Nevada Senate Rejects Construction Defect Bill
June 07, 2011 —
CDJ STAFFThe Las Vegas Sun reports that Assembly Bill 401, the construction defect bill, lost in a vote of 9 to 12. The measure extended the time for construction defect suits to be filed, awarded legal costs only to successful plaintiffs, and set a definition of construction defects. Two Democrats joined the Republicans in the Senate in defeating the bill.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
When a Request for Equitable Adjustment Should Be Treated as a Claim Under the Contract Disputes Act
August 29, 2022 —
David Adelstein - Florida Construction Legal UpdatesIn federal contracting, contractors are sometimes torn about submitting a request for equitable adjustment (known as an “REA” under 48 C.F.R. 252.243-7002) or submitting a formal claim under the Contract Disputes Act (41 U.S.C. s. 7103), the latter requiring a final decision by the contracting officer and starts the clock with respect to interest and preserving rights. It is also sometimes not easy for the contracting officer receiving an REA to determine whether the REA is actually a claim under the Contract Disputes Act requiring more immediate action. This recent take by the United States Court of Appeals for the Federal Circuit hits the nail on the head:
We recognize that contracting officers will sometimes face the difficult challenge of determining whether a request for equitable adjustment is also a claim. Contractors must choose between submitting a claim—which starts the interest clock but requires the contracting officer to issue a final decision within 60 days—and submitting a mere request for equitable adjustment—which does not start the interest clock but gives the contractor more time to negotiate a settlement and possibly avoid hefty legal fees. The overlap between these two types of documents might create room for gamesmanship. For example, a contractor could submit a document that is a claim—starting the interest clock—but appears to be a mere request for equitable adjustment—causing the contracting officer to not issue a final decision within the 60-day deadline and allowing interest to accrue for months or years. But the government has tools to address this challenge: The contracting officer can communicate to the contractor that she is going to treat the document as a claim and issue a final decision within 60 days. Or the government can explicitly require the contractor to propose settlement terms and attempt to settle disputes before submitting a claim to the contracting officer for a final decision.
Zafer Construction Company v. U.S., 2022 WL 2793596, *5 (Fed.Cir. 2022).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Repeated Use of Defective Fireplace Triggers Duty to Defend Even if Active Fire Does Not Break Out Until After End of Policy Period
November 30, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Tidwell Enterprises v. Financial Pacific Ins. Co. (No. C078665, filed 11/29/16), a California appeals court held that that even though a house fire occurred after the policy period, there was nonetheless a possibility of coverage because the fire might have been the result of ongoing damage to the wood in the chimney chase during the policy period, due to the exposure of that wood to excessive heat from the chimney every time a fire was burned in the fireplace.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Finds That SIR Requirements are Not Incorporated into High Level Excess Policies and That Excess Insurers’ Payment of Defense Costs is Not Conditioned on Actual Liability
April 22, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Deere & Co. v. Allstate Ins. Co. (No. A145170, filed 2/25/19), a California appeals court held that the insured was not required to pay additional self-insured retentions (SIRs) in order to trigger higher level excess coverage because the retained limits applicable to the first layer of coverage did not also apply to the higher-layer excess policies.
In Deere, the insured was sued for injuries from alleged exposure to asbestos-containing assemblies used in Deere machines. In a declaratory relief action against its umbrella and excess insurers, the case was tried on: (1) whether the higher-layer excess policies were triggered once the first-layer excess policy limits, which were subject to an SIR paid by Deere, had been exhausted; and (2) whether the insurers’ indemnity obligation extended to Deere’s defense costs incurred in asbestos claims that had been dismissed. The trial court found in favor of the insurers, concluding that the retained limits in the first layer of coverage also applied to the higher-layer excess, which was not triggered until Deere paid additional SIRs. The court also concluded that the insurers were not obligated to pay defense costs when underlying cases were dismissed without payment to a claimant either by judgment or settlement.
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP Read the court decisionRead the full story...Reprinted courtesy of
Insurer Granted Summary Judgment on Faulty Workmanship Claim
October 20, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court found no coverage for the insured developer after water intruded into the homeowners' basements. W. Bend Mut. Ins. Co. v. Cleland Homes, 2016 U.S. Dist. LEXIS 108030 (N.D. Ind. Aug. 16, 2016).
The underlying complaint alleged that the subdivision was designed to create a run off of ground water onto the lots where Cleland built plaintiffs' homes. The design of the subdivision and construction of the homes was defective in that the plaintiffs' homes were situated so that the water table underneath their homes was so high that their basements flooded and damage occurred to the structure of their homes. Cleland was allegedly negligent in designing and/or constructing the homes or negligent in the water drainage plan for the subdivision.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Recent Developments Involving Cedell v. Farmers Insurance Company of Washington
September 05, 2022 —
Donald Verfurth, Sally Kim, Stephanie Ries & Kyle Silk-Eglit - Gordon & Rees Insurance Coverage Law BlogEver since the Washington Supreme Court’s 2013 decision in Cedell v. Farmers Insurance Company of Washington, 176 Wn.2d 686, 295 P.3d 239 (2013), insurance coverage attorneys have been struggling to define the exact parameters of the Cedell ruling in order to safeguard the attorney-client privilege as to the communications between the insurer and its counsel. As a brief background, the Washington Supreme Court held in Cedell that there is a presumption of no attorney-client privilege in a lawsuit involving bad faith claims handling. However, an insurer can overcome the presumption of no attorney-client privilege by showing that its counsel provided legal advice regarding the insurer’s potential liability under the policy and law, and did not engage in any quasi-fiduciary activities, i.e. claims handling activities, such as investigating, evaluating, adjusting or processing the insured’s claim.
Since Cedell, various trial courts have held that the following activities by an insurer’s counsel constitute quasi-fiduciary conduct that do not overcome the presumption of no attorney-client privilege, resulting in an order to produce documents and/or to permit the deposition of the insurer’s counsel:
- Insurer’s attorney being the primary or sole point of contact with the insured for the insurer;
- Insurer’s attorney requesting documents from the insured that are relevant to the investigation of the claim;
- Insurer’s attorney communicating directly with the insured or the insured’s counsel regarding claims handling issues or payments;
- Insurer’s attorney interviewing witnesses for purposes of the investigation of the claim;
- Insurer’s attorney conducting an examination under oath of the insured;
- Insurer’s attorney drafting proposed or final reservation of rights letter or denial letter to the insured; and
- Insurer’s attorney conducting settlement negotiations in an underlying litigation.
Reprinted courtesy of
Donald Verfurth, Gordon Rees Scully Mansukhani,
Sally Kim, Gordon Rees Scully Mansukhani,
Stephanie Ries, Gordon Rees Scully Mansukhani and
Kyle Silk-Eglit, Gordon Rees Scully Mansukhani
Mr. Verfurth may be contacted at dverfurth@grsm.com
Ms. Kim may be contacted at sallykim@grsm.com
Ms. Ries may be contacted at sries@grsm.com
Mr. Silk-Eglit may be contacted at ksilkeglit@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Finding Plaintiff Intentionally Spoliated Evidence, the Northern District of Indiana Imposes Sanction
March 14, 2018 —
Shannon M. Warren – The Subrogation Strategist On January 23, 2018, the Northern District of Indiana issued a decision that clarifies what constitutes spoliation of evidence under Indiana law. In
Arcelormittal Ind. Harbor LLC v. Amex Nooter, LLC, 2018 U.S. Dist. LEXIS 10141 (N.D. Ind.), the defendant filed a motion for sanctions, alleging that the plaintiff intentionally spoliated critical evidence. The defendant sought dismissal of the action, asserting that the plaintiff intentionally discarded and lost important physical evidence within hours of a fire that occurred while the defendant’s employees were performing work at its facility. The decision underscores the importance of taking immediate action to properly identify and secure potentially material evidence in order to satisfy ones duty to preserve pre-suit evidence and avoid any spoliation defenses and associated sanctions.
In
Arcelormittal, the court initially considered whether to apply state or federal law when analyzing a litigant’s duty to preserve pre-suit evidence and determine if that party committed spoliation. Since the case was brought in federal court based on diversity jurisdiction, the court held that Indiana state law governed the spoliation analysis.
As noted by the court, under Indiana state law, “the intentional destruction, mutilation, altercation, or concealment of evidence” is considered to be spoliation. Thus, under Indiana law, a party who knew or should have known that litigation was imminent “may not lose, destroy or suppress material facts or evidence.” The plaintiff argued that Indiana law requires a showing of improper purpose or bad faith to establish that a litigant spoliated evidence. The
Arcelormittal court rejected the plaintiff’s argument.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and Williams LLPMs. Warren may be contacted at
warrens@whiteandwilliams.com
Colorado’s Need for Condos May Spark Construction Defect Law Reform
January 29, 2014 —
Beverley BevenFlorez-CDJ STAFFOn January 6th, Ed Sealover of the Denver Business Journal reported that Denver Mayor Michael Hancock has asked Colorado legislators “to pass a reform law that will make it easier to build condos without fear of getting sued.” Hancock is one of several mayors “to advocate for a construction defects reform proposal that was killed by Democrats in a committee last year.”
The problem, Sealover notes, is that only “2 percent of new housing in the state is multifamily units made for ownership—far lower than the 20 to 25 percent of such housing stock in other states represented by condos.”
There is some dissent as to whether reforming construction defect laws is the solution to the housing problem: “Taking away rights of homeowners to get shoddy construction fixed in what is likely the most expensive purchase in their life is not the way to fix the lack of affordable housing,” Lynea Hansen, spokeswoman for a group of construction defect homeowners told Sealover.
Furthermore, on January 7th, Sealover reported that Democrats “expressed skepticism” about a need to reform the laws, saying “they need more data on what is causing owner-occupied multifamily housing to be such a small part of the new housing market.” Moreover, Senate President-elect Morgan Carroll stated that she “wants to look into issues like why it is so hard to get insurance for building condominiums or examine why some areas of Colorado are seeing condo development and others aren’t.”
Read the full story, January 6th article...
Read the full story, January 7th article... Read the court decisionRead the full story...Reprinted courtesy of