Natural Disasters’ Impact on Construction in the United States
December 14, 2020 —
Robert S. Peckar & Crystal T. Dang - Construction ExecutiveIn these times of easy and instant access to news from around the globe, the effects of major earthquakes in Indonesia and Mexico, cyclones in Southeast Asia, Tsunamis around the world, volcanoes in Europe in unexpected places and, of course, raging forest fires and hurricanes in the United States are frequently in the news. Accompanying each of these disasters are immediate threats to construction projects, both physical and those affecting the safety and health of personnel.
However, after the dust settles or the waters recede, myriad issues will become obstacles to the road to recovery for a contractor to navigate. In 2020 alone, the volume of strong storms and forest fires have focused so much attention on the impact of disasters. The purpose of this article is to provide guidelines in anticipation of disasters, for reviewing the impact of a disaster as it is happening, and developing a mitigation plan to limit losses.
Anticipating Disasters
The best time to prepare for a disaster on a project is before the project starts. Reviewing contract rights, insurance policies and company disaster response protocols while a category 3 hurricane is a day away is not a best practice. To avoid falling into that situation, a contractor should follow the following guidelines. Doing so facilitates proper action during the actual disaster itself and in the aftermath.
Reprinted courtesy of
Robert S. Peckar & Crystal T. Dang, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Peckar may be contacted at rpeckar@pecklaw.com
Ms. Dang may be contacted at cdang@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
US Homes Face Costly Retrofits for Induction Stoves, EV Chargers
May 20, 2024 —
Kendra Pierre-Louis - BloombergBuyers of new homes in the US may find themselves saddled with electrical systems better suited to the 20th century than the 21st.
The International Code Council, which sets model construction standards for new homes, was expected to include building electrification measures in its 2024 energy code on March 20. But following appeals lodged by industry groups, the ICC board moved the measures to the code’s appendices, effectively making them optional, as first reported by the Huffington Post.
If new homes aren’t wired for increasing power needs from electric appliances and car chargers, it will bump the effort and cost of making such upgrades onto homeowners — a deterrent to going electric. Energy efficiency advocates say this could slow the pace of the energy transition, costing both jobs and the planet.
Read the court decisionRead the full story...Reprinted courtesy of
Kendra Pierre-Louis, Bloomberg
A Court-Side Seat: An End-of-Year Environmental Update
January 09, 2023 —
Anthony B. Cavender - Gravel2GavelAs 2022 draws to a close, here is a brief description of recent environmental and regulatory law rulings, as well as new federal rulemaking proceedings.
United States Tax Court
Green Valley Investors, LLC et al, v. Commissioner of Internal Revenue
On November 9, 2022, the Tax Court agreed with the taxpayers that the IRS’s use of administrative Notice 2017-10 to impose substantial tax liabilities violated the Administrative Procedure Act (APA). The notice was the agency’s response to a provision in the American Jobs Creation Act of 2004 which increased the penalties for engaging in a reportable transaction understatement. Here, at issue was the value of charitable deductions generated by the creation of environmental easements made in connection with land transactions. These claimed deductions amounted to more than $60 million. The petitioners argued that IRS Notice 2017-10, which authorized such large penalties, was in fact a “legislative rule” whose promulgation should have complied with the notice and comment requirements of the APA. The agency contended that the Congress, by implication, absolved the IRS from the notice and comment requirements. The court agreed with the petitioners and set aside Notice 2017-10 and the imposition of penalties under Section 6662A of the Jobs Creation Act. On December 8, 2022, the IRS published a notice of proposed rulemaking that would correct the APA deficiencies noted by the courts. (See 87 FR 75185.)
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Need to Be Specific and Precise in Drafting Settling Agreements
December 30, 2013 —
W. Berkeley Mann, Jr. — Higgins, Hopkins, McLain & Roswell, LLCThe case of Bituminous Casualty Corp. v. Hartford Casualty Insurance Corp., 2013 WL 452374 (D. Colo. February 6, 2013) is instructive as an example of both the confusion and resulting escalation of litigation that can result from a lack of clarity in settlement negotiations. This is particularly true where parties settle outside of their insurance coverage, and/or without notifying their insurer(s), which have denied coverage.
The case involved coverage litigation following settlement of a multi-party construction defect case involving the Rivergate multi-family residential development in Durango, Colorado. The condominium owners association sued, among others, the developer (Rivergate Lofts Partners, hereafter “RLP”) and the general contractor (Genex Construction, LLC, hereafter “Genex”). This follow-on case involved the insurers for RLP (“Hartford”) and Genex (“Bituminous”). The coverage dispute was complicated by the Bituminous allegations that Hartford insured Genex in its alleged role as a manager for RLP, as part of Hartford’s insurance of RLP more generally.
The underlying facts were that Hartford denied insurance coverage and defense to Genex/Bituminous. The underlying construction defect case went to mediation, with the COA, RLP, and Genex all in attendance with their respective insurer representatives, and coverage counsel. While the evolving facts of that mediation were later disputed as to their motives, intentions, and the contemporaneous knowledge of the parties, the facts reflected in documents were fairly clear.
Read the court decisionRead the full story...Reprinted courtesy of
W. Berkeley Mann, Jr.W. Berkeley Mann, Jr. can be contacted at
mann@hhmrlaw.com
Some Construction Contract Basics- Necessities and Pitfalls
January 03, 2022 —
Christopher G. Hill - Construction Law MusingsRecently, I’ve been on an “advising” kick here at Construction Law Musings. My last two posts have been about communication and trusting your gut when it comes to a smooth construction project. This post will be the third in the trilogy (and who knows maybe I’ll have a 4th and 5th like the Hitchhiker’s Guide to the Galaxy “trilogy”).
While all construction contractors should use their communication skills and instincts to assure a smooth and hopefully profitable project, all of the gut following and great communication will not help you if your contract is not up to snuff. In the spirit of giving you a few basics things to look at, here’s my list of three basics that you need in your contract and a three things to be on the lookout for in others’ contracts.
First, the good stuff that needs to be there:
- Attorney Fees Clause– without it, a Virginia court (and most other courts) will not award you a judgment for any attorney fees spent to protect your rights.
- Dispute Resolution– whether the specified resolution is through the litigation process, ADR or some combination, such a clause or paragraph will only help define the parameters of what happens with a claim.
- Detailed scope of work– Without the proper detail in the scope of work, the parties cannot properly set expectations and know what happens when things change.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
"Occurrence" May Include Intentional Acts In Montana
June 22, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Montana Supreme Court found that policy language defining "accidents may include intentional acts." Employers Mut. Cas. Co. v. Fisher Builders, Inc., 2016 Mont. LEXIS 269 (Mont. Sup. Ct. April 19, 2016).
Jerry and Karen Slack hired Fisher Builders to build a remodeled home located on the site of their home at Flathead Lake. The existing home was an aged vacation home. The County zoning regulations required the remodeled home to incorporate the existing structure. The permit issued to the Slacks required the existing deck to remain unchanged.
Fisher elevated the existing home structure on steel beams to pour a new foundation. Fisher began to dismantle the walls while the structure was resting on the beams, and found an infestation of carpenter ants. The ant-infested planks were cut out, apparently in order to salvage what usable materials he could from the remaining structure. The ant-infested boards were subsequently burned. Eventually, the deck collapsed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
OSHA’s COVID-19 Emergency Temporary Standard Is in Flux
December 06, 2021 —
Megan E. Baroni & Jonathan H. Schaefer - Construction ExecutiveOn Friday, Nov. 5, 2021, Occupational Safety and Health Administration’s COVID-19 Vaccination and Testing Emergency Temporary Standard was issued, with most requirements set to go into effect on Dec. 5. The ETS applies to employers with a total of 100 or more employees company-wide. Employers covered by the ETS would be required to develop, implement and enforce a mandatory vaccination policy, subject to limited exemptions, or allow unvaccinated employees to test regularly and be subject to a mask policy, among other associated recordkeeping, reporting and training requirements.
Almost immediately, the ETS was hit with a number of legal challenges in various courts across the country. On November 6, just a day after the ETS was issued, the U.S. Circuit Court of Appeals for the Fifth Circuit issued an order staying the implementation of the ETS until further notice. The Court’s order was not a final ruling on the validity of the ETS but has halted implementation of the ETS, at least for the time being. Other legal challenges are already in process, further complicating the issue of if and when the ETS will become effective.
As of November 2021, the ETS is on hold, at least temporarily. That could change any day and the ETS could be back in effect, in whole or in part, or permanently halted. The legal challenges to the ETS are unlikely to end, or diminish, until the Supreme Court has weighed in, making for a few uncertain months ahead.
Reprinted courtesy of
Megan E. Baroni and Jonathan H. Schaefer, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Baroni may be contacted at mbaroni@rc.com
Mr. Schaefer may be contacted at jschaefer@rc.com
Read the court decisionRead the full story...Reprinted courtesy of
Filing Motion to Increase Lien Transfer Bond (Before Trial Court Loses Jurisdiction Over Final Judgment)
May 15, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf a construction lien is recorded against real property, the lien can be transferred to a lien transfer bond. This transfers the security or collateral of the construction lien from the real property to the lien transfer bond. The lien transfer bond can be a bond posted by a surety company or it can be cash. This is governed by Florida Statute s. 713.24. The amount of the lien does not dictate the amount of the lien transfer bond. Rather, the lien transfer bond needs to be in the amount of the lien, plus interest on that amount for three years, plus $1,000 or 25% of the amount of the lien (whichever is greater so factor in the 25%) to cover attorney’s fees. Fla. Stat. 713.24(1).
If you are looking to transfer a construction lien to a lien transfer bond, make sure to consult with counsel.
Keep in mind there is a statutory mechanism for a lienor to increase the lien transfer bond to cover attorney’s fees and costs and notice the word “must” in the statute below. Pursuant to Florida Statute s. 713.24(3):
Any party having an interest in such security or the property from which the lien was transferred may at any time, and any number of times, file a complaint in chancery in the circuit court of the county where such security is deposited, or file a motion in a pending action to enforce a lien, for an order to require additional security, reduction of security, change or substitution of sureties, payment of discharge thereof, or any other matter affecting said security. If the court finds that the amount of the deposit or bond in excess of the amount claimed in the claim of lien is insufficient to pay the lienor’s attorney’s fees and court costs incurred in the action to enforce the lien, the court must increase the amount of the cash deposit or lien transfer bond. Nothing in this section shall be construed to vest exclusive jurisdiction in the circuit courts over transfer bond claims for nonpayment of an amount within the monetary jurisdiction of the county courts.
Read the court decisionRead the full story...Reprinted courtesy of