Sinking Buildings on the Rise?
July 01, 2019 —
Jason M. Adams - Gibbs GidenBy now everyone in the construction and insurance industries is familiar with the 58-story Millennium Tower building in San Francisco that has sunk 17 inches and tilted another 14 inches to the northwest. Another recent New York lawsuit alleges that a 58-story luxury Manhattan condo high-rise is also sinking and causing significant damage. With construction booming in the Southeast and other areas with questionable soils, sinking building cases may be on the rise. Given this reality, the issue of subsidence should be of paramount importance to every construction and insurance professional when insuring a project.
Most insurance carriers will include a subsidence and/or other earth movement exclusion on a commercial general liability ("CGL") quote for insurance as a matter of course. Construction professionals (owners/developers, general contractors, and subcontractors) or their brokers may be under the mistaken impression that they have no choice but to accept these subsidence exclusions as part of a standard construction policy. This is not the case. To the contrary, most insurance carriers are willing to remove subsidence exclusions if the underwriters are provided with acceptable geotechnical/soils reports when considering the project.
The insured construction professional often pushes back on the insurance carrier's request for soils reports because the insured sees the request as an unnecessary hassle, expense or unwelcome interference in the job. However, the carrier's soils review is designed to benefit everyone. If potential soils issues are discovered during the underwriting process they can be addressed at the outset of the project rather than after the project is built, which will typically cost substantially more to remedy. Moreover, a thorough analysis of the condition of the soils at the outset of the project allows the risk management team to recognize any potential issues and ensure that the proper coverage is obtained in order to provide protection down the road. Even if the insurance carrier charges more money to sign off on questionable soils after a review of the reports, the slight increase in premium is likely a worthwhile investment in the event of a subsidence loss.
The lesson is that the insured should not blindly accept a subsidence exclusion and should negotiate its removal. The insured should provide its broker and the insurance carrier the information they need in order to make a fully-informed decision as it pertains to the soils. Once the insurance carrier has had the opportunity to review and sign off on the condition of the soil, the carrier should feel comfortable enough to remove any subsidence exclusions or other similar earth movement limitations.
Subsidence is a relatively straightforward issue to deal with as long as the project team’s lawyers, brokers, risk managers and insurance company underwriters are working together toward the common goal of properly evaluating the risk and adequately insuring the project. This simple cooperative process between the entire risk management team could mean the difference between being covered or not covered in the event of a loss related to earth movement.
Jason M. Adams, Esq. is Senior Counsel at Gibbs Giden representing construction professionals (owners/developers, contractors, architects, etc.) in the areas of Construction Law, Insurance Law and Risk Management, Common Interest Community Law (HOA) and Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms. Mr. Adams can be reached at jadams@gibbsgiden.com.
The content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settlements, and does not constitute legal advice. Do not act on the information contained herein without seeking the advice of licensed counsel. The transmission of information by email, or any transmission or exchange of information over the Internet, or by any of the included links is not intended to create and does not constitute an attorney-client relationship. This publication may not be reproduced or used in whole or in part without written consent of the author. Copyright 2019 ©
Read the court decisionRead the full story...Reprinted courtesy of
Wisconsin Supreme Court Abandons "Integrated Systems Analysis" for Determining Property Damage
September 12, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe Wisconsin Supreme Court departed from its previous mechanism for determining property damage under the "integrated systems analysis" and found the insurers were not entitled to summary judgment as determined by the trial court. 5 Walworth, LLC v. Engerman Contracting, Inc., 2023 Wis. LEXIS 152 (Wis. June 20, 2023).
5 Walworth LLC hired Engerman as general contractor to construct a swimming pool complex. Engerman subcontracted with Downes Swimming Pool Co., Inc. to construct the pool complex. Otto Jacobs supplied Downes with a ready-mixed concrete called shotcrete, commonly used in swimming poll construction.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Haight Welcomes New Attorneys to Los Angeles, Sacramento and San Francisco
October 07, 2019 —
Haight Brown & BonesteelHaight Brown & Bonesteel is happy to announce the addition of new attorneys to our Los Angeles, Sacramento and San Francisco offices.
- Alexandra Angel – Los Angeles: Alexandra is a member of the firm’s Business Solutions, General Liability and Transportation Law Practice Groups. Her practice focuses on a variety of civil litigation matters involving premises liability, personal injury, judgment collection, breach of contract, and landlord-tenant. Her clients have included individual private clients, international property management companies, national and local real estate investment companies, a large car finance company, and local businesses.
- Josh Maltzer – San Francisco: Josh is a partner in the firm’s Construction Law, General Liability and Risk Management & Insurance Law Practice Groups. He is a seasoned civil litigator who focuses his practice on construction defect, general liability and insurance coverage. Josh is an experienced trial attorney who has litigated matters in state and federal courts throughout California and in Arizona, Washington and Wyoming. He has represented business owners, property managers, developers, real estate purchasers and public housing agencies in matters that resulted in millions of dollars in insurance recovers, judgments and settlements for his client.
Reprinted courtesy of Haight Brown & Bonesteel attorneys
Alexandra Angel,
Josh A. Maltzer,
Philip E. McDermott,
Patrick F. McIntyre,
Evan M. Reese, and
Amanda F. Riley
Ms. Angel may be contacted at aangel@hbblaw.com
Mr. Maltzer may be contacted at jmaltzer@hbblaw.com
Mr. McDermott may be contacted at pmcdermott@hbblaw.com
Mr. McIntyre may be contacted at pmcintyre@hbblaw.com
Mr. Reese may be contacted at ereese@hbblaw.com
Ms. Riley may be contacted at ariley@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Unable to Declare its Coverage Excess In Construction Defect Case
January 06, 2012 —
CDJ STAFFThe Ninth Circuit Court of Appeals has upheld a summary judgment in the case of American Family Mutual Insurance Co. v. National Fire & Marine Insurance Co. Several other insurance companies were party to this case. In the earlier case, the US District Court of Appeals for Arizona had granted a summary judgment to Ohio Casualty Group and National Fire & Marine Insurance Company. At the heart of it, is a dispute over construction defect coverage.
The general contractor for Astragal Luxury Villas, GFTDC, contracted with American Family to provide it with a commercial liability policy. Coverage was issued to various subcontractors by Ohio Casualty and National Fire. These policies included blanket additional insured endorsements that provided coverage to GFTDC. The subcontractor policies had provisions making their coverage excess over other policies available to GFTDC.
The need for insurance was triggered when the Astragal Condominium Unit Owners Association filed a construction defect claim in the Arizona Superior Court. CFTDC filed a third-party claim against several subcontractors. The case was settled with American Family paying the settlement, after which it filed seeking reimbursement from the subcontractor’s insurers. The court instead granted summary judgment in favor of Ohio Casualty and National Fire.
American Family appealed to the Ninth Circuit for a review of the summary judgment, arguing that the “other insurance” clauses were “mutually repugnant and unenforceable.” The Ninth Circuit cited a case from the Arizona Court of Appeals that held that “where two policies cover the same occurrence and both contain ‘other insurance’ clauses, the excess insurance provisions are mutually repugnant and must be disregarded. Each insurer is then liable for a pro rate share of the settlement or judgment.”
The court noted that unlike other “other insurance” cases, the American Family policy “states that it provides primary CGL coverage for CFTDC and is rendered excess only if there is ‘any other primary insurance’ available to GFTDC as an additional insured.” They note that “the American Family policy purports to convert from primary to excess coverage only if CFTDC has access to other primary insurance as an additional insured.”
In comparison, the court noted that “the ‘other insurance’ language in Ohio Casualty’s additional insured endorsement cannot reasonably be read to contradict, or otherwise be inconsistent with, the ‘other primary insurance’ provision in the American Family policy.” They find other reasons why National Fire’s coverage did not supersede American Family’s. In this case, the policy is “written explicitly to apply in excess.”
Finally, the Astragal settlement did not exhaust American Family’s coverage, so they were obligated to pay out the full amount. The court upheld the summary dismissal of American Family’s claims.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
California Court of Appeals Says, “We Like Eich(leay)!”
March 30, 2016 —
Garret Murai – California Construction Law BlogTime is money.
And nowhere can than be best observed than on a construction project.
Project delays can mean lost profits for owners, liquidated damages for general contractors, and increased material, labor, field overhead, and home office overhead costs for general contractors and subcontractors alike.
Pricing the impact of delays, however, can be thorny. Particularly, for home office overhead.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
How the Jury Divided $112M in Seattle Crane Collapse Damages
April 04, 2022 —
Richard Korman - Engineering News-RecordThe jury verdict in a wrongful death lawsuit against companies involved in a 2019 Seattle crane collapse that killed four people split damages among three different companies—and also blamed a fourth firm that wasn't a defendant—but not in a way that matched the state safety fines proposed against the firms.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Thank You Once Again for the Legal Elite Election for 2022
December 18, 2022 —
Christopher G. Hill - Construction Law MusingsThank you once again to those in the Virginia legal community who elected me to the Virginia Business Legal Elite in the Construction Law category for the 16th consecutive year. The 16 consecutive years of election to the Legal Elite in the Construction Category span my time as a solo construction attorney. The fact that you all have continued to elect “100%” of the lawyers at The Law Office of Christopher G. Hill, PC for the last 12 years is most gratifying and only confirms that my decision to “go solo” over 12 years ago was a good one. To be included in this list of top construction attorneys is both humbling and gratifying. For the complete list of the Virginia construction lawyers that were elected along with me, see the
2022 Virginia Business Legal Elite in Construction Law.
So without further ado, thank you to all of you who voted for me. I truly appreciate your continued confidence and support of my construction law practice. Your yearly votes always prod me to learn and continually improve to meet your expectations and keep my practice at this high level. I also couldn’t do this without the great support from friends and family (not to mention clients), so my gratitude goes out to these great folks.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Enforcement Of Contractual Terms (E.G., Flow-Down, Field Verification, Shop Drawing Approval, And No-Damage-For-Delay Provisions)
May 04, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhat you contractually agree to matters, particularly when you are deemed a sophisticated entity. This means you can figuratively live or die by the terms and conditions agreed to. Don’t take it from me, but it take it from the Fourth Circuit’s decision in U.S. f/u/b/o Modern Mosaic, Ltd. v. Turner Construction Co., 2019 WL 7174550 (4th Cir. 2019), where the Court started off by stressing, “One of our country’s bedrock principles is the freedom of individuals and entities to enter into contracts and rely that their terms will be enforced.” Id. at *1.
This case involved a dispute between a prime contractor and its precast concrete subcontractor on a federal project. The subcontractor filed a Miller Act payment bond lawsuit. The trial court ruled against the subcontractor based on…the subcontract’s terms! So, yes, what you contractually agree to matters.
Example #1 – The subcontractor fabricated and installed precast concrete panels per engineering drawings. However, the parking garage was not built per dimensions meaning the panels it fabricated would not fit. The subcontractor had to perform remedial work on the panels to get them to fit. The subcontractor pursued the prime contractor for these costs arguing the prime contractor should have field verified the dimensions. The problem for the subcontractor, however, was that the subcontract required the subcontractor, not the prime contractor, to field verify the dimensions. Based on this language that required the subcontractor to field verify existing conditions and take field measurements, the subcontractor was not entitled to its remedial costs (and they were close to $1 Million). Furthermore, and of importance, the Court noted that the subcontract contained a flow down provision requiring the subcontractor to be bound by all of the terms and conditions of the prime contract and assume those duties and obligations that the prime contractor was to assume towards the owner. While this flow-down provision may often be overlooked, here it was not, as it meant the subcontractor was assuming the field verification duties that the prime contractor was responsible to perform for the owner.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com