Construction Group Seeks Defense Coverage for Hard Rock Stadium Claims
December 09, 2019 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogIn an insurance coverage action pending in the S.D.N.Y., Hunt Construction Group (Hunt) contends that Berkley Assurance Company wrongfully denied defense coverage for claims arising out of the renovation of Hard Rock Stadium (home to the Miami Dolphins and Miami Hurricanes football teams).
The stadium owner, South Florida Stadium LLC (SFS), hired Hunt to serve as the construction manager for the renovation project. Hunt subcontracted with Alberici Constructors Inc. (Alberici) to design and fabricate roof structures for the stadium.
Hunt and SFS sued Alberici over its work on the project. In March 2017, Alberici asserted counterclaims against Hunt and SFS. In May 2018, SFS sought defense and indemnification from Hunt with respect to Alberici’s coverage claims.
Hunt is insured under claims made and reported professional liability insurance policies issued by Berkley with policy periods from June 15, 2016 to June 15, 2017 (with an automatic extended reporting period through August 14, 2017) and from July 15, 2017 to June 15, 2018. Hunt notified Berkley of Alberici’s counterclaim on July 20, 2017 (within the extended reporting period of the 2016-2017 policy) and of SFS’s indemnity claim on June 5, 2018 (within the 2017-2018 policy period).
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Toronto Skyscraper With $1.2 Billion of Debt Has Been Put in Receivership
November 16, 2023 —
Ari Altstedter - BloombergA landmark condominium project in one of Toronto’s ritziest neighborhoods has been put into receivership after construction delays and cost overruns.
Construction of the 85-story tower will be taken over by a court-appointed receiver after its owners, developer Sam Mizrahi and investor Jenny Coco, defaulted on part of the project’s nearly C$1.7 billion in debt ($1.2 billion), according to a Wednesday order from the Ontario Superior Court of Justice.
Two funds run by South Korea-based IGIS Asset Management Co. applied for the receivership. Another IGIS fund will extend at least another C$315 million to continue work on the project, court documents said.
Read the court decisionRead the full story...Reprinted courtesy of
Ari Altstedter, Bloomberg
UPDATE: Texas Federal Court Permanently Enjoins U.S. Department of Labor “Persuader Rule” Requiring Law Firms and Other Consultants to Disclose Work Performed for Employers on Union Organization Efforts
December 08, 2016 —
Aaron C. Schlesinger & Gregory R. Begg – Peckar & Abramson, P.C.As an update to our prior alert, on November 16, 2016, a federal judge in Texas issued a permanent injunction blocking the U.S. Department of Labor’s (“DOL”) “persuader rule” – a preliminary injunction had been granted this past June.
In rendering the permanent injunction, the court adopted the reasoning of its prior June 27, 2016 decision that granted a nationwide preliminary injunction on the rule. In the earlier decision, the court held that a temporary injunction was appropriate because the parties challenging the rule were likely to succeed on the merits of their claim […].
Reprinted courtesy of
Aaron C. Schlesinger, Peckar & Abramson, P.C. and
Gregory R. Begg, Peckar & Abramson, P.C.
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Mr. Begg may be contacted at gbegg@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Covenant of Good Faith and Fair Dealing Applied to Pass-Through Agreements
June 19, 2023 —
Scott D. Cessar - Construction ExecutivePass-through claims are claims by a party that has suffered damages but does not have a contractual relationship with the entity that caused the damages. In the construction industry, subcontractors commonly have claims for additional costs based on actions or inactions by the owner. However, since the subcontractor is not in privity of contract with the owner, it has no direct cause of action against the owner other than, perhaps, on a nongovernment project, a lien claim. In such cases, subcontractors may seek to pass the claim through the general contractor, who is in privity with the owner, to the owner.
Indeed, many construction contracts require the subcontractor, in such cases of owner-caused damages, to pass the claim through the general contractor to the owner. And since the harm visited on a subcontractor by the owner usually also affected the general contractor, the subcontractor’s claim is packaged together with the general contractor’s claim, which is usually greater, for presentation to the owner and, if not resolved, litigation with the owner.
Reprinted courtesy of
Scott D. Cessar, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Be Careful with Good Faith Payments
February 24, 2020 —
Christopher G. Hill - Construction Law MusingsSometimes doing the expedient thing and what looks good at the time can come back to bite you. Just ask 3M Company.
In Faneuil, Inc. v. 3M Co., the Virginia Supreme Court considered a customer services subcontract between Faneuil and 3M relating to a toll collection contract 3M entered into with ERC. The subcontract had a “pay if paid” clause in it requiring payment to 3M from ERC before ERC was required to pay Faneuil, a written change order provision and a base monthly payment to Faneuil for the services that could be reduced in the event of less than expected toll collections. Further, the subcontract stated that if either party settled 3rd party claims, that settlement would not bind the other party to the subcontract absent consent or Court order.
Faneuil was then alleged to have been required to provide “Special Services” relating to manual identification of license plates and other information necessary for toll billing due to 3M’s alleged failure to provide adequate imaging services. Faneuil requested (without written change order) and 3M promised to pay extra for these services. When 3M was slow to pay for the special services, Faneuil did what you would expect and threatened to stop providing them. Instead of contesting the right to the work, 3m made sporadic “good faith” payments to induce continued Special Services from Faneuil. Eventually 3M’s issues caused ERC to stop payments and thus 3M stopped paying Faneuil. 3M then settled the payment claims with ERC and still failed to pay Faneuil.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Just Because You Allege There Was an Oral Contract Doesn’t Mean You’re Off the Hook for Attorneys’ Fees if you Lose
March 28, 2022 —
Garret Murai - California Construction Law BlogThere’s certain things in life you shouldn’t mix. Like drinking and driving. Bleach and ammonia. Triple dog dares and frozen poles. And angry lawyers and litigation.
In Spahn v. Richards, Case No. A159495 (November 30, 2021), angry lawyer Jeffrey Spahn sued general contractor Dan Richards claiming that Richards orally agreed to build Spahn’s million dollar plus house for $515,000. Not only did Spahn not recover anything from Richards, he ended up owing Richards $239,171 in attorney’s fees and costs, after he denied a request for admission asking that he admit that there was no oral contract.
The Spahn Case
In 2017, Spahn filed suit against Richards for breach of oral contract, breach of implied covenant of good faith and fair dealing, and promissory estoppel. According to Spahn, he met Richards in June 2015 and the two reached an agreement whereby Richards agreed to demolish Spahn’s house for $12,500 and build a new one for $515,000. Further according to Spahn, Richards agreed to this “fixed price” “oral contract” in June 2015, and then, on July 1, 2015, Richards “confirmed and agreed that he would perform the construction project” for $515,000 and would complete construction by May 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Understanding California’s Pure Comparative Negligence Law
November 13, 2023 —
Yaron Shaham - Kahana FeldIn order for a plaintiff to prove a defendant is negligent, the plaintiff must prove the defendant (1) owed a duty to plaintiff, (2) breached that duty, (3) the breach was the actual and proximate cause of plaintiff’s injury, and (4) the resulting monetary damage. However, for both plaintiffs and defendants it is not an all or nothing game in California. This is because California is a pure Comparative Negligence state.
California’s Comparative Negligence law provides that even if a plaintiff is deemed 99% at fault, the plaintiff can still recover 1% in damages from a defendant. Thus, even if a plaintiff is deemed to be more than 50% (or even 99%) at fault for the incident, the plaintiff could still recover some monetary amount, or the defendant will still have to pay plaintiff, depending on how you see it. In most instances, a jury decides what percentage of fault to assign to each party.
Just as a plaintiff must prove he/she/its negligence case against a defendant, if the defendant claims plaintiff was partially responsible for the incident, the defendant must prove plaintiff was also negligent and said negligence contributed to plaintiff’s injuries. The total amount of monetary responsibility distributed among all defendants and plaintiffs must equal 100%. As crazy as it may sound, a plaintiff found to be 99.9% at fault, is still entitled to recover 0.01% from a defendant in California.
Read the court decisionRead the full story...Reprinted courtesy of
Yaron Shaham, Kahana FeldMr. Shaham may be contacted at
yshaham@kahanafeld.com
Policy Sublimit Does Not Apply to Business Interruption Loss
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiRefusing to give the sublimit in a flood policy an expansive reading, the court found that the sublimit did not apply to business interruption loss. Federal-Mogul Corp. v. Ins. Co. of Pa., 2015 U.S. Dist. LEXIS 137394 (E.D. Mich. Oct. 8, 2015).
The insured's facility in Thailand was damaged by flood. The parties stipulated that the insured suffered a loss of $64,500,000, which included $39,406,467 in property damage and $25,093,533 in time element loss (i.e., economic loss due to an inability to operate normally). The insurer paid $30 million, stating that the High Hazard flood zone provision in the policy limited the amount owed under the policy.
The insured argued the High Hazard sublimit applied only to physical loss or damage caused by the flood, and not to time element loss. Therefore, the insured was entitled to judgment on its time element loss claim for $29,093,533. The insurer argued it was entitled to judgment as a matter of law because the High Hazard sublimit applied to all loss caused by flood, including time element loss.
Read the court decisionRead the full story...Reprinted courtesy of