Revisiting Statutory Offers to Compromise
August 28, 2023 —
Kathryne Baldwin - Wilke FleuryThe fourth appellate district published an opinion earlier this year in Smalley v. Subaru of America, Inc. (2022) 87 Cal.App.5th 450 that serves as an excellent refresher on requirements of the “998 Offer,” or a statutory offer to compromise pursuant to Code of Civil Procedure (“CCP”) §998.
In Smalley, set in the context of a Lemon Law action, Defendant Subaru made a 998 Offer for $35,001.00, together with attorneys’ fees and costs totaling either $10,000.00 or costs and reasonably incurred attorneys’ fees, in an amount to be determined by the Court. (Smalley, supra, 87 Cal.App.5th at 454.) Plaintiff objected that the offer was not reasonable and the case proceeded to trial. At trial, a jury found in favor of Plaintiff and awarded him a total judgment award of $27,555.74 – far short of the $35,001.00 offer. The trial court found Plaintiff had failed to beat the 998 at trial and that Subaru’s earlier 998 offer was reasonable. Plaintiff appealed the post-judgment order awarding Plaintiff pre-offer costs and Defendant post-offer costs on the grounds that the 998 was not reasonable in that it did not specify whether Plaintiff would be deemed the prevailing party for purposes of a motion for attorneys’ fees. The fourth district affirmed the trial court’s order and engaged in a helpful review of 998 requirements.
Read the court decisionRead the full story...Reprinted courtesy of
Kathryne Baldwin, Wilke FleuryMs. Baldwin may be contacted at
kbaldwin@wilkefleury.com
Duuers: Better Proposals with Less Work
July 21, 2018 —
Aarni Heiskanen - AEC BusinessSmall contractors, consultants, and design professionals have a love–hate relationship with responding to RFPs. Duuers, a Finnish startup, wants to turn this struggle into an inspiring experience.
“We followed a day in the life of a hand-picked group of entrepreneurs,” says Paula Viinamäki, co-founder of Duuers. “We were flies on the wall, observing how small business owners wrestle with their daily tasks. Proposal-writing seemed to be an especially painful and time-consuming, yet vital, job.”
Defining the Scope through Experiments
After discovering this poorly supported but essential job that had to be done, Viinamäki and Jussi Paanajärvi, the other co-founder of Duuers, realized that they might be onto something. Consequently, they decided to start working on a prototype app for proposal-writing in the spring of 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Contractor Succeeds At the Supreme Court Against Public Owner – Obtaining Fee Award and Determination The City Acted In Bad Faith
September 20, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCA contractor won a rare but much-deserved victory at the Supreme Court on July 8, 2021 in Conway Construction Co. v. City of Puyallup, 197 Wn.2d 825, 490 P.2d 221 (2021). The case, which involved an aggressive stance by a public owner:
- confirmed that the public owner bears the burden of demonstrating a termination for default is justified,
- reaffirmed the requirement to provide an opportunity to cure, and
- rejected the public owner’s attempts to escape its own contract language that the contractor relied upon.
John Ahlers and Lindsay Watkins of Ahlers Cressman and Sleight and Jamie Becker of Osborne Construction submitted the Amicus Brief for the Associated General Contractors (AGC) of Washington in support of Conway to the Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com
Hunton Insurance Partner Syed Ahmad Serves as Chair of the ABA Minority Trial Lawyer Committee’s Programming Subcommittee
January 13, 2020 —
Michelle M. Spatz - Hunton Insurance Recovery BlogSyed Ahmad, a partner in Hunton Andrews Kurth’s Insurance Coverage practice, has volunteered to serve as Chair of the
ABA Minority Trial Lawyer Committee’s Programming Subcommittee. The Minority Trial Lawyer Committee (MTL) serves as a resource for minority litigators, in-house counsel and law students, aiming to foster professional development, legal scholarship, advocacy and community involvement. As Chair of the Programming Subcommittee, Syed, who was named to Benchmark Litigation’s 40 & Under Hot List earlier this year, will help advance MTL’s mission of facilitating discussions about diversity and the law and providing career network opportunities for minority trial lawyers.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle M. Spatz, Hunton Andrews KurthMs. Spatz may be contacted at
mspatz@HuntonAK.com
Avoid a Derailed Settlement in Construction
March 28, 2022 —
Patrick Barthet - Construction ExecutiveMore and more construction cases are settling because lawyers know juries can prove to be unpredictable. The litigation process, as well as any actual trial, can be stressful, expensive and quite lengthy. Settlements are, for the most part, private while suits are public. Current reports find more than 90% of civil cases filed in state circuit courts are disposed of before trial. When that doesn't happen, things could go very poorly, as the case below illustrates.
The Case
Adam was seriously injured in a collision with a dump truck owned by Bang and driven by Tomas. While suit by Adam against Bang and Tomas was pending, Adam suggested they settle by having Bang pay him. Upon receipt of the offer, Bang's lawyer reached out confirming that his client was okay with the settlement amount but wished to add that the settlement also include the satisfaction of a lien filed by Adam's workers' compensation carrier. Adam's attorney refused that additional request, but that didn't stop Bang's lawyer. Based on the fact that Adam had agreed to the settlement amount, the lawyer filed a boiler plate notice of acceptance of settlement and had Bang issue a settlement check payable to Adam in the amount Adam had requested. Adam remained unwilling to compromise. He continued to resist the modified terms, which added satisfaction of the worker’s compensation lien. Bang then filed a motion to enforce settlement, arguing that since there was agreement on the settlement amount, Adam was required to do the deal.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
L.A.’s Modest Solution to the ‘Missing Middle’ Housing Problem
May 24, 2021 —
Kriston Capps - BloombergPractical ideas aren’t often the stuff of architecture contests. Right off the bat, that set Los Angeles’s Low-Rise design challenge apart.
A project led by the mayor’s office and the city’s chief design officer, Christopher Hawthorne, Low-Rise asked entrants to reimagine what an L.A. urban landscape with abundant housing could look like in the years to come. The organizers wanted the participating designers to think about their submissions the way they might approach a project for a local client or community. The results, which were unveiled this week, don’t look like future-forward science fiction, but rather doable local solutions to a thorny problem: the stubborn lack of affordable options across the city.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Risk Protection: Force Majeure Agreements Take on Renewed Relevance
November 30, 2020 —
Michael E. Carson - Construction ExecutiveForce majeure clauses have been standard in contracts dating back hundreds of years in the United States—and even longer in Europe. “Force majeure,” which is French for “greater force,” removes liability for unforeseen events that prevent parties from fulfilling contractual obligations.
In a year defined by the COVID-19 pandemic, these clauses have gone from boilerplate basics to something worthy of further examination and attention in order to minimize risk for all parties involved in a construction project. Prior to COVID-19, drafters might have considered a localized or regional event that would lead to invoking a force majeure clause. It is doubtful, however, that anybody envisioned the impact on such a world-wide scale.
UNDERSTANDING THE AGREEMENTS
Force majeure clauses cover unforeseen events, a broad term that encompasses both acts of God and human-caused incidents. These range from natural disasters like earthquakes and hurricanes to acts of terrorism, strikes, political strife, government actions, war and other difficult- or impossible-to-predict disruptions. When such an event occurs, the force majeure clause attempts to remove, or at least reduce, uncertainty as to the rights and liabilities of the parties to the agreement.
Reprinted courtesy of
Michael E. Carson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Carson may be contacted at
michael.carson@nationwide.com
The End of Eroding Limits Policies in Nevada is Just the Beginning
August 28, 2023 —
Payne & Fears LLPOn June 3, 2023, Nevada Gov. Joe Lombardo signed into law
AB 398 (the Act) which modifies the Nevada insurance code by restricting the types of liability policies that can be offered in the state.
The End of Eroding Limits Policies in Nevada
First, the Act prohibits liability insurers from issuing “eroding limits” or “burning limits” policies. These are insurance policies under which defense costs decrease policy limits. Most professional liability policies are eroding limits policies. As of Oct. 1, 2023, insurers in Nevada may no longer issue or renew any policy where policy limits are eroded by defense costs.
This change may result in higher premiums on these types of policies to compensate for the higher payouts they will now have to provide in Nevada.