Maximizing Contractual Indemnity Rights: Components of an Effective Provision
December 02, 2015 —
William Kennedy – White and Williams LLPTort law is aimed at providing compensation to the victims of negligence. Tort law encourages plaintiffs to cast a wide net, pursuing claims or suits against not only those whose fault seems manifestly primary, but also against defendants whose causal exposure is minimal, against those whose exposure is purely by operation of law. As discussed in the first installment of this series, "Maximizing Contractual Indemnity: Problems with Common Law," three common law principles – vicarious liability, joint and several liability, and common law indemnity – cause some parties to pay in excess of their actual degree of causal fault. Contractual indemnity can remedy that harsh result.
Part Two: Components of an Effective Provision
Properly composed, “broad form” contractual indemnity provisions permit an Indemnitee to shift the full range of financial consequences from tort exposure, including civil damages, defense fees, expert fees, and litigation expenses. Such contracts permit indemnity even where the underlying damage was incurred due to a degree of negligence or fault on the part of the Indemnitee. Such contracts can also allow an Indemnitee to shift to the Indemnitor the risk of loss for someone from whom the Indemnitor would otherwise be immune from suit (e.g., the Indemnitor’s employees). A well-written contract can even convert an entity which is an Indemnitor as to one party (e.g., a general contractor which has to indemnify a property owner) into an Indemnitee as to another party (e.g., a subcontractor) for the very same risk.
Read the court decisionRead the full story...Reprinted courtesy of
William Kennedy, White and Williams LLPMr. Kennedy may be contacted at
kennedyw@whiteandwilliams.com
Insured's Lack of Knowledge of Tenant's Growing Marijuana Means Coverage Afforded for Fire Loss
August 17, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe California Court of Appeals reversed the trial court's grant of summary judgment to the insurer regarding a claim for fire loss. Mosley v. Pacific Sec. Ins, Co., 2020 Cal. App LEXIS (Cal. Ct. App, May 26, 2020).
The Mosleys rented their property to Pedro Lopez. Six months later, the property was damaged by fire. Lopez had tapped a main power line into the attic to power his energy-intensive marijuana growing operation. The illegal power line caused the fire.
Pacific Specialty Insurance Company (PSIC) insured the property under an HO-3 Standard Homeowners policy. Paragraph E of the policy provided,
We do not insure for loss resulting from any manufacturing, product or operation, engaged in:
- The growing of plants; or
- The manufacture, production, operation or processing of chemical, biological, animal or plant materials.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
SIGAR Report Finds +$15 Billion in “Waste, Fraud and Abuse” in Afghanistan
August 20, 2018 —
Pillsbury's Construction & Real Estate Law Team - Gravel2GavelToday, our colleagues Alex Ginsberg, Glenn Sweatt and Kevin Massoudi published their Client Alert on a recently issued Special Inspector General for Afghanistan Reconstruction (SIGAR) Report that finds over $15 billion in waste, fraud and abuse. In New SIGAR Report Identifies “Waste, Fraud and Abuse” in Afghanistan, our colleagues identify key takeaways from the Report include:
- The Report reviewed public spending for Afghanistan reconstruction efforts and identified at least $15.5 billion in waste, fraud and abuse.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
What is an Alternative Dispute Resolution?
August 26, 2019 —
Bremer Whyte Brown & O'Meara LLPAlternative Dispute Resolution (“ADR”) is a term that refers to a number of processes that can be used to resolve a conflict, dispute, or claim. ADR processes are alternatives to having a court decide the dispute in trial.
ADR processes can be used to resolve any type of dispute including but not limited those related to families, neighborhoods, employment, businesses, housing, personal injury, consumers, and the environment. ADR is usually less formal, less expensive, and less time-consuming than a trial.
Most Common Types of Alternative Dispute Resolutions
Mediation
In mediation, an impartial person called a “mediator” helps the parties try to reach a mutually acceptable resolution of the dispute. The mediator does not decide the dispute but helps the parties communicate so they can try to settle the dispute themselves. Mediation leaves control of the outcome with the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Proposed Law Protecting Tenants Amended: AB 828 Updated
June 08, 2020 —
Rhonda Kreger – Newmeyer DillionOn May 18, 2020, AB 828 was amended and is currently on its second reading in the Senate Rules Committee. This legislation proposes a temporary moratorium on foreclosures and unlawful detainers while Governor Newsom's COVID-19 emergency order is in effect. In addition to the moratorium, AB 828 also required landlords to reduce rent by 25% under certain circumstances. AB 828 was amended to remove the provision that required landlords to reduce rent by 25% for 12 months. The new provision requires landlords to allow tenant to remain in possession, and requires tenants to start paying rent the month following the end of the emergency order. Tenants must timely pay monthly rent plus 10% of any rent due and owing when the emergency order ended.
Under AB 828, a tenant may stipulate to the entry of an order in response to a residential unlawful detainer action filed by the landlord. Upon a hearing, the court determines if the tenant's inability to pay rent is the result of increased expenses or a reduction in income due to COVID-19. The court must also make a determination that there is no material economic hardship for the landlord. Upon making such determinations, the court will issue an order that permits the tenant to remain in possession, and requires tenant to commence rental payments the month following the end of the COVID-19 emergency order. Tenant's payment would include the monthly rent plus 10% of an unpaid rent during the COVID-19 emergency order, but excludes any late charges or other fees or charges. The tenant would be required to make timely payments, and if tenant fails to do so, after a 48 hour notice from landlord, the landlord can file for an immediate writ of possession in favor of the landlord and money judgment for any unpaid balance, court costs and attorneys' fees.
Newmeyer Dillion continues to follow COVID-19 and its impact on your business and our communities. Feel free to reach out to us at NDcovid19response@ndlf.com or visit us at www.newmeyerdillion.com/covid-19-multidisciplinary-task-force/.
Rhonda Kreger is Senior Counsel on Newmeyer Dillion's transactional team at our Newport Beach office. Her practice focuses on all aspects of commercial real estate law, with a particular emphasis on the representation of residential developers, merchant builders and institutional investors. You can reach Rhonda at rhonda.kreger@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Effects of Amendment to Florida's Statute of Repose on the Products Completed Operations Hazard
November 06, 2018 —
Richard W. Brown & Grace V. Hebbel - Saxe Doernberger & Vita, P.C.Recent amendments to Florida’s Statute of Repose have resulted in concerns as to the scope of risk Florida homebuilders face as a result, and the availability of insurance coverage for such exposures. Previously, the statute provided for a strict, yet straightforward 10-year limitation for latent construction defect claims. Under that language, issues arose when suits were filed near expiration of the statute, because parties seeking to defend claims were given little time to effectively assert related claims. The amendment to the statute serves to lengthen the statute of repose to 11 years for certain cross-claims, compulsory counterclaims, and third-party claims, and in limited circumstances, potentially even longer. Most policies in the Florida marketplace serve to limit coverage under the products-completed operations hazard (“PCO”) to 10 years, and thus, in very limited circumstances, an insured contractor may be exposed to third-party claims under the revised statute. It is important to note, however, that coverage under most CGL policies is occurrence-based, meaning that the policy is triggered by property damage that occurs during the policy period, and therefore, any subsequent claims permitted under the amended statute will necessarily relate to the original property damage that occurred during the 10-year period, and thus, would be covered under the standard 10-year PCO extension. This paper will analyze the anticipated effect of the amendments upon coverage under a 10-year PCO extension.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita P.C. and
Grace V. Hebbel, Saxe Doernberger & Vita P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Ms. Hebbel may be contacted at gvh@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Chinese Hunt for Trophy Properties Boosts NYC, London Prices
January 21, 2015 —
Vinicy Chan – BloombergWhat do New York’s most famous hotel, the Lloyd’s of London building and the headquarters of the U.K.’s top law firm have in common? They’re all owned by Chinese insurers.
This new breed of buyers, who weren’t allowed to invest overseas before 2012, are flooding into the global market for prime commercial real estate after being given more freedom to deploy their $1.6 trillion of assets. That has meant good times for sellers of trophy real estate in major cities.
Read the court decisionRead the full story...Reprinted courtesy of
Vinicy Chan, BloombergMs. Chan may be contacted at
vchan91@bloomberg.net
Congratulations to Nicholas Rodriguez on His Promotion to Partner
November 25, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is very proud to announce that Nick Rodriguez has been promoted to the position of partner with the firm!
Nick has been with BWB&O since 2019 and is licensed to practice law in California and the U.S. District Courts. Nick’s practice focuses on complex construction defect matters, as well as personal injury and wrongful death claims. During his time with the firm, Nick has successfully represented numerous clients through alternative dispute resolution and has taken matters to trial where he has received favorable jury verdicts. He also supervises and manages a team of associates in the Newport Beach office.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP