You Don’t Have To Be a Consumer to Assert a FDUTPA Claim
February 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesA few years ago, the Fourth District Court of Florida rendered an opinion in
Caribbean Cruise Line, Inc. v. Better Business Bureau of Palm Beach County, Inc., 169 So.3d 164 (Fla. 4th DCA 2015) regarding
Florida’s Deceptive and Unfair Trade Practices Act (referred as to “FDUTPA”) (Florida Statute s. 501.201et seq.).
This case held that a party can assert a FDUTPA claim even though the party is NOT a consumer. The party still has to prove there was an injury to consumers in filing such claim, but again, the party can bring the claim even though it is NOT a consumer. Caribbean Cruise Line, 169 So.3d at 169 (“[W]hile the claimant would have to prove that there was an injury or detriment to consumers in order to satisfy all of the elements of a FDUTPA claim, the claimant does not have to be a consumer to bring the claim.”).
See also Cemex Construction Materials Florida, LLC v. Armstrong World Industries, Inc., 2018 WL 905752, *15 (M.D.Fla 2018) (relying on
Caribbean Cruise Line to find that even though the plaintiff does not need to be a consumer, the plaintiff still must prove an injury to consumers to satisfy elements of a FDUTPA claim).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Protecting Your Business From Liability Claims Stemming From COVID-19 Exposure
June 01, 2020 —
Andrew Hamelsky, Jenifer Scarcella & Joshua Tumen - White and WilliamsBusinesses of every nature – including grocery stores, banks, daycares, gyms and restaurants – may face increasing liability claims from customers and third parties claiming to have been exposed to the novel coronavirus, or COVID-19, while at their location. The novel virus raises issues as to whether businesses have a heightened duty of care to their customers, and what type of exposure businesses face if a customer claims to have been exposed to COVID-19 while at their premises.
Recently, a lawsuit was filed against Princess Cruise lines for gross negligence in allowing passengers to be exposed to COVID-19 on a cruise ship. The lawsuit alleges that the cruise ship was allowed to go out to sea knowing that it was infected from two previous passengers who came down with symptoms of COVID-19. It further claims that the passengers were not warned of the potential exposure either before or after they boarded the ship.
In other news reports around the country, business owners have reported taking extraordinary precautions to prevent customers’ risk of contracting COVID-19. For example, one grocery store recently reported that it discarded $35,000 worth of food after a customer coughed on fresh produce.
Reprinted courtesy of White and Williams LLP attorneys
Andrew Hamelsky,
Jenifer Scarcella and
Joshua Tumen
Mr. Hamelsky may be contacted at hamelskya@whiteandwilliams.com
Ms. Scarcella may be contacted at scarcellaj@whiteandwilliams.com
Mr. Tumen may be contacted at tumenj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Strikes Down Reasonable Construction Defect Settlement
December 20, 2012 —
CDJ STAFFThe Court of Appeals of Washington has struck down a construction defect settlement between a building owner and the companies she hired to repair the siding, among other repairs to bring the building up to code. Yuan Zhang hired Hawk Construction LLC to do repair work. Hawk, in turn, hired Ready Construction LLC for some aspects of the project. Hawk and Ready were both insured by Capital Specialty Insurance Corporation.
There were several problems with Ready’s work. After removing old siding, they did not protect the building, nor did they remove all of the damaged layers. Ready covered, but did not fix, a mildew problem under the old siding. When new siding was reattached, the nails used were too short to adequately attach it.
After paying for an inspection of the work, Zhang had Hawk and Ready begin the repairs again, but the work was abandoned without being completed. Zhang sued Hawk for breach of contract. Hawk then sued Ready, claiming that “Ready was liable to Hawk to the extent that Hawk was liable to Zhang.” Capitol retained defense for both contractors.
Zhang settled with Hawk, in an agreement that gave her “the right to collect and/or pursue all costs and attorney fees paid by Hawk or its insurance company defending against the Zhang’s claims and pursuing claims against Ready.” Subsequently, she also settled with Ready. Both companies ceased operations.
Zhang had the settlements reviewed by a court, which concluded that the settlements were reasonable. Capital was allowed to appeal, claiming that the settlement included costs that were Zhang’s responsibility. The appeals court did not examine the question of the reasonableness of the settlement, concluding that Capitol’s interests were relevant only to “questions of bad faith, collusion, and fraud.”
In the case of Zhang, the court concluded that the relationship between Zhang and her former contractors was collusive. The court noted that “bad faith or collusion may exist when the evidence indicates a joint effort to create, in a non-adversarial atmosphere, a resolution beneficial to both parties, yet highly prejudicial to the insurer as intervener.” The court noted that both companies had minimal assets which were, in any case, exempted from the agreement. Further, the court found that the agreements failed to determine “what amount of the repairs related to preexisting water damage.” Zhang’s calculation of costs also included her expenses for architectural and engineering services, which the court points out, “where always Zhang’s costs to bear.”
The court concluded that “the overall structure of the settlements is highly probative of collusion, fraud, or bad faith.” Zhang’s agreements with Hawk and Ready allowed her to collect compensation from Hawk and then collect Ready’s compensation to Hawk for their portion of the settlement, allowing Zhang to collect the monies twice. Further, she was allowed to pursue Capitol for Hawk’s attorney expenses, even though Hawk had none. “The right to recover Hawk’s fees merely set up a windfall recovery for Zhang.” The court described the agreements among Zhang, Hawk, and Ready as “precisely the type of manipulation [the law] is intended to preclude.”
Read the court decisionRead the full story...Reprinted courtesy of
Not Remotely Law as Usual: Don’t Settle for Delays – Settle at Remote Mediation
May 25, 2020 —
Victor J. Zarrilli, Robert G. Devine & Michael W. Horner - White and Williams LLPThe emergence and rapid spread of COVID-19 has created extraordinary circumstances that have significantly impacted how we go about living, working and interacting with one another. The practice of law is no exception.
While most cases have been postponed and some extended indefinitely, the issues and disputes that first triggered the litigation remain. In fact, the burdens created by social distancing and other responses to the COVID-19 outbreak have served to only increase these disputes and create an urgent need in some for quick resolution.
In our previous article, we summarized some of the best practices that should be applied when taking and defending depositions in a remote, virtual setting. That technology can also offer the same benefits for alternative dispute resolutions. If planned properly, the use of technology allows remote mediations to be conducted as seamlessly as in-person mediations and, in some circumstances, affords additional benefits that can achieve the best possible resolution for all sides.
This article summarizes the opportunities technology has created by which parties can attempt to resolve their disputes through alternative dispute resolution methods, even in a time of social distancing.
Reprinted courtesy of White and Williams LLP attorneys
Victor J. Zarrilli,
Robert G. Devine and
Michael W. Horner
Mr. Zarrilli may be contacted at zarrilliv@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Horner may be contacted at hornerm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Owners Bound by Arbitration Clause on Roofing Shingles Packaging
December 04, 2018 —
David Adelstein - Florida Construction Legal UpdatesIn today’s age, you are probably familiar with terms such as a shrinkwrap contract (terms and conditions), which is a boilerplate contract included with a retained product, or a clickwrap contract (terms and conditions), which is generally a boilerplate contract that is digitally accepted when purchasing software or an electronic product. These are are boilerplate terms from manufacturers or vendors of products or software. Arbitration provisions in these types of agreements have generally found to be enforceable.
In the recent ruling by the Eleventh Circuit Court of Appeals in Dye v. Tamko Building Products, Inc., 2018 WL 5729085 (11th Cir. 2018), the court held that an arbitration provision included in a product-purchase limited warranty agreement on the package of every roofing shingles binds a homeowner to arbitrating disputes over the opened and retained product with the manufacturer, irrespective of whether the shingles were purchased by an owner’s roofer. The shingles do not have to be purchased and opened by the owner for the arbitration provision to apply. If the roofer uses or retained the shingles for purposes of the owner’s home, such knowledge of the product-purchase limited warranty agreement on the packaging of the shingles is imputed to the owner (end-user of the shingles).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Mich. AG Says Straits of Mackinac Tunnel Deal Unconstitutional
June 03, 2019 —
Jeff Yoders - Engineering News-RecordMichigan Attorney General Dana Nessel (D) has declared unconstitutional a late-2018 law that would create an authority to oversee construction of a key tunnel. The tunnel would house an oil-and-gas pipeline under the Straits of Mackinac.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Yoders, ENRMr. Yoders may be contacted at
yodersj@enr.com
Floating Crane on Job in NYC's East River Has a Storied Past of Cold War Intrigue
March 22, 2017 —
Nadine M. Post – Engineering News-RecordThe complex maneuver of lifting heavy prefabricated modules out of New York City's East River to build a university laboratory took careful planning and the work of one particular floating crane with a complicated past.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, Engineering News-RecordMs. Post may be contacted at
postn@enr.com
Construction Employment Rises in Half of the States
December 09, 2011 —
CDJ STAFFThe Labor Department has noted that half the states and the District of Columbia saw increases in construction employment during the month of October. During the same month, twenty-three states lost construction jobs.
The biggest gains were in North Dakota, Oklahoma, DC, Texas, and California. The biggest losses were in Georgia, New Mexico, Wisconsin, and Florida. There was no change for Alabama.
The chief executive officer of the Association of General Contractors of America, Stephen E. Sandherr, called for more infrastructure development. “Allowing water, transportation and energy networks to deteriorate will hurt construction employment and force taxpayers to spend more later, to fix broken infrastructure.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of