Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Energy Company Covered for Business Interruption Losses Caused by Fire and Resulting in Town-Ordered Shutdown
February 15, 2021 —
David G. Jordan - Saxe Doernberger & Vita, P.C.In the case of NextSun Energy Littleton, LLC v. Acadia Ins. Co., the United States District Court of Massachusetts held that once direct physical damage from a covered peril causes a covered business interruption loss, any increase in the duration of such business interruption, due to the enforcement of an ordinance or law, extends the coverage period provided for lost income. The Court further held that a policy exclusion for business interruption due to the enforcement of any ordinance or law not in force at the time of the loss only applies when the ordinance or law itself, not the enforcement action that it authorizes, was not in force at the time of the loss.
The case involved a solar panel company, NextSun Energy Littleton (NextSun), that operated solar panel arrays providing electricity to the town of Littleton, Massachusetts. Due to a fire, 88 of the solar panels were damaged, and the Town immediately issued a “red-tag” order halting all energy-generating activity pending a safety inspection. The plaintiff purchased insurance for its panels along with “Energy Generating Income” (EGI) coverage, from the defendant, Acadia Ins. Co. (Acadia). The EGI policy covered “direct physical loss or damage” to “renewable energy generating equipment” and also covered the actual loss of surplus power income incurred during the interruption period. However, it excluded interruption of energy-generating income “caused by the enforcement of any ordinance, law, or decree … not in force at the time of loss.”
Read the court decisionRead the full story...Reprinted courtesy of
David G. Jordan, Saxe Doernberger & VitaMr. Jordan may be contacted at
DJordan@sdvlaw.com
The Future of Construction Defects in Utah Unclear
December 11, 2013 —
CDJ STAFFIn recent years, more courts have started to view construction defects as accidents, covered under insurance policies. In a post on the Parr Brown Gee & Loveless web site, Jeffrey D. Stevens writes that “the number of courts siding with insurance companies to deny contractors and subcontractors insurance coverage in construction defect lawsuits has been shrinking.” Recently, the Supreme Court of West Virginia “switched sides on this issue completely.”
The Utah Supreme Court has not made a ruling on this, but the Federal District Court for the District of Utah and the Tenth Circuit have looked at Utah law and concluded that “under Utah law damage caused by construction defects is not accidental.” But in another case, “the district court determined that property damage allegedly caused by defective or defectively installed windows was caused by an accident.”
Mr. Stevens thinks that “it is likely” that the Utah Supreme Court “will follow the increasing number of courts that have held that damage caused by construction defects is an accident for insurance purposes.
Read the court decisionRead the full story...Reprinted courtesy of
Case Remanded for Application of Efficient Proximate Cause Doctrine
November 06, 2013 —
Tred Eyerly — Insurance Law HawaiiThe Florida Court of Appeals remanded the case after the insured was awarded an $8 million dollar judgment against its property insurer for hurricane and other damage to a home. Am. Home Assur. Co. v. Sebo, 2013 Fla. App. LEXIS 14799 (Fla. Ct. App. Sept. 18, 2013).
Sebo purchased his home in April 2005, when it was four years old. It was insured under a manuscript policy issued by AHAC for $8 million. The all-risk policy covered rain, but excluded damage caused by faulty, inadequate or defective planning.
After Sebo bought the home, water leaks were noticed. Sebo believed that the house suffered from major design and construction defects. In October 2005, Hurricane Wilma struck and further damaged the home.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Attorneys Fees Under California’s Prompt Payment Statutes. Contractor’s “Win” Fails the Sniff Test
October 02, 2015 —
Roger Hughes – California Construction Law BlogThis past month, the California Court of Appeals for the Third District, in James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., Case No. C072169 (August 27, 2015), handed down a decision in a construction contract battle that has raged since 2007. And, once again, the winner is . . . in the words of Justice Andrea Lynn Hoch who authored the opinion . . . . “no prevailing party in [the] case” and hence “no prevailing party attorney’s fees [ ] awarded.”
Background
In Harris, subcontractor James L. Harris Painting & Decorating, Inc. (“Harris”) sued general contractor West Bay Builders, Inc. (“West Bay”) for extra work performed on a school construction project in Stockton, California. Among its claims, Harris asserted that West Bay was liable under California’s prompt payment statutes for failure to timely pay Harris.
Read the court decisionRead the full story...Reprinted courtesy of
Roger Hughes, Wendel Rosen Black & Dean LLPMr. Hughes may be contacted at
rhughes@wendel.com
Brown and Caldwell Team with AECOM for Landmark Pure Water Southern California Program
May 15, 2023 —
Brown and CaldwellLOS ANGELES, May 09, 2023 — A joint venture of AECOM and Brown and Caldwell (AECOM-BC Team) has been chosen to provide program and project management support and engineering design services for the
Pure Water Southern California program, one of the largest water reuse programs in the world.
The innovative program, being developed by the Metropolitan Water District of Southern California (Metropolitan) in partnership with the Los Angeles County Sanitation Districts (Sanitation Districts), will produce up to 150 million gallons of high-quality, purified water per day for up to 15 million people.
Anticipated for water delivery by 2032 and potentially earlier, the program will reuse the largest untapped wastewater source in the region that currently flows to the ocean to increase water resiliency, enhance water quality, and fuel economic growth. It will lower Southern California’s reliance on imported water supplies from the Colorado River and Sierra Nevada and replenish groundwater basins while leveraging cutting-edge research and development to increase regional water reuse.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and over 1,900 professionals across North America and the Pacific. For more than 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients’ expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
Subcontractor Exception to "Your Work" Exclusion Does Not Apply to Coverage Under Subcontractor's Policy
January 26, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Arizona Court of Appeals overturned the trial court's determination that the general contractor was entitled to coverage under the subcontractor's exception to the "Your Work" exclusion. Double AA Builders v. Preferred Contrs. Ins. Co., 2016 Ariz. App. LEXIS 294 (Ariz. Ct. App. Dec. 30, 2016).
Harkins Theatres hired Double AA Builders, Ltd. to serve as general contractor to build a theater complex. Double AA subcontracted with Anchor Roofing, Inc. to install the roof. Anchor was the "Named Insured" under a policy issued by Preferred Contractors Insurance Company, LLC. Double AA was an "Additional Insured" under the Preferred policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Environmental Justice: A Legislative and Regulatory Update
November 01, 2021 —
Anthony B. Cavender - Gravel2GavelEnvironmental Justice, as an urgent policy priority of the Federal Government, dates back to 1994, and President Clinton’s issuance of Executive Order 12898. This order directed federal agencies to identify and address, as appropriate, “the disproportionately high and adverse human health and environment effects of its many programs, policies, and procedures on minority populations and low-income populations.” Executive Order 12898 supplements Executive Order 12550 (1980), whose primary legal basis was Title VI of the Civil Rights Act of 1964, in particular, Sections 601 and 602, which prohibit discrimination in programs and activities receiving federal financial aid and assistance.
Over the years, the Supreme Court has reviewed the scope and importance of Title VI. For example, in Alexander v. Sandoval, decided in 2001, the Court concluded that while private parties could sue to enforce Section 601 or its implementing regulations, Section 601 only prohibits intentional discrimination; which is very difficult to prove. In addition, the Court ruled in Sandoval, that private parties cannot sue to enforce regulations implementing Section 602. Perhaps as an acknowledgement of these shortcomings, the Environmental Protection Agency (EPA) has for many years operated an administrative system to process environmental justice complaints (see 40 CFR Part 7). The process is complex and the results—usually whether a state agency has failed to uphold Title VI—have generally been unsatisfactory. To be successful, many proponents of environmental justice believe that a statutory foundation must be established, and significant efforts have been made to do so.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com