Colorado Abandons the “Completed and Accepted Rule” in Favor of the “Foreseeability Rule” in Determining a Contractor’s Duty to a Third Party After Work Has Been Completed
January 17, 2013 —
Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLCIn a recent case, the Colorado Court of Appeals found that a contractor had a duty to a third party to warn it of a dangerous condition, even after the contractor had completed its work and the owner had accepted the contractor’s work. Collard v. Vista Paving Corp., -- P.3d --, 2012 WL 5871446 (Colo. App. 2012). While not an earth shattering or entirely new concept, the decision rendered in Collard directly accepted the foreseeability rule at the expense of the completed and accepted rule. Id.
In Collard, the City of Grand Junction (“the City”) hired Vista Paving Corp. (“Vista”) to construct two road medians according to the City’s plans and designs. On July 9, 2007, Vista began work on the medians. According to its contract with the City, Vista was responsible for traffic control during construction of the medians. On July 19, 2007, Vista completed its construction of both medians. On that date, the City’s project inspector conducted his final inspection of Vista’s work. The City’s inspector then told Vista that its work had been completed and that Vista was authorized to leave the site. Vista requested permission to remove the traffic control devices to which the City’s inspector agreed. Vista removed all of its traffic control devices.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioMr. Iandiorio can be contacted at
iandiorio@hhmrlaw.com
Public Projects in the Pandemic Pandemonium
September 07, 2020 —
Ashlynn E. Hutton, Michael J. Crook & Christian F. Torgrimson - Construction ExecutiveDespite the ongoing pandemic, states are opening up for business and establishing a new normal. This determination to move forward includes pushing public transportation projects full steam ahead. While this may be good news for certain industries, it may not be for commercial property owners hoping to see a slow down to public projects and avoid a taking of private property. As many grapple with new economic realities, we examine the approaches employed by states in the southeast to manage construction of public projects in this unprecedented time.
GEORGIA
The Georgia Department of Transportation (GDOT) is moving forward with all of its previously funded public projects, including the massive I-285 Top-End Project, designated as a “Major Mobility Project” for the Atlanta metro region. Affecting approximately 260 property owners along I-285 and Georgia Highway 400, environmental review of the project continues. GDOT anticipates a contract let date in 2022 and construction start in 2023. Like ocean liners, these projects don’t turn on a dime. Under the 2015 Transportation Funding Act, the budgeted funds cannot be shifted to other needs or projects due to economic shutdown. Once environmental review is complete, GDOT will approve the final design and move toward acquiring right-of-way from affected property owners.
Reprinted courtesy of
Ashlynn E. Hutton, Michael J. Crook & Christian F. Torgrimson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
In Pricey California, Renters Near Respite From Landlord Gouging
September 16, 2019 —
Noah Buhayar - BloombergThe housing crisis engulfing California has state lawmakers racing to pass bills that would boost construction and stop corporate landlords from egregiously jacking up rents.
The bills overcame key hurdles last week and are due for final votes before the legislature adjourns on Sept. 13. The hardest-fought measure would set a higher standard for evictions and cap annual rent increases at 5% plus the rate of inflation. While that’s below the typical pace of lease hikes -- and the bill has many caveats for landlords -- it would still mark the state’s most significant new protection for tenants in decades.
Read the court decisionRead the full story...Reprinted courtesy of
Noah Buhayar, Bloomberg
Construction Law Client Advisory: What The Recent Beacon Decision Means For Developers And General Contractors
August 20, 2014 —
Steven M. Cvitanovic and Whitney L. Stefko - Haight Brown & Bonesteel LLPOn July 3, 2014, the California Supreme Court (the “Court”) came out with its decision in Beacon Residential Community Association v. Skidmore, Owings & Merrill, et al. The Beacon decision settled a long-standing dispute in California about whether design professionals such as architects and engineers owe a duty to non-client third parties. In finding that the plaintiffs in Beacon could state a claim against the architects of the Beacon project, the Court also sowed the seeds of change in the way contracts are structured between developers, architects, engineers, and even general contractors.
So, how will Beacon change the landscape for developers and general contractors? It is important to understand the factual background in Beacon to predict how the decision may alter the playing field. For a detailed analysis of the Amicus briefs in the Beacon matter from the AIA, the CBIA, and the Consumer Attorneys of California, please click here.
The Beacon case arose from a common development model in California: a developer conceives a multi-unit project, maps the project as a condo development but rents as apartments. Shortly after completion of the Beacon project, the developer sold the entire project and the new owner finalized the existing condominium map and placed the units on the market as condominiums. Although the architects always knew they had designed a residential structure, the project ultimately became a condominium development. The newly formed homeowners’ association filed a construction defect suit against the developers, general contractor, the subcontractors and the architects for design and construction defects.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Issue and Claim Preclusion When Forced to Litigate Similar Issues in Different Forums: White River Village, LLP v. Fidelity and Deposit Company of Maryland
October 10, 2013 —
Brady Iandiorio — Higgins, Hopkins, McLain & Roswell, LLC.Often in construction litigation the parties wish to move the case to arbitration. However, there are certain circumstances in which such change of litigation forums should be carefully analyzed. The case of White River Village, LLP v. Fidelity and Deposit Company of Maryland, serves as an example of one of those circumstances.
In March 2013, U.S. District Court Judge Blackburn ruled on a motion for summary judgment filed by Fidelity and Deposit Company of Maryland (“F&D”). The order grants the motion in part and denies it in part. White River Village, LLP (“White River”) was the owner of the project which hired S&S Joint Venture (“S&S”), the contractor, to build two similar developments, directly adjacent to each other. The contracts between Whiter River and S&S for the two projects were so substantially similar that the court referred to them as the S&S Contracts. F&D issued payment and performance bonds guarantying the obligations of S&S under the S&S Contracts.
After S&S defaulted on the construction contracts, F&D, as the surety, undertook to complete performance on the contracts. White River alleged that F&D was liable for construction defects and delays in completing the project, and failed to fulfill its obligations under the performance bonds after it overtook the construction of the projects.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at
Iandiorio@hhmrlaw.com
Serving Notice of Nonpayment Under Miller Act
January 20, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the federal Miller Act, if a claimant is NOT in privity with the prime contractor, it needs to serve a “notice of nonpayment” within 90 days of its final furnishing. In this manner, 40 U.S.C. 3133 (b)(2) states:
A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made. The action must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. The notice shall be served–
(A) by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor’s residence; or
(B) in any manner in which the United States marshal of the district in which the public improvement is situated by law may serve summons.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
How Does Weather Impact a Foundation?
December 27, 2021 —
Brent Pearson - Construction ExecutiveWhen it comes to commercial properties, it pays to be prepared. However, there are few things as unpredictable as the weather. With there being several weeks left in hurricane season, the weather can have quite an impact on the foundations of different properties. Whether it’s a new home or a century-old commercial property, preserving the integrity and safety of the structure is paramount. For those in construction looking to learn more about how the weather can sway a foundation, below are several examples along with tips on prevention.
Rain, Rain Go Away!
Hurricanes are known for bringing strong winds and plenty of rain. This can spell disaster for buildings with weak foundations. Torrential downpours can cause wet and weak soil. Too much rain—whether generated by hurricanes or frequent storms—can negatively impact the foundations of commercial properties and homes as well. It can also cause the soil to weaken, which can lead to a foundation sinking into the ground. For those that may have crawl spaces underneath their properties, heavy rains may cause water to seep under and into it. Water will sit in the crawl space, and it could take days or even weeks to dry out, causing moisture and possible mold damage.
Reprinted courtesy of
Brent Pearson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Blindly Relying on Public Adjuster or Loss Consultant’s False Estimate Can Play Out Badly
May 03, 2021 —
David Adelstein - Florida Construction Legal UpdatesInsurance policies, particularly property insurance policies, have a concealment or fraud provision that, in essence, gives the insurer an out if the insured submits a fraudulent claim, a false claim, or conceals material facts. Unlike a traditional fraud claim where a party needs to prove intent, the provision is broad enough that it does not require any intent behind making a false statement. See Mezadieu v. Safepoint Ins. Co., 46 Fla.L.Weekly D691c (Fla. 4th DCA 2021). For this reason, and as exemplified below, do NOT blindly rely on a public adjuster or loss consultant’s estimate that contains false statements because those false statements, particularly if you know they are false, can play out badly for you! Review the estimate and ask questions about it to make sure you understand what is being included in the loss or damages estimate.
In Mezadieu, a homeowner submitted a claim to her property insurance carrier due to a second-floor water leak emanating from her bathroom. She submitted an estimate from her public adjuster that included damages for her kitchen cabinets directly below the second-floor bathroom, as well as other items on her first-floor. Her carrier denied coverage based on the exclusion that the policy excludes damage caused by “[c]onstant or repeated seepage of water or steam…which occurs over a period of time.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at