmullin.com
Ms. Cook may be contacted at mcook@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
Bert Hummel Appointed Vice Chair of State Bar of Georgia Bench & Bar Committee
October 24, 2021 —
Bert Hummel - Lewis BrisboisAtlanta, Ga. (October 4, 2021) – Atlanta Partner Bert Hummel was recently named Vice Chair of the State Bar of Georgia's Bench & Bar Committee for the 2021-2022 year.
The Bench & Bar Committee identifies and facilitates solutions to issues of mutual interest between State judges and Georgia lawyers for the benefit of the bench, the bar and the public. It also oversees the annual Justice Thomas O. Marshall Professionalism Award, which honors one lawyer and one judge who have demonstrated the highest professional conduct and paramount reputation for professionalism.
Read the court decisionRead the full story...Reprinted courtesy of
Bert Hummel, Lewis BrisboisMr. Hummel may be contacted at
Bert.Hummel@lewisbrisbois.com
Did the Building Boom Lead to a Boom in Construction Defects?
May 10, 2013 —
CDJ STAFFThe height of the building boom is now almost a decade past but some are saying that the results of the rush to get housing built during the profitable market are still with us. The Wall Street Journal reports on the rise of construction defect lawsuits as these homes have aged, some not too gracefully. One couple thought they were hearing acorns falling on their roof. They were less happy to find that the source of the noises was their house slumping on one end, leading to cracks throughout the house. Their neighbors had similar problems and they are now part of a lawsuit against the builder. The expenses to repair the houses could total millions of dollars.
Some have suggested that during the building boom both building and inspection standards were more lax in order to keep up with the pace of building. Criterium Engineers, a building-inspection firm, estimates that 17% of new homes built in 2006 had at least two significant defect, while only 15% of those built in 2003 fit these criteria. Meanwhile others attribute the rise in construction defect lawsuits to home inspector and construction defect attorneys looking for new territories to exploit.
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Supreme Court Hears Insurers’ Bid to Overturn a $400M Decision
January 25, 2021 —
Lawrence J. Bracken II, Michael S. Levine & Daniel Hentschel - Hunton Andrews KurthNew Jersey’s highest court heard arguments Monday in the appeal of a ruling that the New Jersey Transit Corp.’s (“NJ Transit”) insurers are required to insure $400 million of water damage loss caused by Hurricane Sandy.
The matter stems from an insurance claim NJ Transit made after the super storm rocked the East Coast in 2012. NJ Transit claimed over $400 million in losses as a result of damage to its tracks, bridges, tunnels and power stations. In response, its tower of property insurers took the position that a $100 million flood sublimit applied to limit NJ Transit’s recovery under its insurance tower, not the policy’s $400 million overall limits.NJ Transit filed a coverage action in state court. The trial court granted summary judgment to NJ Transit, holding that NJ Transit was entitled to full coverage of $400 million under the tower’s named windstorm coverage. The insurers appealed, again arguing that the flood sublimit applied to the claim.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of