Did You Really Accept That Bid? – How Contractors Can Avoid Post-Acceptance Bid Disputes Over Contract Terms
July 28, 2016 —
David A. Harris & Steven M. Cvitanovic – Haight Brown & Bonesteel LLPWhen California general contractors submit bids to an owner, can they force their subcontractors to honor their bids? Can they recover damages if the subcontractor later refuses to do so?
While the general rule in California is that a general contractor who reasonably relies on a subcontractor’s bid may recover damages when the subcontractor reneges, the Court of Appeal for the Second Appellate District recently held that there is a substantial and important exception to the general rule.
In Flintco Pacific, Inc. v. TEC Management Consultants, Inc. (LASC No. YC067984), the Court of Appeal held that where a general contractor requires a subcontractor to enter into a “standard-form subcontract” which materially differs from the subcontractor’s bid, the general contractor has rejected the subcontractor’s bid and has instead issued a counteroffer. The subcontractor is thereafter free to walk, or accept the new terms. If the subcontractor walks, the general contractor may not seek to enforce the terms of the subcontract or seek reliance damages.
Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLP and
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP
Mr. Harris may be contacted at dharris@hbblaw.com
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Seyfarth Shaw’s Construction Group Receives Top Tier Recognition from Legal 500
July 05, 2023 —
Alison Ashford, Michael McKeeman, Bennett Greenberg, Meghan Douris, Jason Smith, Michael Wagner & Ryan Gilchrist - The Construction SeyfarthSeyfarth Shaw’s Construction group have achieved a top tier ranking in the highly regarded
Legal 500 United States 2023 edition, solidifying their reputation as one of the nation’s top legal teams. This recognition reaffirms Seyfarth’s unwavering commitment to excellence in Real Estate Construction and Construction Litigation.
The Legal 500 United States guide recognizes Seyfarth’s Construction practice as having a “very deep team with extensive construction knowledge as well as experts in related fields such as government contracting and business organization.” Our team is regarded by clients and peers as “collegial, intelligent, direct and adaptable.” The guide specifically recognizes the firm’s former Construction group chair, Bennett Greenberg, in their Hall of Fame. Alison Ashford, the firm’s current Construction group co-chair, is named a Leading Lawyer and Washington, DC Associate, Michael Wagner, made the Rising Stars list. Other notable mentions include, Michael McKeeman, Construction group co-chair, Jason Smith, Meghan Douris, and Ryan Gilchrist.
Reprinted courtesy of
Alison Ashford, Seyfarth,
Michael McKeeman, Seyfarth,
Bennett Greenberg, Seyfarth,
Meghan Douris, Seyfarth,
Jason Smith, Seyfarth,
Michael Wagner, Seyfarth and
Ryan Gilchrist, Seyfarth
Ms. Ashford may be contacted at aashford@seyfarth.com
Mr. McKeeman may be contacted at mmckeeman@seyfarth.com
Mr. Greenberg may be contacted at bgreenberg@seyfarth.com
Ms. Douris may be contacted at mdouris@seyfarth.com
Mr. Smith may be contacted at jnsmith@seyfarth.com
Mr. Wagner may be contacted at mewagner@seyfarth.com
Mr. Gilchrist may be contacted at rgilchrist@seyfarth.com
Read the court decisionRead the full story...Reprinted courtesy of
Corrective Action Protest Grounds for GSA Schedule Federal Construction Contractors
September 09, 2024 —
Marissa L. Downs - The Dispute ResolverA contract awarded, protested, terminated, appealed, then reinstated. It’s no secret that federal construction procurements are plagued with uncertainty. From delays, constructive suspensions, compromised supply chains, the litigation-laden critical path method, and the mandate for all construction materials used in federally funded projects for infrastructure to be produced in the United States under the Build America, Buy America Act (BABAA) (to name just a few traditional and emerging favorites), just one of these issues could fill the rest of anyone’s month with substantive research. To add one more, which is entirely unique to bid protests, federal contractors–including construction contractors–listed in a General Service Administration (GSA) Schedule may have new grounds to have a contract award reinstated that was terminated by a federal agency pending a GAO decision.
GAO Protest
An initial GAO protest filed by Deloitte & Touche LLP (Deloitte) argued that the National Geo-Spatial Intelligence Agency (Agency) wrongfully made an award to Kearney & Company, P.C. (Kearney) when the Agency: (1) improperly evaluated quotes; and (2) failed to conduct a proper best-value tradeoff analysis. At issue was a competed task order with Kearney under a GSA FSS multiple-award contract. Before the GAO issued an opinion, however, it held an unrecorded predictive-outcome conference with Deloitte and Kearney where the only mutual consensus was the likely ineligibility of all offerors for the relevant award. The Agency subsequently elected to take corrective action, terminating Kearney’s contract award for convenience, amending the solicitation to avoid issues (including undisputed issues) addressed in the GAO protest. After the Agency adopted their corrective action, the GAO protest was dismissed as academic and moot.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Hurricane Laura: Implications for Insurers in Louisiana
October 19, 2020 —
Jennifer Michel & Tabitha Durbin - Lewis BrisboisJust two days before the 15th Anniversary of Hurricane Katrina, Category 4 Hurricane Laura made landfall near Cameron, Louisiana. Although the “unsurvivable” 20-foot storm surge, which had been predicted ahead of the storm, thankfully was significantly less, the impact of Laura on the Southwest Coast of Louisiana and Southeast Coast of Texas and its neighboring parishes and counties, most notably Cameron Parish, was quite severe. Lake Charles, Louisiana suffered widespread flooding and sustained catastrophic wind damage. Although the storm moved quickly, it retained its strength longer than expected such that even areas well inland sustained considerable damage. Preliminary estimates for insured losses from storm surge, flooding, and winds range from $8 to $12 billion for residential and commercial properties. Insurers providing residential or commercial property insurance in Louisiana should keep the following statutory claims handling requirements in mind.
Louisiana Statutory Provisions
Under Louisiana law, an insurer is expected to comply with certain statutory requirements in investigating and handling claims submitted by its insureds and third-party claimants. The majority of these requirements, and the consequences of their violation, are codified by La. R.S. 22:1892, which governs the payment and adjustment of claims, and La. R.S. 22:1973, which delineates an insurer’s duty of good faith. Together, the statutes impose three requirements on insurers: timely initiation of loss adjustment, timely payment of claims, and a duty of good faith and fairness in the adjustment and payment of said claims.
Reprinted courtesy of
Jennifer Michel, Lewis Brisbois and
Tabitha Durbin, Lewis Brisbois
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Ms. Durbin may be contacted at Tabitha.Durbin@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado General Assembly Sets Forth Prerequisites for an Insurance Company to Use Failure to Cooperate as a Defense to a Claim for First Party Insurance Benefits
August 10, 2020 —
Christine Kroupa, John Palmeri & Katelyn Werner - Gordon & ReesDespite first party insurance policies generally requiring cooperation from an insured in the investigation of a claim, insurers can no longer rely on the failure to cooperate as a defense in a claim for first party insurance benefits in Colorado unless certain conditions are met.
The Bill:
On July 2, 2020, Colorado Governor Jared S. Polis signed House Bill 20-1290 which addresses the ability of an insurer to use a failure to cooperate defense in an action where the insured has made a claim for benefits under an insurance policy. This bill bars an insurer from raising the failure to cooperate unless the following conditions are met:
- The insurer submitted a written request to the insured or the insured’s representative for the information (via electronic means if consent was given by insured or insured’s representative, or via certified mail);
- The information is not available to the insurer without the assistance of the insured;
- The written request provides the insured 60 days to respond;
- The written request is for information a reasonable person would determine the insurer needs to adjust the claim filed by the insured or to prevent fraud; and
- The insurer gives the insured an opportunity to cure, which must:
- Provide written notice to the insured of the alleged failure to cooperate, describing with particularity the alleged failure within 60 days after the alleged failure; and
- Allow the insured 60 days after receipt of the written notice to cure the alleged failure to cooperate.
Reprinted courtesy of Gordon & Rees attorneys
Christine Kroupa,
John Palmeri and
Katelyn Werner
Ms. Kroupa may be contacted at ckroupa@grsm.com
Mr. Palmeri may be contacted at jpalmeri@grsm.com
Ms. Werner may be contacted at kwerner@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
North Carolina Weakened Its Building Codes in 2013
October 09, 2018 —
Ari Natter - BloombergFive years ago, encouraged by home builders and an anti-regulatory zeal, lawmakers in North Carolina joined other states in weakening building code requirements.
It’s a decision they may regret as Hurricane Florence takes aim at the Carolinas.
The Legislature in 2013 increased the amount of time between updates to its building code from three years to six. That means that updates that set new standards for elevating the floors in flood-prone homes aren’t in effect, according to the Federal Alliance for Safe Homes Inc., a non-profit disaster safety organization.
Read the court decisionRead the full story...Reprinted courtesy of
Ari Natter, Bloomberg
Quick Note: Staying, Not Dismissing, Arbitrable Disputes Under Federal Arbitration Act
July 31, 2024 —
David Adelstein - Florida Construction Legal UpdatesAs you hopefully know from posted articles, arbitration is a creature of contract. Stated differently, there must be a contractual basis to have a dispute resolved through binding arbitration. The Federal Arbitration Act (FAA) applies to transactions involving interstate commerce. Oftentimes, lawsuits are filed despite an arbitration provision in a contract because parties can, if they desire, waive their rights to have their dispute resolved through binding arbitration.
In what should not be a shocker, the United States Supreme Court in Smith v. Spizzirri, 144 S.Ct. 1173, 1178 (2024), held that when a federal “district court finds that a lawsuit involves an arbitrable dispute, and a party requests a stay pending arbitration, section 3 of the FAA compels the court to stay the proceeding.” Dismissing the lawsuit should not be the option. Staying the lawsuit should.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New York Restaurant and Bar Fire Caused by Electric Defect
February 04, 2014 —
Beverley BevenFlorez-CDJ STAFFA fire at McGill’s Restaurant and Bar located in Schuyler, New York, resulted in “a total loss” according to the Little Fall Times. Schuyler Fire Chief Don Kane told the Little Fall Times, “no one was inside the building at the time of the fire, as the bar had closed at 2:30 a.m.” and the fire was reported at 3:52 a.m. Weather hindered the firefighters abilities to deal with the situation as “a small squall moved through the area.”
An investigation concluded that an “electrical malfunction is to blame,” reported the Utica Observer-Dispatch. The Herkimer County Office of Emergency Services stated that the “fire was caused by an electrical defect within the base of the front wall.”
The restaurant owner, who leased the building, “did not carry fire loss insurance for his business,” though the “building owner was insured,” according to the Utica Observer-Dispatch.
Read the full story at The Little Falls Times...
Read the full story at The Utica Observer-Dispatch... Read the court decisionRead the full story...Reprinted courtesy of